CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for
Arches, domes, vaults up to 6 m span
- Item number
- 5.9.9
- Analysis basis
- Details of cost for 10 semicircular arch 3.6m
- Priced inputs
- 6
- Derived rate
- ₹2,154.35 / semicircular
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.9 — Centering and shuttering including strutting, propping etc. and removal of form for Arches, domes, vaults up to 6 m span — is derived from 6 priced inputs for 10 semicircular and works out to ₹2,154.35 per semicircular after water charges, GST, CPOH and cess. The full build-up is below.
- clear span and 3.6m long.
- Area of centering = 10x(22/7)
- x1.8x3.6=203.7sqm.
- Frame work in 2nd class kail wood for one
- Tie-1x3.6x0.15x0.20 = 0.108cum.
- Struts-3x1.8x0.10x0.10 =0.054cum
- Struts-2x2.55x0.10x0.10=0.051cum.
- Ribs-4x1.38x.075x0.075=0.031cum.
- Total = 0.244 cum.
- Quantity for 10x7 such frames
- 10x7x0.244 = 17.08cum.
- Strips 5cmx2.5cm
- centre to centre
- 10x(5.66/0.075)x0.05x0.025x3.6 = 3.40cum.
- Total= 20.48 cum = 20480 cudm
- Qty taken for cost using once = 20480/8 =
- 2560 cudm
- Safeda ballies 125 mm dia
- 10x7x4x3.6= 1008m
- Qty taken for cost using once = 1008/8 =
- 126m
- G.I. Plain sheet 203.7 sqm = 1160kg. Or 11.6
- quintal
- Qty taken for cost using once =11.6/8 = 1.45
- qtl
- CarriageKail wood = 20.48cum.
- Ballies - 1008x3.142x(0.125) /4= 12.37cum.
- Total = 32.85 cum.
- Qty taken for cost using once ² = 32.85/8 =
- 4.106 cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1197 | Second class kail wood in scantlingMaterial | cudm 10 | 256 | 260.00 | 66,560.00 |
| 0302 | Safeda ballies 125 mm diameterMaterial | metre | 126 | 44.00 | 5,544.00 |
| 0992 | Galvanised steel plain sheetsMaterial | quintal | 1.45 | 6,800.00 | 9,860.00 |
| 0112 | Carpenter 2nd classLabour | day | 160 | 816.00 | 1,30,560.00 |
| 0114 | BeldarLabour | day | 130 | 736.00 | 95,680.00 |
| 9999 | SundriesMaterial | L.S. | 117 | 2.27 | 265.59 |
- TOTAL
- 3,08,469.59
- Add 1 % Water charges on “W”
- 3,084.70
- TOTAL
- 3,11,554.29
- Add GST on “X” (multiplying factor 0.2127)
- 66,267.60
- TOTAL
- 3,77,821.89
- Add 15% CPOH on “Y”
- 56,673.28
- TOTAL
- 4,34,495.17
- Add Cess @ 1% on “Z”
- 4,344.95
- Cost of 203.7sqm.
- 4,38,840.12
- Cost per sqm.
- 2,154.35
- Say
- 2,154.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 225. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works