Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing materials to any distance within compound and stacking
- Item number
- 14.19
- Analysis basis
- 30 mtrs
- Priced inputs
- 3
- Derived rate
- ₹5.40/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.19 (Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing materials to any distance within compound and stacking) is derived from 3 priced inputs for 30 mtrs and works out to ₹5.40 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- M.S. Flats 40x6mm @ 1.9kg./m = 30x1.9 = 57
- kg. (A)
- J’ hook bolts @ 30cm centre to centre = 101
- Nos. x 0.15 m = 15.15 m @ 0.40kg./ m =
- 6.06kg (B)
- Total (A+B) = 63.06 kg Say 63 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0103 | LAB | Blacksmith 2nd class | day | 0.09 | 816.00 | 73.44 |
| 0100 | LAB | Bandhani | day | 0.06 | 816.00 | 48.96 |
| 0114 | LAB | Beldar | day | 0.16 | 736.00 | 117.76 |
- TOTAL
- 240.16
- Add 1 % Water charges on “W”
- +2.40
- TOTAL
- 242.56
- Add GST on “X” (multiplying factor 0.2127)
- +51.59
- TOTAL
- 294.15
- Add 15% CPOH on “Y”
- +44.12
- TOTAL
- 338.27
- Add Cess @ 1% on “Z”
- +3.38
- Cost for 63 kg.
- 341.65
- Cost of 1.00 kg
- 5.42
- SAY
- ₹5.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1057
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1057. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.