Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge

Sal wood battens

Item number
14.15.1
Analysis basis
Details of cost for 10 battens i.e. 300 cudm
Priced inputs
11
Derived rate
99,120.65 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.15.1 Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Sal wood battens — is derived from 11 priced inputs for 10 battens and works out to ₹99,120.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • 3 metres long of 100x100mm
  • 10x3x0.1x0.1 = 0.3cum =300cudm
  • Taking out the existing battens and refixing
  • new one including supporting the roof
  • Add wastage @ 2%= 6 cudm, Total = 306 cudm
CodeInputUnitQuantityRate (INR)Amount (INR)
1199Sal wood in scantlingMaterial10 cudm30.6600.0018,360.00
0112Carpenter 2nd classLabourday0.5816.00408.00
0114BeldarLabourday2736.001,472.00
9999Disposal of mulbaMaterialL.S.5.332.2712.10
9999Making good the holes including sundriesMaterialL.S.80.732.27183.26
0859Oil type wood preservativeMateriallitre1.22130.00158.60
0131PainterLabourday0.183816.00149.33
0115CoolieLabourday0.183736.00134.69
9977CarriageMaterialL.S.0.782.271.77
9999BrushesMaterialL.S.5.072.2711.51
9999SundriesMaterialL.S.4.812.2710.92
TOTAL
20,902.18
Add 1 % Water charges on “W”
209.02
TOTAL
21,111.20
Add GST on “X” (multiplying factor 0.2127)
4,490.35
TOTAL
25,601.55
Add 15% CPOH on “Y”
3,840.23
TOTAL
29,441.78
Add Cess @ 1% on “Z”
294.42
Cost of 300 Cudm
29,736.20
Cost of 1.00 cum
99,120.67
Say
99,120.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1051. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.