CPWD Analysis of Rates · Repairs to Buildings

Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge

Item number
14.17
Analysis basis
Detail of cost for 10 sqm
Priced inputs
4
Derived rate
72.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.17 Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge — is derived from 4 priced inputs for 10 sqm and works out to ₹72.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.53736.00390.08
0115CoolieLabourday0.08736.0058.88
0101BhistiLabourday0.07816.0057.12
9999SundriesMaterialL.S.1.432.273.25
TOTAL
509.33
Add 1 % Water charges on “W”
5.09
TOTAL
514.42
Add GST on “X” (multiplying factor 0.2127)
109.42
TOTAL
623.84
Add 15% CPOH on “Y”
93.58
TOTAL
717.42
Add Cess @ 1% on “Z”
7.17
Cost of 10.00 sqm
724.59
Cost of 1.00 sqm
72.46
Say
72.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1055. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate