Replacing sand stone slabs in roofing, laid in cement mortar 1:4 (1 cement : 4 coarse sand), including necessary repairs and cement pointing with same mortar complete, including disposal of rubbish to dumping ground, all complete as per direction of Engineer-in-Charge
- Item number
- 14.14.1
- Analysis basis
- 100 sqm
- Priced inputs
- 13
- Derived rate
- ₹1,365.85/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.14.1 (Replacing sand stone slabs in roofing, laid in cement mortar 1:4 (1 cement : 4 coarse sand), including necessary repairs and cement pointing with same mortar complete, including disposal of rubbish to dumping ground, all complete as per direction of Engineer-in-Charge Red/ white sand stone slabs 30 to 50 mm thick) is derived from 13 priced inputs for 100 sqm and works out to ₹1,365.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Dismantling existing stone, slabs roofing
- 10x10 sqmx0.05m = 5 cum.
- Cement mortar 1 : 4 (1 cement : 4 coarse
- sand)
- Cement mortar 1 : 3 (1 cement : 3 fine sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 8.85 | 736.00 | 6,513.60 |
| 0115 | LAB | Coolie | day | 3.75 | 736.00 | 2,760.00 |
| 9999 | MAT | Sundries | L.S. | 40.3 | 2.27 | 91.48 |
| 9999 | MAT | Cleaning the surface including necessary repairs | L.S. | 404.3 | 2.27 | 917.76 |
| 1174 | MAT | Red sand stone slab 45 mm and 50 mm thick (un-dressed)Red sand stone slab 45 mm to 50 mm thick (un-dressed) | sqm | 110 | 340.00 | 37,400.00 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.105 | 4,211.70 | 442.23 | |
| SUB | Rate as per Item Number 3.3 of SH: MortarsRate as per item 3.3 | cum | 0.075 | 4,379.05 | 328.43 | |
| 0155 | LAB | Mason (average) | day | 16.9 | 857.00 | 14,483.30 |
| 0100 | LAB | Bandhani | day | 20.3 | 816.00 | 16,564.80 |
| 0115 | LAB | Coolie | day | 16.9 | 736.00 | 12,438.40 |
| 0101 | LAB | Bhisti | day | 3.4 | 816.00 | 2,774.40 |
| 9999 | MAT | Sundries | L.S. | 161.2 | 2.27 | 365.92 |
| 2264 | MAT | Carriage of Rubbish | cum | 5 | 185.55 | 927.75 |
- TOTAL
- 96,008.07
- Add 1 % Water charges on “W”
- +960.08
- TOTAL
- 96,968.15
- Add GST on “X” (multiplying factor 0.2127)
- +20,625.13
- TOTAL
- 1,17,593.28
- Add 15% CPOH on “Y”
- +17,638.99
- TOTAL
- 1,35,232.27
- Add Cess @ 1% on “Z”
- +1,352.32
- Cost of 100 sqm
- 1,36,584.59
- Cost of 1.00 sqm
- 1,365.85
- SAY
- ₹1,365.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1050
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1050. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate