Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.8A
Analysis basis
10 sets
Priced inputs
21
Derived rate
₹11,283.55/ CUM
D-01/RATE ANALYSISITEM 5.8A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.8A (Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 21 priced inputs for 10 sets and works out to ₹11,283.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • fins 4m high and 1m center with 2 horizontal
  • fins, all projecting 60cm from face of wall and
  • 5cm thick = 10x0.66cum =6.6 cum. Cement
  • Concrete 1 : 1 . 5 : 3 = 10 x 4x4.00x0.60x0.05
  • = 4.8 cum and 10x2x3x1.00x0.60x0.05 = 1.8
  • cum, Total = 6.6 cum.
  • MATERIAL:
  • Extra labour for lifting material upto floor V
  • level:(Coolie 6.6x0.75x2.00=9.9)
  • Extra for restricted working in fins
ANALYSIS OF RATES · ITEM 5.8ADETAILS OF COST FOR 10 SETS OF 4 RCC VERTICAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal sizecum3.011,425.004,289.25
0279MATRecycled Concrete Aggregate (RCA) 20 mm nominal sizecum0.752957.00719.66
0297MATStone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal sizecum1.4781,400.002,069.20
0281MATRecycled Concrete Aggregate (RCA) 10 mm nominal sizecum0.37957.00354.09
0982MATCoarse sand (zone III) derived from natural sourcesCoarse sand (zone III)cum2.2441,450.003,253.80
0278MATManufactured sand derived from Recycled Concrete Aggregate (RCA)cum0.561957.00536.88
0367MATPortland Cement (0.2833cum)Portland Cement (OPC-43 Grade)tonne2.645,156.0013,611.84
0114LABBeldarday7.9736.005,814.40
0115LABCoolieday5.6736.004,121.60
0101LABBhistiday6816.004,896.00
0123LABMason 1st classMason 1st classday0.6897.00538.20
0124LABMason (brick layer) 2 nd classMason 2nd classday0.6816.00489.60
9999MATScaffoldingL.S.301.62.27684.63
9999MATSundriesL.S.94.92.27215.42
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.5900.00450.00
0012MACHVibrator (Needle type 40 mm)day0.5400.00200.00
0115LABCoolieday9.9736.007,286.40
0123LABMason 1st classMason 1st classday0.5897.00448.50
0124LABMason (brick layer) 2 nd classMason 2nd classday0.5816.00408.00
0114LABBeldarday1736.00736.00
0101LABBhistiday1.5816.001,224.00
BUILD-UP TO RATE
Total
52,347.47
Add 1 % Water charges on “W”
+523.47
TOTAL
52,870.94
Add GST on “X” (multiplying factor 0.2127)
+11,245.65
TOTAL
64,116.59
Add 15% CPOH on “Y”
+9,617.49
TOTAL
73,734.08
Add Cess @ 1% on “Z”
+737.34
Cost of 6.6 cum
74,471.42
Cost of 1 cum
11,283.55
SAY
₹11,283.55
D-02/SOURCEPRINTED PAGE 217
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
217

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 217. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.