CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Extra for arches, domes, vaults exceeding 6 m span

Item number
5.9.10
Analysis basis
Details of cost for 333.1 sqm
Priced inputs
7
Derived rate
608.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.10 Centering and shuttering including strutting, propping etc. and removal of form for Extra for arches, domes, vaults exceeding 6 m span — is derived from 7 priced inputs for 333.1 sqm and works out to ₹608.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Centering and shuttering for 10 Nos. arches
  • and carved surface exceeding 6m in span
  • (an average of 8m)
  • Radius R = 5m 2R-2 = 8
  • tan - (4/3)=53.28°
  • 2x53.28° = 106°
  • Surface ¹ area =10x2x(22/7)x5x3.6x106/360
  • =333.10 sqm
  • Arc=9.25m
  • Tie-2x8x0.18x0.05 =0.144cum
  • Struts-2x2.5x0.1x0.1 =0.050cum.
  • Struts-2x1.77x0.1x0.1=0.035cum.
  • Ribs-6x1.54x0.23x0.1=0.213cum.
  • Struts-2x1.72x0.1x0.1=0.034cum.
  • Total=0.476cum.
  • For 10x4 such frames =0.476x4x10 = 19.04
  • cum
  • laggings-10x75x3.6x0.125x0.075=25.31cum
  • Tie-10x2x3.6x0.225x0.038=0.62cum
  • Brace-10x3x2x2.14x0.225x0.038=1.10 cum
  • Brace-10x3x4x3.8x0.225x0.038=3.90 cum
  • Sleepers-10x4x3.6x0.20x0.15=4.32 cum
  • Sleepers-10x2x4x3.6x0.175x0.075=3.78 cum
  • Vertical post-10x4x4x3.6x0.15x0.15=12.96
  • cum
  • Total =71.03cum. or 71030 cudm
  • Qty taken 1/8th of qty for cost using once
  • =71030/8 = 8879 Cudm
  • Bolts 160x10 Nos. 254 mm long 16mm dia.1600x.254x 1.58=642.1 kg=6.42q.
  • Qty taken l/8th of qty for cost using once
  • =6.42/8 = 0.802
  • 6 m span
  • Less Cost of shuttering etc. for an arch upto
CodeInputUnitQuantityRate (INR)Amount (INR)
1197Second class kail wood in scantlingMaterialcudm 10887.9260.002,30,854.00
1225Mild steel flat strap fittingMaterialquintal0.8784,120.003,617.36
1034Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterialquintal0.8025,200.004,170.40
0112Carpenter 2nd classLabourday280816.002,28,480.00
0114BeldarLabourday240736.001,76,640.00
9999SundriesMaterialL.S.1,345.52.273,054.29
Rate as per item no 5.9.9 of SH : RCCRate as per item 5.9.9Sub-analysissqm-333.12,154.35-7,17,613.99
TOTAL
-70,797.94
Add 1 % Water charges on “W-A”
6,468.16
TOTAL
-64,329.78
Add GST on “X-A” (multiplying factor 0.2127)
1,38,953.55
TOTAL
74,623.77
Add 15% CPOH on “Y-A”
1,18,835.66
TOTAL
1,93,459.43
Add Cess @ 1% on “Z-A”
9,110.73
Cost of 333.1sqm.
2,02,570.16
Cost per sqm of soffit area
608.14
Say
608.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 226. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.