Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Shelves (Cast in situ)

Item number
5.9.4
Analysis basis
Detail of cost for 10 room of size 4.50x3m
Priced inputs
9
Derived rate
927.25 / room

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.4 Centering and shuttering including strutting, propping etc. and removal of form for Shelves (Cast in situ) — is derived from 9 priced inputs for 10 room and works out to ₹927.25 per room after water charges, GST, CPOH and cess. The full build-up is below.

  • =10x4.5x3.0 = 135 sqm, height 3.5 m
  • Adding for maintenance @ 10% of cost
  • Taking salvage value after full use of material
  • @ 25% of cost
  • 1. Plates (size 0.75 x 0.60)
  • Angle 40x40x5mm
  • 2x0.75 = 1.50 m
  • 2x0.60 = 1.20 m
  • = 2.70 m @ 3.00 kg/m = 8.1 kg
  • sheet 1.6 mm thick
  • 0.75x0.60 = 0.45 sqm
  • 0.45 sqm @ 12.55kg/sqm = 5.65kg
  • Weight of one plate = 13.75kg
  • Total weight for one plate = 14.44kg
  • Total weight of all plates =10x 5x6x14.44 =
  • 4332 kg.
  • Qty taken for cost using once = 4332x0.85/40
  • = 92.055 kg
  • Qty taken for cost using once = 10x5x0.85/40
  • = 1.063
  • Qty taken for cost using once = 10x6x0.85/40
  • = 1.275
  • Qty taken for cost using once =
  • 10x1040x0.85/40 = 221
  • Add for wastage @ 5% = 0.69 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no.10.1 S.H. steel workRate as per item 10.1Sub-analysiskg92.055117.3510,802.65
7342Adjustable span ESO+SI (2.35-3.40)Materialeach1.0631,540.001,637.02
7343Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach1.2751,051.001,340.03
99994. Assembly nut & bolts etc.MaterialL.S.2212.27501.67
9977CarriageMaterialL.S.1,3002.272,951.00
0116Fitter (grade 1)Labourday30897.0026,910.00
0114BeldarLabourday60736.0044,160.00
9999Shuttering oilMaterialL.S.7802.271,770.60
9999Sundries, paper tap etc.MaterialL.S.4972.271,128.19
TOTAL
91,201.16
Add 1 % Water charges on “W-A”
803.99
TOTAL
92,005.15
Add GST on “X-A” (multiplying factor 0.2127)
17,271.77
TOTAL
1,09,276.92
Add 15% CPOH on “Y-A”
14,771.14
TOTAL
1,24,048.06
Add Cess @ 1% on “Z-A”
1,132.45
Cost for 135 sqm.
1,25,180.51
Cost per sqm.
927.26
Say
927.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 221. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works