CPWD Analysis of Rates · Repairs to Buildings

Providing and fixing 16 mm M.S. Fan clamps of standard shape and size in existing R.C.C. slab, including cutting chase, anchoring clamp to reinforcement bar, including cleaning, refilling, making good the chase with matching concrete, plastering and painting the exposed portion of the clamps complete

Item number
14.12
Analysis basis
Details of cost for 100 Nos. fan clamp.
Priced inputs
7
Derived rate
563.90 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.12 Providing and fixing 16 mm M.S. Fan clamps of standard shape and size in existing R.C.C. slab, including cutting chase, anchoring clamp to reinforcement bar, including cleaning, refilling, making good the chase with matching concrete, plastering and painting the exposed portion of the clamps complete — is derived from 7 priced inputs for 100 Nos and works out to ₹563.90 each after water charges, GST, CPOH and cess. The full build-up is below.

  • M.S.bar 16mm dia = 100x0.40 m (including
  • wastage) @ 1.58 kg/m = 63.2 kg=0.632 q
  • Labour for fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
1003Mild steel round bar above 12 mm diaMaterialquintal0.6325,450.003,444.40
9999Cement concrete 1:2:4 (1 Cement : 2 Coarse sand : 4 graded stone aggregate 20mm nominal size) mortar for rendering or plasteringMaterialL.S.1,3522.273,069.04
9999Painting two or more coats to exposed portion of the clamp including priming coatMaterialL.S.7152.271,623.05
0102Blacksmith 1st classLabourday3897.002,691.00
0124Mason 2nd classMason 2nd classLabourday12816.009,792.00
0114BeldarLabourday25736.0018,400.00
9999SundriesMaterialL.S.2732.27619.71
TOTAL
39,639.20
Add 1 % Water charges on “W”
396.39
TOTAL
40,035.59
Add GST on “X” (multiplying factor 0.2127)
8,515.57
TOTAL
48,551.16
Add 15% CPOH on “Y”
7,282.67
TOTAL
55,833.83
Add Cess @ 1% on “Z”
558.34
Cost of 100 Nos.
56,392.17
Cost of each
563.92
Say
563.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1048. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.