Centering and shuttering including strutting, propping etc. and removal of form for

Stairs, (excluding landings) except spiral-staircases
Item number
5.9.7
Analysis basis
57.9 sqm
Priced inputs
6
Derived rate
₹764.95/ SQM
D-01/RATE ANALYSISITEM 5.9.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.7 (Centering and shuttering including strutting, propping etc. and removal of form for Stairs, (excluding landings) except spiral-staircases) is derived from 6 priced inputs for 57.9 sqm and works out to ₹764.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details of 10 Nos. staircase, 3.40m clear
  • span including 1m landing.
  • (i) Cost of plank 38mm (2nd class kail wood)
  • Waist= 10x2.69x1.30 = 35.0sqm.
  • Side shuttering of steps and side of waistSteps
  • 10x8x1.30x0.15 = 15.6 sqm.
  • Face of landing
  • 10x1x1.30x0.15 = 2.0 sqm.
  • Side of waist
  • 10x2.69x0.13 = 3.5 sqm.
  • Side of steps10x8x0.50x0.30x0.15 = 1.80sqm.
  • Total = 57.9 sqm.
  • Wastage 5% = 2.9sqm.
  • Total = 60.8 sq.
  • Cubical content- 60.8x0.038 = 2.31 cum =
  • 2310 dm
  • Qty taken for cost using once = 2310/8=
  • 288.75 cudm ³
  • (ii) Batten 100mm x 75mm
  • 10x4x1.30x0.100x0.075=0.39 cum = 390 dm
  • Qty taken for cost using once = 390/8 =
  • 48.75 cudm ³
  • 10x2x4x0.80 = 64.0m
  • Qty taken for cost using once = 64.0/8 = 8.0 m
  • Planks = 2.31 cum.
  • Battens = 0.39 cum.
  • Ballies 64x3.142/4x(0.125) = 0.79cum.
  • Total = 3.49 cum.
  • Qty taken for cost using once ² = 3.49/8 =
  • 0.436 cum
ANALYSIS OF RATES · ITEM 5.9.7DETAILS OF COST FOR 57.9 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1198MATSecond class kail wood in plankscudm28.875260.007,507.50
1197MATSecond class kail wood in scantlingcudm4.875260.001,267.50
0302MATSafeda ballies 125 mm diametermetre844.00352.00
0112LABCarpenter 2nd classday17.5816.0014,280.00
0114LABBeldarday10736.007,360.00
9999MATSundriesL.S.161.22.27365.92
BUILD-UP TO RATE
TOTAL
31,132.92
Add 1 % Water charges on “W”
+311.33
TOTAL
31,444.25
Add GST on “X” (multiplying factor 0.2127)
+6,688.19
TOTAL
38,132.44
Add 15% CPOH on “Y”
+5,719.87
TOTAL
43,852.31
Add Cess @ 1% on “Z”
+438.52
Cost of 57.9 sqm.
44,290.83
Cost per sqm.
764.95
SAY
₹764.95
D-02/SOURCEPRINTED PAGE 224
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
224

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 224. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.