Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.7
- Analysis basis
- 57.9 sqm
- Priced inputs
- 6
- Derived rate
- ₹764.95/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.7 (Centering and shuttering including strutting, propping etc. and removal of form for Stairs, (excluding landings) except spiral-staircases) is derived from 6 priced inputs for 57.9 sqm and works out to ₹764.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Details of 10 Nos. staircase, 3.40m clear
- span including 1m landing.
- (i) Cost of plank 38mm (2nd class kail wood)
- Waist= 10x2.69x1.30 = 35.0sqm.
- Side shuttering of steps and side of waistSteps
- 10x8x1.30x0.15 = 15.6 sqm.
- Face of landing
- 10x1x1.30x0.15 = 2.0 sqm.
- Side of waist
- 10x2.69x0.13 = 3.5 sqm.
- Side of steps10x8x0.50x0.30x0.15 = 1.80sqm.
- Total = 57.9 sqm.
- Wastage 5% = 2.9sqm.
- Total = 60.8 sq.
- Cubical content- 60.8x0.038 = 2.31 cum =
- 2310 dm
- Qty taken for cost using once = 2310/8=
- 288.75 cudm ³
- (ii) Batten 100mm x 75mm
- 10x4x1.30x0.100x0.075=0.39 cum = 390 dm
- Qty taken for cost using once = 390/8 =
- 48.75 cudm ³
- 10x2x4x0.80 = 64.0m
- Qty taken for cost using once = 64.0/8 = 8.0 m
- Planks = 2.31 cum.
- Battens = 0.39 cum.
- Ballies 64x3.142/4x(0.125) = 0.79cum.
- Total = 3.49 cum.
- Qty taken for cost using once ² = 3.49/8 =
- 0.436 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1198 | MAT | Second class kail wood in planks | cudm | 28.875 | 260.00 | 7,507.50 |
| 1197 | MAT | Second class kail wood in scantling | cudm | 4.875 | 260.00 | 1,267.50 |
| 0302 | MAT | Safeda ballies 125 mm diameter | metre | 8 | 44.00 | 352.00 |
| 0112 | LAB | Carpenter 2nd class | day | 17.5 | 816.00 | 14,280.00 |
| 0114 | LAB | Beldar | day | 10 | 736.00 | 7,360.00 |
| 9999 | MAT | Sundries | L.S. | 161.2 | 2.27 | 365.92 |
- TOTAL
- 31,132.92
- Add 1 % Water charges on “W”
- +311.33
- TOTAL
- 31,444.25
- Add GST on “X” (multiplying factor 0.2127)
- +6,688.19
- TOTAL
- 38,132.44
- Add 15% CPOH on “Y”
- +5,719.87
- TOTAL
- 43,852.31
- Add Cess @ 1% on “Z”
- +438.52
- Cost of 57.9 sqm.
- 44,290.83
- Cost per sqm.
- 764.95
- SAY
- ₹764.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 224
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 224. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.