Replacing sand stone slabs in roofing, laid in cement mortar 1:4 (1 cement : 4 coarse sand), including necessary repairs and cement pointing with same mortar complete, including disposal of rubbish to dumping ground, all complete as per direction of Engineer-in-Charge

Red/ white sand stone slabs 30 to 50 mm thick
Item number
14.14.1
Analysis basis
100 sqm
Priced inputs
13
Derived rate
₹1,365.85/ SQM
D-01/RATE ANALYSISITEM 14.14.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.14.1 (Replacing sand stone slabs in roofing, laid in cement mortar 1:4 (1 cement : 4 coarse sand), including necessary repairs and cement pointing with same mortar complete, including disposal of rubbish to dumping ground, all complete as per direction of Engineer-in-Charge Red/ white sand stone slabs 30 to 50 mm thick) is derived from 13 priced inputs for 100 sqm and works out to ₹1,365.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Dismantling existing stone, slabs roofing
  • 10x10 sqmx0.05m = 5 cum.
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Cement mortar 1 : 3 (1 cement : 3 fine sand)
ANALYSIS OF RATES · ITEM 14.14.1DETAIL OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday8.85736.006,513.60
0115LABCoolieday3.75736.002,760.00
9999MATSundriesL.S.40.32.2791.48
9999MATCleaning the surface including necessary repairsL.S.404.32.27917.76
1174MATRed sand stone slab 45 mm and 50 mm thick (un-dressed)Red sand stone slab 45 mm to 50 mm thick (un-dressed)sqm110340.0037,400.00
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.1054,211.70442.23
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.0754,379.05328.43
0155LABMason (average)day16.9857.0014,483.30
0100LABBandhaniday20.3816.0016,564.80
0115LABCoolieday16.9736.0012,438.40
0101LABBhistiday3.4816.002,774.40
9999MATSundriesL.S.161.22.27365.92
2264MATCarriage of Rubbishcum5185.55927.75
BUILD-UP TO RATE
TOTAL
96,008.07
Add 1 % Water charges on “W”
+960.08
TOTAL
96,968.15
Add GST on “X” (multiplying factor 0.2127)
+20,625.13
TOTAL
1,17,593.28
Add 15% CPOH on “Y”
+17,638.99
TOTAL
1,35,232.27
Add Cess @ 1% on “Z”
+1,352.32
Cost of 100 sqm
1,36,584.59
Cost of 1.00 sqm
1,365.85
SAY
₹1,365.85
D-02/SOURCEPRINTED PAGE 1050
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1050

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1050. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.