CPWD Analysis of Rates · Repairs to Buildings
Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Not exceeding 4.00 metres in length
Hollock wood beams
- Item number
- 14.16.1.2
- Analysis basis
- Details of cost for 3000 cudm or 3 cum
- Priced inputs
- 19
- Derived rate
- ₹70,271.70 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.16.1.2 — Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Not exceeding 4.00 metres in length Hollock wood beams — is derived from 19 priced inputs for 3000 cudm and works out to ₹70,271.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Consider 10 beam
- 10x0.25 x 0.30m x 4.0m (long) = 3 cum
- =3060cudm
- (I) Propping the roof
- 100x100mm hollock wood battens 1.0 metre
- long = 50 nos.x1.0x0.1x0.1 =0.5cum = 500
- cudm.
- These materials can be used for 16 times
- hence qty for one operation 1/16 = 500/16=
- 31.25 cudm
- (ii) Taking out the existing beams etc.
- (iii) Renewal
- Materials and Labour
- Painting with oil preservative=
- 10x[(4x1.1) + (2.0x0.25x0.30)] =10(4.4 +
- 0.15)= 45.5 sqm @ 1 litre/10sqm = 4.55 litre
- Add wastage @ 2% (0.06 cum)= 3.06 cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2466 | Hollock wood in scantlingMaterial | 10 cudm | 3.125 | 366.00 | 1,143.75 |
| 0112 | Carpenter 2nd classLabour | day | 2.5 | 816.00 | 2,040.00 |
| 0114 | BeldarLabour | day | 2.5 | 736.00 | 1,840.00 |
| 0155 | Mason (average)Labour | day | 1.3 | 857.00 | 1,114.10 |
| 0100 | BandhaniLabour | day | 5 | 816.00 | 4,080.00 |
| 0114 | BeldarLabour | day | 3.3 | 736.00 | 2,428.80 |
| 2466 | Hollock wood in scantlingMaterial | 10 cudm | 306 | 366.00 | 1,11,996.00 |
| 0112 | Carpenter 2nd classLabour | day | 10 | 816.00 | 8,160.00 |
| 0100 | BandhaniLabour | day | 5 | 816.00 | 4,080.00 |
| 0114 | BeldarLabour | day | 10 | 736.00 | 7,360.00 |
| 0859 | Oil type wood preservativeMaterial | litre | 4.55 | 130.00 | 591.50 |
| 0131 | PainterLabour | day | 0.7 | 816.00 | 571.20 |
| 0115 | CoolieLabour | day | 0.7 | 736.00 | 515.20 |
| 9999 | SundriesMaterial | L.S. | 1.3 | 2.27 | 2.95 |
| 9977 | CarriageMaterial | L.S. | 18.2 | 2.27 | 41.31 |
| 9999 | BrushesMaterial | L.S. | 18.2 | 2.27 | 41.31 |
| 9999 | Making good the holesMaterial | L.S. | 206.7 | 2.27 | 469.21 |
| 9999 | SundriesMaterial | L.S. | 269.1 | 2.27 | 610.86 |
| 0302 | Safeda ballies 125 mm diameterMaterial | metre | 25 | 44.00 | 1,100.00 |
- TOTAL
- 1,48,186.19
- Add 1 % Water charges on “W”
- 1,481.86
- TOTAL
- 1,49,668.05
- Add GST on “X” (multiplying factor 0.2127)
- 31,834.39
- TOTAL
- 1,81,502.44
- Add 15% CPOH on “Y”
- 27,225.37
- TOTAL
- 2,08,727.81
- Add Cess @ 1% on “Z”
- 2,087.28
- Cost of 3.00 Cum
- 2,10,815.09
- Cost of 1.00 cum
- 70,271.70
- Say
- 70,271.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1052. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.