Centering and shuttering including strutting, propping etc. and removal of form for

Foundations, footings, bases of columns, etc. for mass concrete
Item number
5.9.1
Analysis basis
footing size
Priced inputs
12
Derived rate
₹392.15/ FOOTING SIZE
D-01/RATE ANALYSISITEM 5.9.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.1 (Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete) is derived from 12 priced inputs for footing size and works out to ₹392.15 per footing size after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.00m
  • Contact area = 10.00 sqm.
  • Assuming shuttering material will become
  • unserviceable after use of 40 times
  • Adding for maintenance @ 10% of cost
  • Taking salvage value after full use of material
  • @ 25% of cost
  • Qty taken for cost of using once =
  • 16x0.85/40 = 0.34
  • Qty taken for cost of using once = 4x0.85/40
  • = 0.085
  • Qty taken for cost of using once =
  • 8x0.85/40= 0.17
  • Qty taken for cost of using once =
  • 16x0.85/40 = 0.34
  • Qty taken for cost of using once = 8x0.85/40
  • = 0.17
  • Qty taken for cost of using once =
  • 10.00x0.85/40 = 0.213
  • Qty taken for cost using once = 1040x0.85/40
  • = 22.10
ANALYSIS OF RATES · ITEM 5.9.1DETAILS OF COST FOR FOOTING SIZE 2.5MX2.5MX-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7319MATWall form panel 1250x500 mmeach0.34900.00306.00
7326MATCorner angle 45x45x5 mm 1.50 m longeach0.085257.0021.85
7327MAT100 mm channel shoulder 2.5 m longeach0.17950.00161.50
7328MATDouble clip ( bridge clip)Double clip (bridge clip)each0.3480.0027.20
7329MATSingle clipeach0.1764.0010.88
7330MATM.S. tube 40 mm diametre0.213225.0047.93
9999MATAssembly nuts & boltsL.S.22.12.2750.17
9977MATCarriageL.S.782.27177.06
0116LABFitter (grade 1)day0.75897.00672.75
0114LABBeldarday1.5736.001,104.00
9999MATShuttering oilL.S.522.27118.04
9999MATSundriesL.S.262.2759.02
BUILD-UP TO RATE
TOTAL
2,756.40
Add 1 % Water charges on “W”
+27.56
TOTAL
2,783.96
Add GST on “X” (multiplying factor 0.2127)
+592.15
TOTAL
3,376.11
Add 15% CPOH on “Y”
+506.42
TOTAL
3,882.53
Add Cess @ 1% on “Z”
+38.83
Cost for 10.00 sqm.
3,921.36
Cost per sqm.
392.14
SAY
₹392.15
D-02/SOURCEPRINTED PAGE 218
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
218

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 218. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.