Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Lintels, beams, plinth beams, girders, bressumers and cantilevers

Item number
5.9.5
Priced inputs
9
Derived rate
736.40

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.5 Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers — is derived from 9 priced inputs and works out to ₹736.40 after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider 10 beam of 6 m clear span, 0.50 m
  • deep 0.30 m wide and height 3.5 m from floor
  • Cubical contents
  • 10x6.60x0.5x0.3 = 9.9 cum
  • 10x1x1.30x6.00 = 78 sqm
  • Assuming shuttering will become unserviceable after use of 40 times
  • @ 25% of cost of material
  • 1. Steel plates for side and bottom
  • (plate size 1.20 x 0.50m)
  • Angle 40x40x5mm
  • 2x1.20 = 2.40 m
  • 3x0.50 = 1.50 m
  • 3.90 m @ 3.00 kg/m = 11.70 kg
  • sheet 1.6 mm thick
  • 1.20m x 0.50 m = 0.60 sqm.
  • 0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.
  • Weight of one plate = 19.23 kg.
  • Total = 20.19 kg.
  • Total weight of all plates=
  • 10x3x5x20.19 = 3028.5 kg
  • Qty taken for cost of using once =
  • 13028.5x0.85/40 = 64.356 kg.
  • Qty taken for cost of using once
  • =10x6x0.85/40 = 1.275 m
  • Qty taken for cost of using once =
  • 10x5x0.85/40 = 1.063 m
  • Qty taken for cost of using once =
  • 10x1040x0.85/40 = 221
  • Add maintenance charges @ 10% of cost of
  • Less salvage value of material after full use
  • Add for wastage @ 5% = 0.96 kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no.10.1 S.H. steel workRate as per item 10.1Sub-analysiskg64.356117.357,552.18
7343Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach1.2751,051.001,340.03
7344Beam clamp 300-380 mm (450-1070 mm)Materialeach set1.063375.00398.63
9999(iv) Assembly nut & bolts etc.MaterialL.S.2212.27501.67
9977CarriageMaterialL.S.7802.271,770.60
0116Fitter (grade 1)Labourday12.5897.0011,212.50
0114BeldarLabourday25736.0018,400.00
9999Shuttering oilMaterialL.S.3902.27885.30
9999Sundries, paper tape etc.MaterialL.S.246.12.27558.65
TOTAL
42,619.56
Add 1 % Water charges on “W-A”
350.67
TOTAL
42,970.23
Add GST on “X-A” (multiplying factor 0.2127)
7,533.42
TOTAL
50,503.65
Add 15% CPOH on “Y-A”
6,442.72
TOTAL
56,946.37
Add Cess @ 1% on “Z-A”
493.94
Cost for 78 sqm.
57,440.31
Cost per sqm.
736.41
Say
736.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 222. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works