CPWD Analysis of Rates · Repairs to Buildings
Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge
Sal wood battens
- Item number
- 14.15.1
- Analysis basis
- Details of cost for 10 battens i.e. 300 cudm
- Priced inputs
- 11
- Derived rate
- ₹99,120.65 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.15.1 — Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Sal wood battens — is derived from 11 priced inputs for 10 battens and works out to ₹99,120.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- 3 metres long of 100x100mm
- 10x3x0.1x0.1 = 0.3cum =300cudm
- Taking out the existing battens and refixing
- new one including supporting the roof
- Add wastage @ 2%= 6 cudm, Total = 306 cudm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1199 | Sal wood in scantlingMaterial | 10 cudm | 30.6 | 600.00 | 18,360.00 |
| 0112 | Carpenter 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | Disposal of mulbaMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| 9999 | Making good the holes including sundriesMaterial | L.S. | 80.73 | 2.27 | 183.26 |
| 0859 | Oil type wood preservativeMaterial | litre | 1.22 | 130.00 | 158.60 |
| 0131 | PainterLabour | day | 0.183 | 816.00 | 149.33 |
| 0115 | CoolieLabour | day | 0.183 | 736.00 | 134.69 |
| 9977 | CarriageMaterial | L.S. | 0.78 | 2.27 | 1.77 |
| 9999 | BrushesMaterial | L.S. | 5.07 | 2.27 | 11.51 |
| 9999 | SundriesMaterial | L.S. | 4.81 | 2.27 | 10.92 |
- TOTAL
- 20,902.18
- Add 1 % Water charges on “W”
- 209.02
- TOTAL
- 21,111.20
- Add GST on “X” (multiplying factor 0.2127)
- 4,490.35
- TOTAL
- 25,601.55
- Add 15% CPOH on “Y”
- 3,840.23
- TOTAL
- 29,441.78
- Add Cess @ 1% on “Z”
- 294.42
- Cost of 300 Cudm
- 29,736.20
- Cost of 1.00 cum
- 99,120.67
- Say
- 99,120.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1051. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.