Skip to main content

Centering and shuttering including strutting, propping etc. and removal of form for

Lintels, beams, plinth beams, girders, bressumers and cantilevers
Item number
5.9.5
Priced inputs
9
Derived rate
₹736.40
D-01/RATE ANALYSISITEM 5.9.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.5 (Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers) is derived from 9 priced inputs and works out to ₹736.40 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider 10 beam of 6 m clear span, 0.50 m
  • deep 0.30 m wide and height 3.5 m from floor
  • Cubical contents
  • 10x6.60x0.5x0.3 = 9.9 cum
  • 10x1x1.30x6.00 = 78 sqm
  • Assuming shuttering will become unserviceable after use of 40 times
  • @ 25% of cost of material
  • 1. Steel plates for side and bottom
  • (plate size 1.20 x 0.50m)
  • Angle 40x40x5mm
  • 2x1.20 = 2.40 m
  • 3x0.50 = 1.50 m
  • 3.90 m @ 3.00 kg/m = 11.70 kg
  • sheet 1.6 mm thick
  • 1.20m x 0.50 m = 0.60 sqm.
  • 0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.
  • Weight of one plate = 19.23 kg.
  • Total = 20.19 kg.
  • Total weight of all plates=
  • 10x3x5x20.19 = 3028.5 kg
  • Qty taken for cost of using once =
  • 13028.5x0.85/40 = 64.356 kg.
  • Qty taken for cost of using once
  • =10x6x0.85/40 = 1.275 m
  • Qty taken for cost of using once =
  • 10x5x0.85/40 = 1.063 m
  • Qty taken for cost of using once =
  • 10x1040x0.85/40 = 221
  • Add maintenance charges @ 10% of cost of
  • Less salvage value of material after full use
  • Add for wastage @ 5% = 0.96 kg.
ANALYSIS OF RATES · ITEM 5.9.5
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no.10.1 S.H. steel workRate as per item 10.1kg64.356117.357,552.18
7343MATAdjustable telescopic prop 3 m (2.02-3.75 m)each1.2751,051.001,340.03
7344MATBeam clamp 300-380 mm (450-1070 mm)each set1.063375.00398.63
9999MAT(iv) Assembly nut & bolts etc.L.S.2212.27501.67
9977MATCarriageL.S.7802.271,770.60
0116LABFitter (grade 1)day12.5897.0011,212.50
0114LABBeldarday25736.0018,400.00
9999MATShuttering oilL.S.3902.27885.30
9999MATSundries, paper tape etc.L.S.246.12.27558.65
BUILD-UP TO RATE
TOTAL
42,619.56
Add 1 % Water charges on “W-A”
+350.67
TOTAL
42,970.23
Add GST on “X-A” (multiplying factor 0.2127)
+7,533.42
TOTAL
50,503.65
Add 15% CPOH on “Y-A”
+6,442.72
TOTAL
56,946.37
Add Cess @ 1% on “Z-A”
+493.94
Cost for 78 sqm.
57,440.31
Cost per sqm.
736.41
SAY
₹736.40
D-02/SOURCEPRINTED PAGE 222
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
222

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 222. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.