Skip to main content
R/DAR 2023

Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sq.meters and under, including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge

With cement mortar 1:4 (1cement: 4 coarse sand)
Item number
14.1.2
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹560.50/ SQM
D-01/RATE ANALYSISITEM 14.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.1.2 (Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sq.meters and under, including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge With cement mortar 1:4 (1cement: 4 coarse sand)) is derived from 6 priced inputs for 10 sqm and works out to ₹560.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
ANALYSIS OF RATES · ITEM 14.1.2DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.1834,211.70770.74
0155LABMason (average)day1.21857.001,036.97
0115LABCoolieday1.29736.00949.44
0114LABBeldarday0.54736.00397.44
0101LABBhistiday0.92816.00750.72
9999MATScaffolding and sundriesL.S.15.212.2734.53
BUILD-UP TO RATE
TOTAL
3,939.84
Add 1 % Water charges on “W”
+39.40
TOTAL
3,979.24
Add GST on “X” (multiplying factor 0.2127)
+846.38
TOTAL
4,825.62
Add 15% CPOH on “Y”
+723.84
TOTAL
5,549.46
Add Cess @ 1% on “Z”
+55.49
Cost of 10.00 sqm
5,604.95
Cost of 1.00 sqm
560.50
SAY
₹560.50
D-02/SOURCEPRINTED PAGE 1039
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1039

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1039. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.