Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.5
- Priced inputs
- 9
- Derived rate
- ₹736.40
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.5 (Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers) is derived from 9 priced inputs and works out to ₹736.40 after water charges, GST, CPOH and cess. The full build-up is below.
- Consider 10 beam of 6 m clear span, 0.50 m
- deep 0.30 m wide and height 3.5 m from floor
- Cubical contents
- 10x6.60x0.5x0.3 = 9.9 cum
- 10x1x1.30x6.00 = 78 sqm
- Assuming shuttering will become unserviceable after use of 40 times
- @ 25% of cost of material
- 1. Steel plates for side and bottom
- (plate size 1.20 x 0.50m)
- Angle 40x40x5mm
- 2x1.20 = 2.40 m
- 3x0.50 = 1.50 m
- 3.90 m @ 3.00 kg/m = 11.70 kg
- sheet 1.6 mm thick
- 1.20m x 0.50 m = 0.60 sqm.
- 0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.
- Weight of one plate = 19.23 kg.
- Total = 20.19 kg.
- Total weight of all plates=
- 10x3x5x20.19 = 3028.5 kg
- Qty taken for cost of using once =
- 13028.5x0.85/40 = 64.356 kg.
- Qty taken for cost of using once
- =10x6x0.85/40 = 1.275 m
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063 m
- Qty taken for cost of using once =
- 10x1040x0.85/40 = 221
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use
- Add for wastage @ 5% = 0.96 kg.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no.10.1 S.H. steel workRate as per item 10.1 | kg | 64.356 | 117.35 | 7,552.18 | |
| 7343 | MAT | Adjustable telescopic prop 3 m (2.02-3.75 m) | each | 1.275 | 1,051.00 | 1,340.03 |
| 7344 | MAT | Beam clamp 300-380 mm (450-1070 mm) | each set | 1.063 | 375.00 | 398.63 |
| 9999 | MAT | (iv) Assembly nut & bolts etc. | L.S. | 221 | 2.27 | 501.67 |
| 9977 | MAT | Carriage | L.S. | 780 | 2.27 | 1,770.60 |
| 0116 | LAB | Fitter (grade 1) | day | 12.5 | 897.00 | 11,212.50 |
| 0114 | LAB | Beldar | day | 25 | 736.00 | 18,400.00 |
| 9999 | MAT | Shuttering oil | L.S. | 390 | 2.27 | 885.30 |
| 9999 | MAT | Sundries, paper tape etc. | L.S. | 246.1 | 2.27 | 558.65 |
- TOTAL
- 42,619.56
- Add 1 % Water charges on “W-A”
- +350.67
- TOTAL
- 42,970.23
- Add GST on “X-A” (multiplying factor 0.2127)
- +7,533.42
- TOTAL
- 50,503.65
- Add 15% CPOH on “Y-A”
- +6,442.72
- TOTAL
- 56,946.37
- Add Cess @ 1% on “Z-A”
- +493.94
- Cost for 78 sqm.
- 57,440.31
- Cost per sqm.
- 736.41
- SAY
- ₹736.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 222
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 222. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.