Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.9
- Analysis basis
- 10 semicircular
- Priced inputs
- 6
- Derived rate
- ₹2,154.35/ SEMICIRCULAR
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.9 (Centering and shuttering including strutting, propping etc. and removal of form for Arches, domes, vaults up to 6 m span) is derived from 6 priced inputs for 10 semicircular and works out to ₹2,154.35 per semicircular after water charges, GST, CPOH and cess. The full build-up is below.
- clear span and 3.6m long.
- Area of centering = 10x(22/7)
- x1.8x3.6=203.7sqm.
- Frame work in 2nd class kail wood for one
- Tie-1x3.6x0.15x0.20 = 0.108cum.
- Struts-3x1.8x0.10x0.10 =0.054cum
- Struts-2x2.55x0.10x0.10=0.051cum.
- Ribs-4x1.38x.075x0.075=0.031cum.
- Total = 0.244 cum.
- Quantity for 10x7 such frames
- 10x7x0.244 = 17.08cum.
- Strips 5cmx2.5cm
- centre to centre
- 10x(5.66/0.075)x0.05x0.025x3.6 = 3.40cum.
- Total= 20.48 cum = 20480 cudm
- Qty taken for cost using once = 20480/8 =
- 2560 cudm
- Safeda ballies 125 mm dia
- 10x7x4x3.6= 1008m
- Qty taken for cost using once = 1008/8 =
- 126m
- G.I. Plain sheet 203.7 sqm = 1160kg. Or 11.6
- quintal
- Qty taken for cost using once =11.6/8 = 1.45
- qtl
- CarriageKail wood = 20.48cum.
- Ballies - 1008x3.142x(0.125) /4= 12.37cum.
- Total = 32.85 cum.
- Qty taken for cost using once ² = 32.85/8 =
- 4.106 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1197 | MAT | Second class kail wood in scantling | cudm 10 | 256 | 260.00 | 66,560.00 |
| 0302 | MAT | Safeda ballies 125 mm diameter | metre | 126 | 44.00 | 5,544.00 |
| 0992 | MAT | Galvanised steel plain sheets | quintal | 1.45 | 6,800.00 | 9,860.00 |
| 0112 | LAB | Carpenter 2nd class | day | 160 | 816.00 | 1,30,560.00 |
| 0114 | LAB | Beldar | day | 130 | 736.00 | 95,680.00 |
| 9999 | MAT | Sundries | L.S. | 117 | 2.27 | 265.59 |
- TOTAL
- 3,08,469.59
- Add 1 % Water charges on “W”
- +3,084.70
- TOTAL
- 3,11,554.29
- Add GST on “X” (multiplying factor 0.2127)
- +66,267.60
- TOTAL
- 3,77,821.89
- Add 15% CPOH on “Y”
- +56,673.28
- TOTAL
- 4,34,495.17
- Add Cess @ 1% on “Z”
- +4,344.95
- Cost of 203.7sqm.
- 4,38,840.12
- Cost per sqm.
- 2,154.35
- SAY
- ₹2,154.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 225
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 225. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.