CPWD Analysis of Rates · Repairs to Buildings
Regrading terracing of mud phaska covered with tiles or brick, in cement mortar by dismantling tiles or bricks, removing mud plaster, preparing the surface of mud phaska to proper slope, relaying mud plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand), including replacing unserviceable tiles or bricks with new ones and disposal of unserviceable material to the dumping ground (the cost of the new tiles or brick excluded), all complete as per direction of Engineer-in-Charge
- Item number
- 14.13
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 13
- Derived rate
- ₹696.05 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.13 — Regrading terracing of mud phaska covered with tiles or brick, in cement mortar by dismantling tiles or bricks, removing mud plaster, preparing the surface of mud phaska to proper slope, relaying mud plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand), including replacing unserviceable tiles or bricks with new ones and disposal of unserviceable material to the dumping ground (the cost of the new tiles or brick excluded), all complete as per direction of Engineer-in-Charge — is derived from 13 priced inputs for 10 sqm and works out to ₹696.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Dismantling tiles/bricks in cement mortar
- including removing mud plaster and cleaning
- the tiles/bricks
- (ii) Preparing the surface, for mud phuska
- to proper slope, relaying mud plaster gobri
- leeping.
- 25mm thick mud plaster including gobri
- leaping
- Mud mortar
- Gobri mortar
- (iii) relaying tiles/bricks including Cement
- mortar 1:3 (1 Cement : 3 fine sand) for
- grouting
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0155 | Mason (average)Labour | day | 0.54 | 857.00 | 462.78 |
| 0114 | BeldarLabour | day | 0.54 | 736.00 | 397.44 |
| 0155 | Mason (average)Labour | day | 0.27 | 857.00 | 231.39 |
| Rate as per Item Number 3.18 of SH: MortarsRate as per item 3.18Sub-analysis | cum | 0.24 | 940.55 | 225.73 | |
| 0308 | BhusaMaterial | quintal | 0.084 | 530.00 | 44.52 |
| Rate as per Item Number 3.18 of SH: MortarsRate as per item 3.18Sub-analysis | cum | 0.12 | 940.55 | 112.87 | |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| Rate as per item No 3.3 of SH: MortarsRate as per item 3.3Sub-analysis | cum | 0.061 | 4,379.05 | 267.12 | |
| 0155 | Mason (average)Labour | day | 1.2 | 857.00 | 1,028.40 |
| 0114 | BeldarLabour | day | 1.5 | 736.00 | 1,104.00 |
| 0101 | BhistiLabour | day | 1 | 816.00 | 816.00 |
| 9999 | Disposal of mulbaMaterial | L.S. | 5.33 | 2.27 | 12.10 |
| 9999 | SundriesMaterial | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 4,892.55
- Add 1 % Water charges on “W”
- 48.93
- TOTAL
- 4,941.48
- Add GST on “X” (multiplying factor 0.2127)
- 1,051.05
- TOTAL
- 5,992.53
- Add 15% CPOH on “Y”
- 898.88
- TOTAL
- 6,891.41
- Add Cess @ 1% on “Z”
- 68.91
- Cost of 10.00 sqm
- 6,960.32
- Cost of 1.00 sqm
- 696.03
- Say
- 696.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1049. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.