Regrading terracing of mud phaska covered with tiles or brick, in cement mortar by dismantling tiles or bricks, removing mud plaster, preparing the surface of mud phaska to proper slope, relaying mud plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand), including replacing unserviceable tiles or bricks with new ones and disposal of unserviceable material to the dumping ground (the cost of the new tiles or brick excluded), all complete as per direction of Engineer-in-Charge

Item number
14.13
Analysis basis
10 sqm
Priced inputs
13
Derived rate
₹696.05/ SQM
D-01/RATE ANALYSISITEM 14.13

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.13 (Regrading terracing of mud phaska covered with tiles or brick, in cement mortar by dismantling tiles or bricks, removing mud plaster, preparing the surface of mud phaska to proper slope, relaying mud plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand), including replacing unserviceable tiles or bricks with new ones and disposal of unserviceable material to the dumping ground (the cost of the new tiles or brick excluded), all complete as per direction of Engineer-in-Charge) is derived from 13 priced inputs for 10 sqm and works out to ₹696.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) Dismantling tiles/bricks in cement mortar
  • including removing mud plaster and cleaning
  • the tiles/bricks
  • (ii) Preparing the surface, for mud phuska
  • to proper slope, relaying mud plaster gobri
  • leeping.
  • 25mm thick mud plaster including gobri
  • leaping
  • Mud mortar
  • Gobri mortar
  • (iii) relaying tiles/bricks including Cement
  • mortar 1:3 (1 Cement : 3 fine sand) for
  • grouting
ANALYSIS OF RATES · ITEM 14.13DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0155LABMason (average)day0.54857.00462.78
0114LABBeldarday0.54736.00397.44
0155LABMason (average)day0.27857.00231.39
SUBRate as per Item Number 3.18 of SH: MortarsRate as per item 3.18cum0.24940.55225.73
0308MATBhusaquintal0.084530.0044.52
SUBRate as per Item Number 3.18 of SH: MortarsRate as per item 3.18cum0.12940.55112.87
0114LABBeldarday0.25736.00184.00
SUBRate as per item No 3.3 of SH: MortarsRate as per item 3.3cum0.0614,379.05267.12
0155LABMason (average)day1.2857.001,028.40
0114LABBeldarday1.5736.001,104.00
0101LABBhistiday1816.00816.00
9999MATDisposal of mulbaL.S.5.332.2712.10
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
4,892.55
Add 1 % Water charges on “W”
+48.93
TOTAL
4,941.48
Add GST on “X” (multiplying factor 0.2127)
+1,051.05
TOTAL
5,992.53
Add 15% CPOH on “Y”
+898.88
TOTAL
6,891.41
Add Cess @ 1% on “Z”
+68.91
Cost of 10.00 sqm
6,960.32
Cost of 1.00 sqm
696.03
SAY
₹696.05
D-02/SOURCEPRINTED PAGE 1049
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1049

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1049. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.