CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc

Item number
5.9.2
Priced inputs
11
Derived rate
842.50

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.2 Centering and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc — is derived from 11 priced inputs and works out to ₹842.50 after water charges, GST, CPOH and cess. The full build-up is below.

  • Details for 7.5m long and 1.00m high wall
  • Area of contact= 2 x 7.5 x1.0 = 15.00 sqm.
  • Assuming shuttering material will become
  • unserviceable after use of 40 times
  • Adding for maintenance @ 10% of cost
  • Taking salvage value after full use of material
  • @ 25% of cost
  • 2x3x2x2 = 24Nos.
  • Qty taken for cost of using once =24x0.85/40
  • = 0.51
  • 3x2 = 6
  • Qty taken for cost of using once =6x0.85/40
  • = 0.13
  • 2x6x2 = 24
  • Qty taken for cost of using once =24x0.85/40
  • = 0.51
  • 2x3x2 = 12
  • Qty taken for cost of using once =12x0.85/40
  • = 0.255
  • 2x2x8m = 32m
  • Qty taken for cost of using once =32x0.85/40
  • = 0.68
  • Qty taken for cost using once =1300x0.85/40
  • = 27.62
CodeInputUnitQuantityRate (INR)Amount (INR)
7319Wall form panel 1250x500 mmMaterialeach0.51900.00459.00
7327100 mm channel shoulder 2.5 m longMaterialeach0.13950.00123.50
7328Double clip ( bridge clip)Double clip (bridge clip)Materialeach0.5180.0040.80
7329Single clipMaterialeach0.25564.0016.32
7330M.S. tube 40 mm diaMaterialmetre0.68225.00153.00
9999Nut & BoltsMaterialL.S.27.622.2762.70
9977CarriageMaterialL.S.782.27177.06
0116Fitter (grade 1)Labourday3.5897.003,139.50
0114BeldarLabourday6736.004,416.00
9999Shuttering oilMaterialL.S.782.27177.06
9999SundriesMaterialL.S.522.27118.04
TOTAL
8,882.98
Add 1 % Water charges on “W”
88.83
TOTAL
8,971.81
Add GST on “X” (multiplying factor 0.2127)
1,908.30
TOTAL
10,880.11
Add 15% CPOH on “Y”
1,632.02
TOTAL
12,512.13
Add Cess @ 1% on “Z”
125.12
Cost for 15.00 sqm.
12,637.25
Cost per sqm.
842.48
Say
842.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 219. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.