Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.8A
- Analysis basis
- 10 sets
- Priced inputs
- 21
- Derived rate
- ₹11,283.55/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.8A (Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 21 priced inputs for 10 sets and works out to ₹11,283.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- fins 4m high and 1m center with 2 horizontal
- fins, all projecting 60cm from face of wall and
- 5cm thick = 10x0.66cum =6.6 cum. Cement
- Concrete 1 : 1 . 5 : 3 = 10 x 4x4.00x0.60x0.05
- = 4.8 cum and 10x2x3x1.00x0.60x0.05 = 1.8
- cum, Total = 6.6 cum.
- MATERIAL:
- Extra labour for lifting material upto floor V
- level:(Coolie 6.6x0.75x2.00=9.9)
- Extra for restricted working in fins
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal size | cum | 3.01 | 1,425.00 | 4,289.25 |
| 0279 | MAT | Recycled Concrete Aggregate (RCA) 20 mm nominal size | cum | 0.752 | 957.00 | 719.66 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal size | cum | 1.478 | 1,400.00 | 2,069.20 |
| 0281 | MAT | Recycled Concrete Aggregate (RCA) 10 mm nominal size | cum | 0.37 | 957.00 | 354.09 |
| 0982 | MAT | Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III) | cum | 2.244 | 1,450.00 | 3,253.80 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 0.561 | 957.00 | 536.88 |
| 0367 | MAT | Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade) | tonne | 2.64 | 5,156.00 | 13,611.84 |
| 0114 | LAB | Beldar | day | 7.9 | 736.00 | 5,814.40 |
| 0115 | LAB | Coolie | day | 5.6 | 736.00 | 4,121.60 |
| 0101 | LAB | Bhisti | day | 6 | 816.00 | 4,896.00 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.6 | 897.00 | 538.20 |
| 0124 | LAB | Mason (brick layer) 2 nd classMason 2nd class | day | 0.6 | 816.00 | 489.60 |
| 9999 | MAT | Scaffolding | L.S. | 301.6 | 2.27 | 684.63 |
| 9999 | MAT | Sundries | L.S. | 94.9 | 2.27 | 215.42 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.5 | 900.00 | 450.00 |
| 0012 | MACH | Vibrator (Needle type 40 mm) | day | 0.5 | 400.00 | 200.00 |
| 0115 | LAB | Coolie | day | 9.9 | 736.00 | 7,286.40 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.5 | 897.00 | 448.50 |
| 0124 | LAB | Mason (brick layer) 2 nd classMason 2nd class | day | 0.5 | 816.00 | 408.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 0101 | LAB | Bhisti | day | 1.5 | 816.00 | 1,224.00 |
- Total
- 52,347.47
- Add 1 % Water charges on “W”
- +523.47
- TOTAL
- 52,870.94
- Add GST on “X” (multiplying factor 0.2127)
- +11,245.65
- TOTAL
- 64,116.59
- Add 15% CPOH on “Y”
- +9,617.49
- TOTAL
- 73,734.08
- Add Cess @ 1% on “Z”
- +737.34
- Cost of 6.6 cum
- 74,471.42
- Cost of 1 cum
- 11,283.55
- SAY
- ₹11,283.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 217
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 217. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.