CPWD Analysis of Rates · Repairs to Buildings

Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Above 4.00 metres and upto 5.00 metres length

Hollock wood beams

Item number
14.16.2.2
Analysis basis
Details of cost for 3750 cudm or 3.75 cum
Priced inputs
19
Derived rate
72,987.25 / cudm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.16.2.2 Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Above 4.00 metres and upto 5.00 metres length Hollock wood beams — is derived from 19 priced inputs for 3750 cudm and works out to ₹72,987.25 per cudm after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider 10 beam i.e. 3750 cudm.
  • 10x0.25 x 0.30m x 5.0m (long) = 3.75 cum
  • 3830cudm
  • (i) Propping the roof
  • 100x100mm Hollock wood battens 1.00
  • metre long= 60 nos. x1.0x0.1x0.1 = 600
  • cudm.
  • These materials can be used for 16 times
  • hence qty for one operation 1/16= 600/16 =
  • 37.5 cudm
  • (ii) Taking out the existing beams etc
  • (iii) Renewal
  • Materials and Labour
  • Painting with oil preservative=10(5.00x1.1 +
  • 2.0x0.25x0.30) = 10x(5.5 + 0.15) = 56.5 sqm
  • @ 1 litre/10sqm = 5.65 litre
  • Add wastage @ 2% (0.08 cum) = 3.83 cum =
CodeInputUnitQuantityRate (INR)Amount (INR)
2466Hollock wood in scantlingMaterial10 cudm3.75366.001,372.50
0112Carpenter 2nd clasCarpenter 2nd classLabourday2.5816.002,040.00
0114BeldarLabourday2.5736.001,840.00
0155Mason (average)Labourday2.5857.002,142.50
100 BandhaniOtherday6.3816.005,140.80
0114BeldarLabourday5736.003,680.00
2466Hollock wood in scantlingMaterial10 cudm383366.001,40,178.00
0112Carpenter 2nd clasCarpenter 2nd classLabourday10816.008,160.00
0100BandhaniLabourday10816.008,160.00
0114BeldarLabourday20736.0014,720.00
0859Oil type wood preservativeMateriallitre5.65130.00734.50
0131PainterLabourday0.8816.00652.80
0115CoolieLabourday0.8736.00588.80
9999SundriesMaterialL.S.2.62.275.90
9977CarriageMaterialL.S.23.42.2753.12
9999BrushesMaterialL.S.22.12.2750.17
9999Making good the holesMaterialL.S.206.72.27469.21
9999SundriesMaterialL.S.331.52.27752.51
0302Safeda ballies 125 mm diameterMaterialmetre37.544.001,650.00
Total
1,92,390.81
Add 1 % Water charges on “W”
1,923.91
TOTAL
1,94,314.72
Add GST on “X” (multiplying factor 0.2127)
41,330.74
TOTAL
2,35,645.46
Add 15% CPOH on “Y”
35,346.82
TOTAL
2,70,992.28
Add Cess @ 1% on “Z”
2,709.92
Cost of 3.75 cum
2,73,702.20
Cost for 1 cum
72,987.25
Say
72,987.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1054. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.