Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge
- Item number
- 14.17
- Analysis basis
- 10 sqm
- Priced inputs
- 4
- Derived rate
- ₹72.45/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.17 (Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge) is derived from 4 priced inputs for 10 sqm and works out to ₹72.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 0.53 | 736.00 | 390.08 |
| 0115 | LAB | Coolie | day | 0.08 | 736.00 | 58.88 |
| 0101 | LAB | Bhisti | day | 0.07 | 816.00 | 57.12 |
| 9999 | MAT | Sundries | L.S. | 1.43 | 2.27 | 3.25 |
- TOTAL
- 509.33
- Add 1 % Water charges on “W”
- +5.09
- TOTAL
- 514.42
- Add GST on “X” (multiplying factor 0.2127)
- +109.42
- TOTAL
- 623.84
- Add 15% CPOH on “Y”
- +93.58
- TOTAL
- 717.42
- Add Cess @ 1% on “Z”
- +7.17
- Cost of 10.00 sqm
- 724.59
- Cost of 1.00 sqm
- 72.46
- SAY
- ₹72.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1055
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1055. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.