CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for
Lintels, beams, plinth beams, girders, bressumers and cantilevers
- Item number
- 5.9.5
- Priced inputs
- 9
- Derived rate
- ₹736.40
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.5 — Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers — is derived from 9 priced inputs and works out to ₹736.40 after water charges, GST, CPOH and cess. The full build-up is below.
- Consider 10 beam of 6 m clear span, 0.50 m
- deep 0.30 m wide and height 3.5 m from floor
- Cubical contents
- 10x6.60x0.5x0.3 = 9.9 cum
- 10x1x1.30x6.00 = 78 sqm
- Assuming shuttering will become unserviceable after use of 40 times
- @ 25% of cost of material
- 1. Steel plates for side and bottom
- (plate size 1.20 x 0.50m)
- Angle 40x40x5mm
- 2x1.20 = 2.40 m
- 3x0.50 = 1.50 m
- 3.90 m @ 3.00 kg/m = 11.70 kg
- sheet 1.6 mm thick
- 1.20m x 0.50 m = 0.60 sqm.
- 0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.
- Weight of one plate = 19.23 kg.
- Total = 20.19 kg.
- Total weight of all plates=
- 10x3x5x20.19 = 3028.5 kg
- Qty taken for cost of using once =
- 13028.5x0.85/40 = 64.356 kg.
- Qty taken for cost of using once
- =10x6x0.85/40 = 1.275 m
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063 m
- Qty taken for cost of using once =
- 10x1040x0.85/40 = 221
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use
- Add for wastage @ 5% = 0.96 kg.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no.10.1 S.H. steel workRate as per item 10.1Sub-analysis | kg | 64.356 | 117.35 | 7,552.18 | |
| 7343 | Adjustable telescopic prop 3 m (2.02-3.75 m)Material | each | 1.275 | 1,051.00 | 1,340.03 |
| 7344 | Beam clamp 300-380 mm (450-1070 mm)Material | each set | 1.063 | 375.00 | 398.63 |
| 9999 | (iv) Assembly nut & bolts etc.Material | L.S. | 221 | 2.27 | 501.67 |
| 9977 | CarriageMaterial | L.S. | 780 | 2.27 | 1,770.60 |
| 0116 | Fitter (grade 1)Labour | day | 12.5 | 897.00 | 11,212.50 |
| 0114 | BeldarLabour | day | 25 | 736.00 | 18,400.00 |
| 9999 | Shuttering oilMaterial | L.S. | 390 | 2.27 | 885.30 |
| 9999 | Sundries, paper tape etc.Material | L.S. | 246.1 | 2.27 | 558.65 |
- TOTAL
- 42,619.56
- Add 1 % Water charges on “W-A”
- 350.67
- TOTAL
- 42,970.23
- Add GST on “X-A” (multiplying factor 0.2127)
- 7,533.42
- TOTAL
- 50,503.65
- Add 15% CPOH on “Y-A”
- 6,442.72
- TOTAL
- 56,946.37
- Add Cess @ 1% on “Z-A”
- 493.94
- Cost for 78 sqm.
- 57,440.31
- Cost per sqm.
- 736.41
- Say
- 736.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 222. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.