Centering and shuttering including strutting, propping etc. and removal of form for

Spiral staircases (including landing)
Item number
5.9.8
Analysis basis
6.28 sqm
Priced inputs
3
Derived rate
₹798.35/ SQM
D-01/RATE ANALYSISITEM 5.9.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.8 (Centering and shuttering including strutting, propping etc. and removal of form for Spiral staircases (including landing)) is derived from 3 priced inputs for 6.28 sqm and works out to ₹798.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Treads
  • 10x0.70x0.20(av.) = 1.40 sqm
  • Riser
  • 2x10x0.70x0.23 = 3.22 sqm
  • Newal Post (Column)
  • 10x0.23x3.14x0.23 = 1.66 sqm
ANALYSIS OF RATES · ITEM 5.9.8DETAIL OF COST FOR 6.28 SQM (FOR 10 STEPS)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 5.9.5 of SH: RCCRate as per item 5.9.5sqm1.4736.401,030.96
SUBRate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2sqm3.22842.502,712.85
SUBRate as per item no 5.9.7 of SH: RCCRate as per item 5.9.7sqm1.66764.951,269.82
BUILD-UP TO RATE
Cost of 6.28 sqm
5,013.63
Cost of 1 sqm
798.35
SAY
₹798.35
D-02/SOURCEPRINTED PAGE 225
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
225

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 225. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.