Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Above 4.00 metres and upto 5.00 metres length

Sal wood beams
Item number
14.16.2.1
Analysis basis
3750 cudm
Priced inputs
19
Derived rate
₹1,07,320.00/ CUM
D-01/RATE ANALYSISITEM 14.16.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.16.2.1 (Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Above 4.00 metres and upto 5.00 metres length Sal wood beams) is derived from 19 priced inputs for 3750 cudm and works out to ₹1,07,320.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider 10 beam i.e. 3750 cudm.
  • 10x0.25 x 0.30m x 5.0m (long) = 3.75 cum
  • = 3.83 cum = 3830cudm
  • (i) Propping the roof
  • 100x100mm salwood battens 1.0 metre long
  • 60 nos. x1.0x0.1x0.1 = 600 cudm.
  • These materials can be used for 16 times
  • hence qty for one operation 1/16= 600/16 =
  • 37.50 cudm
  • (ii) Taking out the existing beams etc.
  • (iii) Renewal
  • Materials and Labour
  • Painting with oil preservative=
  • 10(5.00x1.1 + 2.0x0.25x0.30) = 10x(5.5 +
  • 0.15) = 56.5 sqm @ 1 litre/10sqm = 5.65 litre
  • Add wastage @ 2% (0.08 cum)
ANALYSIS OF RATES · ITEM 14.16.2.1DETAILS OF COST FOR 3750 CUDM OR 3.75 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1199MATSal wood in scantling10 cudm3.75600.002,250.00
0112LABCarpenter 2nd classday2.5816.002,040.00
0114LABBeldarday2.5736.001,840.00
0155LABMason (average)day2.5857.002,142.50
0100LABBandhaniday6.3816.005,140.80
0114LABBeldarday5736.003,680.00
1199MATSal wood in scantling10 cudm383600.002,29,800.00
0112LABCarpenter 2nd classday10816.008,160.00
0100LABBandhaniday10816.008,160.00
0114LABBeldarday20736.0014,720.00
0859MATOil type wood preservativelitre5.65130.00734.50
0131LABPainterday0.8816.00652.80
0115LABCoolieday0.8736.00588.80
9999MATSundriesL.S.2.62.275.90
9977MATCarriageL.S.23.42.2753.12
9999MATBrushesL.S.22.12.2750.17
9999MATMaking good the holesL.S.206.72.27469.21
9999MATSundriesL.S.331.52.27752.51
0302MATSafeda ballies 125 mm diametermetre37.544.001,650.00
BUILD-UP TO RATE
TOTAL
2,82,890.31
Add 1 % Water charges on “W”
+2,828.90
TOTAL
2,85,719.21
Add GST on “X” (multiplying factor 0.2127)
+60,772.48
TOTAL
3,46,491.69
Add 15% CPOH on “Y”
+51,973.75
TOTAL
3,98,465.44
Add Cess @ 1% on “Z”
+3,984.65
Cost of 3.75 Cum
4,02,450.09
Cost of 1.00 cum
1,07,320.02
SAY
₹1,07,320.00
D-02/SOURCEPRINTED PAGE 1053
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1053

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1053. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.