CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Stairs, (excluding landings) except spiral-staircases

Item number
5.9.7
Analysis basis
Details of cost for 57.9 sqm.
Priced inputs
6
Derived rate
764.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.7 Centering and shuttering including strutting, propping etc. and removal of form for Stairs, (excluding landings) except spiral-staircases — is derived from 6 priced inputs for 57.9 sqm and works out to ₹764.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Details of 10 Nos. staircase, 3.40m clear
  • span including 1m landing.
  • (i) Cost of plank 38mm (2nd class kail wood)
  • Waist= 10x2.69x1.30 = 35.0sqm.
  • Side shuttering of steps and side of waistSteps
  • 10x8x1.30x0.15 = 15.6 sqm.
  • Face of landing
  • 10x1x1.30x0.15 = 2.0 sqm.
  • Side of waist
  • 10x2.69x0.13 = 3.5 sqm.
  • Side of steps10x8x0.50x0.30x0.15 = 1.80sqm.
  • Total = 57.9 sqm.
  • Wastage 5% = 2.9sqm.
  • Total = 60.8 sq.
  • Cubical content- 60.8x0.038 = 2.31 cum =
  • 2310 dm
  • Qty taken for cost using once = 2310/8=
  • 288.75 cudm ³
  • (ii) Batten 100mm x 75mm
  • 10x4x1.30x0.100x0.075=0.39 cum = 390 dm
  • Qty taken for cost using once = 390/8 =
  • 48.75 cudm ³
  • 10x2x4x0.80 = 64.0m
  • Qty taken for cost using once = 64.0/8 = 8.0 m
  • Planks = 2.31 cum.
  • Battens = 0.39 cum.
  • Ballies 64x3.142/4x(0.125) = 0.79cum.
  • Total = 3.49 cum.
  • Qty taken for cost using once ² = 3.49/8 =
  • 0.436 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterialcudm28.875260.007,507.50
1197Second class kail wood in scantlingMaterialcudm4.875260.001,267.50
0302Safeda ballies 125 mm diameterMaterialmetre844.00352.00
0112Carpenter 2nd classLabourday17.5816.0014,280.00
0114BeldarLabourday10736.007,360.00
9999SundriesMaterialL.S.161.22.27365.92
TOTAL
31,132.92
Add 1 % Water charges on “W”
311.33
TOTAL
31,444.25
Add GST on “X” (multiplying factor 0.2127)
6,688.19
TOTAL
38,132.44
Add 15% CPOH on “Y”
5,719.87
TOTAL
43,852.31
Add Cess @ 1% on “Z”
438.52
Cost of 57.9 sqm.
44,290.83
Cost per sqm.
764.95
Say
764.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 224. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works