Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting masonry for holdfasts, embedding hold fasts in cement concrete blocks of size 15 x 10 x 10 cm with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size), painting two coats of approved wood preservative to sides of chowkhats and making good the damages to walls and floors as required complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge

Door chowkhats

Item number
14.2.1
Analysis basis
Detail of cost for 10 Nos.
Priced inputs
20
Derived rate
1,782.55 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.2.1 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting masonry for holdfasts, embedding hold fasts in cement concrete blocks of size 15 x 10 x 10 cm with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size), painting two coats of approved wood preservative to sides of chowkhats and making good the damages to walls and floors as required complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Door chowkhats — is derived from 20 priced inputs for 10 Nos and works out to ₹1,782.55 each after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 6 (1 cement : 6 fine sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.211,425.00299.25
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0721,400.00100.80
0982Coarse sand (zone III)Materialcum0.1411,450.00204.45
0367Portland Cement (OPC-43 grade)Materialtonne0.0665,156.00340.30
0114BeldarLabourday0.27736.00198.72
0115CoolieLabourday0.195736.00143.52
0130MistryLabourday0.084897.0075.35
0123Mason 1st classMason 1st classLabourday0.018897.0016.15
0124Mason 2nd classMason 2nd classLabourday0.018816.0014.69
0128MateLabourday0.012816.009.79
9999ScaffoldingMaterialL.S.14.32.2732.46
9999Hire and running charges of mechanical mixerMaterialL.S.7.82.2717.71
9999SundriesMaterialL.S.3.92.278.85
Rate as per Item Number 3.6 of SH: MortarsRate as per item 3.6Sub-analysiscum0.13,038.50303.85
9999Cement concrete 1:2:4 filled in chase cutMaterialL.S.241.82.27548.89
9999Painting two coats of coaltarMaterialL.S.135.22.27306.90
9999Disposal of mulbaMaterialL.S.18.22.2741.31
0155Mason (average)Labourday5857.004,285.00
0114BeldarLabourday7.5736.005,520.00
9999SundriesMaterialL.S.27.32.2761.97
TOTAL
12,529.96
Add 1 % Water charges on “W”
125.30
TOTAL
12,655.26
Add GST on “X” (multiplying factor 0.2127)
2,691.77
TOTAL
15,347.03
Add 15% CPOH on “Y”
2,302.05
TOTAL
17,649.08
Add Cess @ 1% on “Z”
176.49
Cost of 10 Nos.
17,825.57
Cost of each
1,782.56
Say
1,782.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1040. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.