CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for
Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc
- Item number
- 5.9.2
- Priced inputs
- 11
- Derived rate
- ₹842.50
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.2 — Centering and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc — is derived from 11 priced inputs and works out to ₹842.50 after water charges, GST, CPOH and cess. The full build-up is below.
- Details for 7.5m long and 1.00m high wall
- Area of contact= 2 x 7.5 x1.0 = 15.00 sqm.
- Assuming shuttering material will become
- unserviceable after use of 40 times
- Adding for maintenance @ 10% of cost
- Taking salvage value after full use of material
- @ 25% of cost
- 2x3x2x2 = 24Nos.
- Qty taken for cost of using once =24x0.85/40
- = 0.51
- 3x2 = 6
- Qty taken for cost of using once =6x0.85/40
- = 0.13
- 2x6x2 = 24
- Qty taken for cost of using once =24x0.85/40
- = 0.51
- 2x3x2 = 12
- Qty taken for cost of using once =12x0.85/40
- = 0.255
- 2x2x8m = 32m
- Qty taken for cost of using once =32x0.85/40
- = 0.68
- Qty taken for cost using once =1300x0.85/40
- = 27.62
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7319 | Wall form panel 1250x500 mmMaterial | each | 0.51 | 900.00 | 459.00 |
| 7327 | 100 mm channel shoulder 2.5 m longMaterial | each | 0.13 | 950.00 | 123.50 |
| 7328 | Double clip ( bridge clip)Double clip (bridge clip)Material | each | 0.51 | 80.00 | 40.80 |
| 7329 | Single clipMaterial | each | 0.255 | 64.00 | 16.32 |
| 7330 | M.S. tube 40 mm diaMaterial | metre | 0.68 | 225.00 | 153.00 |
| 9999 | Nut & BoltsMaterial | L.S. | 27.62 | 2.27 | 62.70 |
| 9977 | CarriageMaterial | L.S. | 78 | 2.27 | 177.06 |
| 0116 | Fitter (grade 1)Labour | day | 3.5 | 897.00 | 3,139.50 |
| 0114 | BeldarLabour | day | 6 | 736.00 | 4,416.00 |
| 9999 | Shuttering oilMaterial | L.S. | 78 | 2.27 | 177.06 |
| 9999 | SundriesMaterial | L.S. | 52 | 2.27 | 118.04 |
- TOTAL
- 8,882.98
- Add 1 % Water charges on “W”
- 88.83
- TOTAL
- 8,971.81
- Add GST on “X” (multiplying factor 0.2127)
- 1,908.30
- TOTAL
- 10,880.11
- Add 15% CPOH on “Y”
- 1,632.02
- TOTAL
- 12,512.13
- Add Cess @ 1% on “Z”
- 125.12
- Cost for 15.00 sqm.
- 12,637.25
- Cost per sqm.
- 842.48
- Say
- 842.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 219. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works