Skip to main content
R/DAR 2023

Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement for flat tile bricks on top of mud phaska

With F.P.S. brick tiles
Item number
14.18.1
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹137.70/ SQM
D-01/RATE ANALYSISITEM 14.18.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.18.1 (Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement for flat tile bricks on top of mud phaska : With F.P.S. brick tiles) is derived from 6 priced inputs for 10 sqm and works out to ₹137.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 3 (1 cement : 3 fine sand)
  • 2% of wt. of cement
ANALYSIS OF RATES · ITEM 14.18.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.0154,379.0565.69
1213MATWater proofing materialskilogram0.15345.006.89
0115LABCoolieday0.36736.00264.96
0124LABMason 2nd classMason 2nd classday0.36816.00293.76
0101LABBhistiday0.36816.00293.76
9999MATSundriesL.S.18.852.2742.79
BUILD-UP TO RATE
TOTAL
967.85
Add 1 % Water charges on “W”
+9.68
TOTAL
977.53
Add GST on “X” (multiplying factor 0.2127)
+207.92
TOTAL
1,185.45
Add 15% CPOH on “Y”
+177.82
TOTAL
1,363.27
Add Cess @ 1% on “Z”
+13.63
Cost of 10.00 sqm
1,376.90
Cost of 1.00 sqm
137.69
SAY
₹137.70
D-02/SOURCEPRINTED PAGE 1056
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1056

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1056. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.