Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.1
- Analysis basis
- footing size
- Priced inputs
- 12
- Derived rate
- ₹392.15/ FOOTING SIZE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.1 (Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete) is derived from 12 priced inputs for footing size and works out to ₹392.15 per footing size after water charges, GST, CPOH and cess. The full build-up is below.
- 1.00m
- Contact area = 10.00 sqm.
- Assuming shuttering material will become
- unserviceable after use of 40 times
- Adding for maintenance @ 10% of cost
- Taking salvage value after full use of material
- @ 25% of cost
- Qty taken for cost of using once =
- 16x0.85/40 = 0.34
- Qty taken for cost of using once = 4x0.85/40
- = 0.085
- Qty taken for cost of using once =
- 8x0.85/40= 0.17
- Qty taken for cost of using once =
- 16x0.85/40 = 0.34
- Qty taken for cost of using once = 8x0.85/40
- = 0.17
- Qty taken for cost of using once =
- 10.00x0.85/40 = 0.213
- Qty taken for cost using once = 1040x0.85/40
- = 22.10
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7319 | MAT | Wall form panel 1250x500 mm | each | 0.34 | 900.00 | 306.00 |
| 7326 | MAT | Corner angle 45x45x5 mm 1.50 m long | each | 0.085 | 257.00 | 21.85 |
| 7327 | MAT | 100 mm channel shoulder 2.5 m long | each | 0.17 | 950.00 | 161.50 |
| 7328 | MAT | Double clip ( bridge clip)Double clip (bridge clip) | each | 0.34 | 80.00 | 27.20 |
| 7329 | MAT | Single clip | each | 0.17 | 64.00 | 10.88 |
| 7330 | MAT | M.S. tube 40 mm dia | metre | 0.213 | 225.00 | 47.93 |
| 9999 | MAT | Assembly nuts & bolts | L.S. | 22.1 | 2.27 | 50.17 |
| 9977 | MAT | Carriage | L.S. | 78 | 2.27 | 177.06 |
| 0116 | LAB | Fitter (grade 1) | day | 0.75 | 897.00 | 672.75 |
| 0114 | LAB | Beldar | day | 1.5 | 736.00 | 1,104.00 |
| 9999 | MAT | Shuttering oil | L.S. | 52 | 2.27 | 118.04 |
| 9999 | MAT | Sundries | L.S. | 26 | 2.27 | 59.02 |
- TOTAL
- 2,756.40
- Add 1 % Water charges on “W”
- +27.56
- TOTAL
- 2,783.96
- Add GST on “X” (multiplying factor 0.2127)
- +592.15
- TOTAL
- 3,376.11
- Add 15% CPOH on “Y”
- +506.42
- TOTAL
- 3,882.53
- Add Cess @ 1% on “Z”
- +38.83
- Cost for 10.00 sqm.
- 3,921.36
- Cost per sqm.
- 392.14
- SAY
- ₹392.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 218
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 218. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.