CPWD Analysis of Rates · Repairs to Buildings
Renewing bottom rail and/or top runner of collapsible gate including making good all damages and applying priming coat of zinc chromate yellow primer of approved brand and manufacturer
- Item number
- 14.21
- Analysis basis
- Detail of cost for gate of size 1.52x2.4 m
- Priced inputs
- 10
- Derived rate
- ₹298.85 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.21 — Renewing bottom rail and/or top runner of collapsible gate including making good all damages and applying priming coat of zinc chromate yellow primer of approved brand and manufacturer — is derived from 10 priced inputs for gate of and works out to ₹298.85 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- (weight 11.55 kg)
- M.S. Tee 40x40x6 mm
- Top rail = 1.725 m
- Bottom rail = 1.570 m
- Total = 3.295 m say 3.30 m @ 3.5 kg/m
- = 11.55 kg
- Total = 12.705 kg = 0.1270 q say 0.13 q
- Taking out collapsible gate including frame
- Refixing of collapsible gate including mending
- good the demaged floor, wall etc.frame
- Cement concrete 1:3:6 (1 cement : 3 coarse
- sand : 6 graded stone aggregate 20 mm
- nominal size)
- Priming coat on Tees 0.16x3.3 = 0.53 sqm
- Labour for fixing the gate
- Add 10% wastage = 1.155 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1007 | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterial | quintal | 0.13 | 5,965.00 | 775.45 |
| (Rate as per item no 15.12.2 of SH Dismantling and Demolishing)Rate as per item 15.12.2Sub-analysis | each | 1 | 502.75 | 502.75 | |
| Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysis | cum | 0.03 | 9,311.40 | 279.34 | |
| Cement mortar 1 : 6 (1 cement : 6 fine sand) (Rate as per item No 3.6)Rate as per item 3.6Sub-analysis | cum | 0.01 | 3,038.50 | 30.39 | |
| 9999 | Cement concrete 1:2:4 filled in chase cutMaterial | L.S. | 24.18 | 2.27 | 54.89 |
| 9999 | Disposal of mulbaMaterial | L.S. | 1.82 | 2.27 | 4.13 |
| Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysis | sqm | 0.53 | 67.40 | 35.72 | |
| 0155 | Mason (average)Labour | day | 0.5 | 857.00 | 428.50 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
| 9999 | SundriesMaterial | L.S. | 2.6 | 2.27 | 5.90 |
- TOTAL
- 2,669.07
- Add 1 % Water charges on “W-A”
- 18.51
- TOTAL
- 2,687.58
- Add GST on “X-A” (multiplying factor 0.2127)
- 397.70
- TOTAL
- 3,085.28
- Add 15% CPOH on “Y-A”
- 340.12
- TOTAL
- 3,425.40
- Add Cess @ 1% on “Z-A”
- 26.08
- Cost of 11.55 kg
- 3,451.48
- Cost of 1.00 kg
- 298.83
- Say
- 298.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1058. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.