Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.6
- Analysis basis
- 45 sqm
- Priced inputs
- 10
- Derived rate
- ₹961.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.6 (Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts) is derived from 10 priced inputs for 45 sqm and works out to ₹961.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Size of column 450x450mm and 2.5m high
- Area of contact = 10x4x0.45x2.5 = 45 sqm.
- Assuming shuttering will become unserviceable after use of 40 times
- @ 25% of cost of material
- Qty taken for cost of using once =10x
- 8x0.85/40 = 1.70
- Qty taken for cost of using once =
- 10x4x0.85/40 = 0.85
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063
- Qty taken for cost of using once =
- 10x4x0.85/40 = 0.85
- Qty taken for cost of using once =
- 10x1300x0.85/40 = 276.2
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7331 | MAT | Wall form panel 1250x450 mm | each | 1.7 | 900.00 | 1,530.00 |
| 7332 | MAT | Corner angle 45x45x5 m 2.50 m longCorner angle 45x45x5 mm 2.50 m long | each | 0.85 | 275.00 | 233.75 |
| 7333 | MAT | Column clamp 450x1070 mColumn clamp 450x1070 mm | each | 1.063 | 1,020.00 | 1,084.26 |
| 7334 | MAT | Prop 2 m ( 2-3.5m)Prop 2 m ( 2-3.5 m) | each | 0.85 | 690.00 | 586.50 |
| 9999 | MAT | Assembly nut & bolt | L.S. | 276.2 | 2.27 | 626.97 |
| 9977 | MAT | Carriage | L.S. | 520 | 2.27 | 1,180.40 |
| 0116 | LAB | Fitter (grade 1) | day | 10 | 897.00 | 8,970.00 |
| 0114 | LAB | Beldar | day | 20 | 736.00 | 14,720.00 |
| 9999 | MAT | Shuttering oil | L.S. | 390 | 2.27 | 885.30 |
| 9977 | MAT | Carriage | L.S. | 260 | 2.27 | 590.20 |
- TOTAL
- 30,407.38
- Add 1 % Water charges on “W”
- +304.07
- TOTAL
- 30,711.45
- Add GST on “X” (multiplying factor 0.2127)
- +6,532.33
- TOTAL
- 37,243.78
- Add 15% CPOH on “Y”
- +5,586.57
- TOTAL
- 42,830.35
- Add Cess @ 1% on “Z”
- +428.30
- Cost for 45 sqm.
- 43,258.65
- Cost per sqm.
- 961.30
- SAY
- ₹961.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 223
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 223. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.