CPWD Analysis of Rates · Repairs to Buildings
Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the same with necessary clamps, nuts and bolts/welding and erection etc. complete
Wheel 50 mm dia and below
- Item number
- 14.22.1
- Analysis basis
- Detail of cost for 10 nos wheels of 40 mm dia.
- Priced inputs
- 14
- Derived rate
- ₹123.70 / nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.22.1 — Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the same with necessary clamps, nuts and bolts/welding and erection etc. complete Wheel 50 mm dia and below — is derived from 14 priced inputs for 10 nos and works out to ₹123.70 each after water charges, GST, CPOH and cess. The full build-up is below.
- Weight of 10 nos wheels
- 10x[3.14x{(40/2)x(40/2)}x40]x0.0078 = 3.92
- kg
- Weight of 10 nos clamps 6 mm thick =10x
- lenth of clamp =10x0.17m @ 1.90kg/m =3.23
- kg
- Weight of 10 nos 10 mm dia. Bolts, 10 cm
- long 10x0.10m = 1m @ 0.618 kg/m = 0.62 kg.
- Total = 7.77 kg say 8 kg
- Labour for dismantling :
- Renewing the wheels with clamps :length = 10x(2x4) = 80cm
- Labour for cutting, assembling and errection
- charges
- Priming coat = 10x2(0.06+0.006)x0.17m =
- 0.22 sqm on (40x40x6) Tees = 0.172x3.30 =
- 0.57 sqm, Total = 0.79 sqm
- Add 5% wastage = 0.16 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0103 | Blacksmith 2nd classLabour | day | 0.01 | 816.00 | 8.16 |
| 0100 | BandhaniLabour | day | 0.01 | 816.00 | 8.16 |
| 0114 | BeldarLabour | day | 0.02 | 736.00 | 14.72 |
| 9999 | SundriesMaterial | L.S. | 0.39 | 2.27 | 0.89 |
| 7441 | Wheel 40 mm dia. 40 mm wideMaterial | each | 10 | 25.00 | 250.00 |
| 1008 | 10 nos clamps out of M.S. flat 40x6 mm, 170 mm long = 10x0.17m = 1.70m @ 1.9 kg/m = 3.23 kgFlats up to 10 mm in thicknessMaterial | NaN | NaN | NaN | |
| Total = 3.39 kg say 3.50 kg Flats upto 10 mm in thicknessOther | quintal | 0.035 | 5,450.00 | 190.75 | |
| 1034 | M.S. bolt/pin 10 mm dia 10 cm long 10 Nos 10x0.06 = 0.6 kg = 0.006 q Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterial | quintal | 0.006 | 5,200.00 | 31.20 |
| 1215 | Welding by electric plantMaterial | cm | 80 | 2.50 | 200.00 |
| 0102 | Blacksmith 1st classLabour | day | 0.03 | 897.00 | 26.91 |
| 0100 | BandhaniLabour | day | 0.02 | 816.00 | 16.32 |
| 0114 | BeldarLabour | day | 0.11 | 736.00 | 80.96 |
| Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysis | sqm | 0.79 | 67.40 | 53.25 | |
| 9999 | SundriesMaterial | L.S. | 1.69 | 2.27 | 3.84 |
- TOTAL
- 885.16
- Add 1 % Water charges on “W-A”
- 8.32
- TOTAL
- 893.48
- Add GST on “X-A” (multiplying factor 0.2127)
- 178.72
- TOTAL
- 1,072.20
- Add 15% CPOH on “Y-A”
- 152.84
- TOTAL
- 1,225.04
- Add Cess @ 1% on “Z-A”
- 11.72
- Cost of 10 nos wheels
- 1,236.76
- Cost per wheel
- 123.68
- Say
- 123.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1059. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.