Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the same with necessary clamps, nuts and bolts/welding and erection etc. complete

Wheel 50 mm dia and below
Item number
14.22.1
Analysis basis
10 nos
Priced inputs
14
Derived rate
₹123.70/ NOS
D-01/RATE ANALYSISITEM 14.22.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.22.1 (Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the same with necessary clamps, nuts and bolts/welding and erection etc. complete Wheel 50 mm dia and below) is derived from 14 priced inputs for 10 nos and works out to ₹123.70 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Weight of 10 nos wheels
  • 10x[3.14x{(40/2)x(40/2)}x40]x0.0078 = 3.92
  • kg
  • Weight of 10 nos clamps 6 mm thick =10x
  • lenth of clamp =10x0.17m @ 1.90kg/m =3.23
  • kg
  • Weight of 10 nos 10 mm dia. Bolts, 10 cm
  • long 10x0.10m = 1m @ 0.618 kg/m = 0.62 kg.
  • Total = 7.77 kg say 8 kg
  • Labour for dismantling :
  • Renewing the wheels with clamps :length = 10x(2x4) = 80cm
  • Labour for cutting, assembling and errection
  • charges
  • Priming coat = 10x2(0.06+0.006)x0.17m =
  • 0.22 sqm on (40x40x6) Tees = 0.172x3.30 =
  • 0.57 sqm, Total = 0.79 sqm
  • Add 5% wastage = 0.16 kg
ANALYSIS OF RATES · ITEM 14.22.1DETAIL OF COST FOR 10 NOS WHEELS OF 40 MM DIA
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0103LABBlacksmith 2nd classday0.01816.008.16
0100LABBandhaniday0.01816.008.16
0114LABBeldarday0.02736.0014.72
9999MATSundriesL.S.0.392.270.89
7441MATWheel 40 mm dia. 40 mm wideeach1025.00250.00
1008MAT10 nos clamps out of M.S. flat 40x6 mm, 170 mm long = 10x0.17m = 1.70m @ 1.9 kg/m = 3.23 kgFlats up to 10 mm in thickness———
OTHERTotal = 3.39 kg say 3.50 kg Flats upto 10 mm in thicknessquintal0.0355,450.00190.75
1034MATM.S. bolt/pin 10 mm dia 10 cm long 10 Nos 10x0.06 = 0.6 kg = 0.006 q Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthquintal0.0065,200.0031.20
1215MATWelding by electric plantcm802.50200.00
0102LABBlacksmith 1st classday0.03897.0026.91
0100LABBandhaniday0.02816.0016.32
0114LABBeldarday0.11736.0080.96
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm0.7967.4053.25
9999MATSundriesL.S.1.692.273.84
BUILD-UP TO RATE
TOTAL
885.16
Add 1 % Water charges on “W-A”
+8.32
TOTAL
893.48
Add GST on “X-A” (multiplying factor 0.2127)
+178.72
TOTAL
1,072.20
Add 15% CPOH on “Y-A”
+152.84
TOTAL
1,225.04
Add Cess @ 1% on “Z-A”
+11.72
Cost of 10 nos wheels
1,236.76
Cost per wheel
123.68
SAY
₹123.70
D-02/SOURCEPRINTED PAGE 1059
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1059

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1059. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.