CPWD Analysis of Rates · Repairs to Buildings

Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the same with necessary clamps, nuts and bolts/welding and erection etc. complete

Wheel 50 mm dia and below

Item number
14.22.1
Analysis basis
Detail of cost for 10 nos wheels of 40 mm dia.
Priced inputs
14
Derived rate
123.70 / nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.22.1 Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the same with necessary clamps, nuts and bolts/welding and erection etc. complete Wheel 50 mm dia and below — is derived from 14 priced inputs for 10 nos and works out to ₹123.70 each after water charges, GST, CPOH and cess. The full build-up is below.

  • Weight of 10 nos wheels
  • 10x[3.14x{(40/2)x(40/2)}x40]x0.0078 = 3.92
  • kg
  • Weight of 10 nos clamps 6 mm thick =10x
  • lenth of clamp =10x0.17m @ 1.90kg/m =3.23
  • kg
  • Weight of 10 nos 10 mm dia. Bolts, 10 cm
  • long 10x0.10m = 1m @ 0.618 kg/m = 0.62 kg.
  • Total = 7.77 kg say 8 kg
  • Labour for dismantling :
  • Renewing the wheels with clamps :length = 10x(2x4) = 80cm
  • Labour for cutting, assembling and errection
  • charges
  • Priming coat = 10x2(0.06+0.006)x0.17m =
  • 0.22 sqm on (40x40x6) Tees = 0.172x3.30 =
  • 0.57 sqm, Total = 0.79 sqm
  • Add 5% wastage = 0.16 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
0103Blacksmith 2nd classLabourday0.01816.008.16
0100BandhaniLabourday0.01816.008.16
0114BeldarLabourday0.02736.0014.72
9999SundriesMaterialL.S.0.392.270.89
7441Wheel 40 mm dia. 40 mm wideMaterialeach1025.00250.00
100810 nos clamps out of M.S. flat 40x6 mm, 170 mm long = 10x0.17m = 1.70m @ 1.9 kg/m = 3.23 kgFlats up to 10 mm in thicknessMaterialNaNNaNNaN
Total = 3.39 kg say 3.50 kg Flats upto 10 mm in thicknessOtherquintal0.0355,450.00190.75
1034M.S. bolt/pin 10 mm dia 10 cm long 10 Nos 10x0.06 = 0.6 kg = 0.006 q Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterialquintal0.0065,200.0031.20
1215Welding by electric plantMaterialcm802.50200.00
0102Blacksmith 1st classLabourday0.03897.0026.91
0100BandhaniLabourday0.02816.0016.32
0114BeldarLabourday0.11736.0080.96
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm0.7967.4053.25
9999SundriesMaterialL.S.1.692.273.84
TOTAL
885.16
Add 1 % Water charges on “W-A”
8.32
TOTAL
893.48
Add GST on “X-A” (multiplying factor 0.2127)
178.72
TOTAL
1,072.20
Add 15% CPOH on “Y-A”
152.84
TOTAL
1,225.04
Add Cess @ 1% on “Z-A”
11.72
Cost of 10 nos wheels
1,236.76
Cost per wheel
123.68
Say
123.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1059. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.