Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.3
- Analysis basis
- 10 room
- Priced inputs
- 9
- Derived rate
- ₹927.25/ ROOM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.3 (Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform) is derived from 9 priced inputs for 10 room and works out to ₹927.25 per room after water charges, GST, CPOH and cess. The full build-up is below.
- 10x4.50x3 = 135 sqm, height 3.5 m
- Adding for maintenance @ 10% of cost
- Taking salvage value after full use of material
- @ 25% of cost
- 1. Plates (size 0.75 x 0.60)
- Angle 40x40x5mm
- 2x0.75 = 1.50 m
- 2x0.60 = 1.20 m
- = 2.70 m @ 3.00 kg/m = 8.1 kg
- sheet 1.6 mm thick
- 0.75x0.60 = 0.45 sqm
- 0.45 sqm @ 12.55kg/sqm = 5.65kg
- Weight of one plate = 13.75kg
- Total weight for one plate = 14.44kg
- Total weight of all plates =10x 5x6x14.44 =
- 4332 kg.
- Qty taken for cost using once = 4332x0.85/40
- = 92.055 kg
- Qty taken for cost using once = 10x5x0.85/40
- = 1.063
- Qty taken for cost using once = 10x6x0.85/40
- = 1.275
- Qty taken for cost using once =
- 10x1040x0.85/40 = 221
- Add for wastage @ 5% = 0.69 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no.10.1 S.H. steel workRate as per item 10.1 | kg | 92.055 | 117.35 | 10,802.65 | |
| 7342 | MAT | Adjustable span ESO+SI (2.35-3.40) | each | 1.063 | 1,540.00 | 1,637.02 |
| 7343 | MAT | Adjustable telescopic prop 3 m (2.02-3.75 m) | each | 1.275 | 1,051.00 | 1,340.03 |
| 9999 | MAT | 4. Assembly nut & bolts etc. | L.S. | 221 | 2.27 | 501.67 |
| 9977 | MAT | Carriage | L.S. | 1,300 | 2.27 | 2,951.00 |
| 0116 | LAB | Fitter (grade 1) | day | 30 | 897.00 | 26,910.00 |
| 0114 | LAB | Beldar | day | 60 | 736.00 | 44,160.00 |
| 9999 | MAT | Shuttering oil | L.S. | 780 | 2.27 | 1,770.60 |
| 9999 | MAT | Sundries, paper tap etc. | L.S. | 497 | 2.27 | 1,128.19 |
- TOTAL
- 91,201.16
- Add 1 % Water charges on “W-A”
- +803.99
- TOTAL
- 92,005.15
- Add GST on “X-A” (multiplying factor 0.2127)
- +17,271.77
- TOTAL
- 1,09,276.92
- Add 15% CPOH on “Y-A”
- +14,771.14
- TOTAL
- 1,24,048.06
- Add Cess @ 1% on “Z-A”
- +1,132.45
- Cost for 135 sqm.
- 1,25,180.51
- Cost per sqm.
- 927.26
- SAY
- ₹927.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 220
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 220. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.