- Analysis basis
- Details of cost for footing size 2.5mx2.5mx-
- Priced inputs
- 12
- Derived rate
- ₹392.15 / footing size
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.1 — Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete — is derived from 12 priced inputs for footing size and works out to ₹392.15 per footing size after water charges, GST, CPOH and cess. The full build-up is below.
- 1.00m
- Contact area = 10.00 sqm.
- Assuming shuttering material will become
- unserviceable after use of 40 times
- Adding for maintenance @ 10% of cost
- Taking salvage value after full use of material
- @ 25% of cost
- Qty taken for cost of using once =
- 16x0.85/40 = 0.34
- Qty taken for cost of using once = 4x0.85/40
- = 0.085
- Qty taken for cost of using once =
- 8x0.85/40= 0.17
- Qty taken for cost of using once =
- 16x0.85/40 = 0.34
- Qty taken for cost of using once = 8x0.85/40
- = 0.17
- Qty taken for cost of using once =
- 10.00x0.85/40 = 0.213
- Qty taken for cost using once = 1040x0.85/40
- = 22.10
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7319 | Wall form panel 1250x500 mmMaterial | each | 0.34 | 900.00 | 306.00 |
| 7326 | Corner angle 45x45x5 mm 1.50 m longMaterial | each | 0.085 | 257.00 | 21.85 |
| 7327 | 100 mm channel shoulder 2.5 m longMaterial | each | 0.17 | 950.00 | 161.50 |
| 7328 | Double clip ( bridge clip)Double clip (bridge clip)Material | each | 0.34 | 80.00 | 27.20 |
| 7329 | Single clipMaterial | each | 0.17 | 64.00 | 10.88 |
| 7330 | M.S. tube 40 mm diaMaterial | metre | 0.213 | 225.00 | 47.93 |
| 9999 | Assembly nuts & boltsMaterial | L.S. | 22.1 | 2.27 | 50.17 |
| 9977 | CarriageMaterial | L.S. | 78 | 2.27 | 177.06 |
| 0116 | Fitter (grade 1)Labour | day | 0.75 | 897.00 | 672.75 |
| 0114 | BeldarLabour | day | 1.5 | 736.00 | 1,104.00 |
| 9999 | Shuttering oilMaterial | L.S. | 52 | 2.27 | 118.04 |
| 9999 | SundriesMaterial | L.S. | 26 | 2.27 | 59.02 |
- TOTAL
- 2,756.40
- Add 1 % Water charges on “W”
- 27.56
- TOTAL
- 2,783.96
- Add GST on “X” (multiplying factor 0.2127)
- 592.15
- TOTAL
- 3,376.11
- Add 15% CPOH on “Y”
- 506.42
- TOTAL
- 3,882.53
- Add Cess @ 1% on “Z”
- 38.83
- Cost for 10.00 sqm.
- 3,921.36
- Cost per sqm.
- 392.14
- Say
- 392.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 218. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.