Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement for flat tile bricks on top of mud phaska
- Item number
- 14.18.2
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹139.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.18.2 (Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement for flat tile bricks on top of mud phaska : With modular brick tiles) is derived from 6 priced inputs for 10 sqm and works out to ₹139.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 3 (1 cement : 3 fine sand)
- 2% of wt. of cement
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3 | cum | 0.017 | 4,379.05 | 74.44 | |
| 1213 | MAT | Water proofing materials | kilogram | 0.173 | 45.00 | 7.79 |
| 0115 | LAB | Coolie | day | 0.36 | 736.00 | 264.96 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.36 | 816.00 | 293.76 |
| 0101 | LAB | Bhisti | day | 0.36 | 816.00 | 293.76 |
| 9999 | MAT | Sundries | L.S. | 18.85 | 2.27 | 42.79 |
- TOTAL
- 977.50
- Add 1 % Water charges on “W”
- +9.78
- TOTAL
- 987.28
- Add GST on “X” (multiplying factor 0.2127)
- +209.99
- TOTAL
- 1,197.27
- Add 15% CPOH on “Y”
- +179.59
- TOTAL
- 1,376.86
- Add Cess @ 1% on “Z”
- +13.77
- Cost of 10.00 sqm
- 1,390.63
- Cost of 1.00 sqm
- 139.06
- SAY
- ₹139.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1056
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1056. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.