CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Arches, domes, vaults up to 6 m span

Item number
5.9.9
Analysis basis
Details of cost for 10 semicircular arch 3.6m
Priced inputs
6
Derived rate
2,154.35 / semicircular

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.9 Centering and shuttering including strutting, propping etc. and removal of form for Arches, domes, vaults up to 6 m span — is derived from 6 priced inputs for 10 semicircular and works out to ₹2,154.35 per semicircular after water charges, GST, CPOH and cess. The full build-up is below.

  • clear span and 3.6m long.
  • Area of centering = 10x(22/7)
  • x1.8x3.6=203.7sqm.
  • Frame work in 2nd class kail wood for one
  • Tie-1x3.6x0.15x0.20 = 0.108cum.
  • Struts-3x1.8x0.10x0.10 =0.054cum
  • Struts-2x2.55x0.10x0.10=0.051cum.
  • Ribs-4x1.38x.075x0.075=0.031cum.
  • Total = 0.244 cum.
  • Quantity for 10x7 such frames
  • 10x7x0.244 = 17.08cum.
  • Strips 5cmx2.5cm
  • centre to centre
  • 10x(5.66/0.075)x0.05x0.025x3.6 = 3.40cum.
  • Total= 20.48 cum = 20480 cudm
  • Qty taken for cost using once = 20480/8 =
  • 2560 cudm
  • Safeda ballies 125 mm dia
  • 10x7x4x3.6= 1008m
  • Qty taken for cost using once = 1008/8 =
  • 126m
  • G.I. Plain sheet 203.7 sqm = 1160kg. Or 11.6
  • quintal
  • Qty taken for cost using once =11.6/8 = 1.45
  • qtl
  • CarriageKail wood = 20.48cum.
  • Ballies - 1008x3.142x(0.125) /4= 12.37cum.
  • Total = 32.85 cum.
  • Qty taken for cost using once ² = 32.85/8 =
  • 4.106 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1197Second class kail wood in scantlingMaterialcudm 10256260.0066,560.00
0302Safeda ballies 125 mm diameterMaterialmetre12644.005,544.00
0992Galvanised steel plain sheetsMaterialquintal1.456,800.009,860.00
0112Carpenter 2nd classLabourday160816.001,30,560.00
0114BeldarLabourday130736.0095,680.00
9999SundriesMaterialL.S.1172.27265.59
TOTAL
3,08,469.59
Add 1 % Water charges on “W”
3,084.70
TOTAL
3,11,554.29
Add GST on “X” (multiplying factor 0.2127)
66,267.60
TOTAL
3,77,821.89
Add 15% CPOH on “Y”
56,673.28
TOTAL
4,34,495.17
Add Cess @ 1% on “Z”
4,344.95
Cost of 203.7sqm.
4,38,840.12
Cost per sqm.
2,154.35
Say
2,154.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 225. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.