Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.8A
Analysis basis
Details of cost for 10 sets of 4 RCC Vertical
Priced inputs
21
Derived rate
11,283.55 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.8A Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 21 priced inputs for 10 sets and works out to ₹11,283.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • fins 4m high and 1m center with 2 horizontal
  • fins, all projecting 60cm from face of wall and
  • 5cm thick = 10x0.66cum =6.6 cum. Cement
  • Concrete 1 : 1 . 5 : 3 = 10 x 4x4.00x0.60x0.05
  • = 4.8 cum and 10x2x3x1.00x0.60x0.05 = 1.8
  • cum, Total = 6.6 cum.
  • MATERIAL:
  • Extra labour for lifting material upto floor V
  • level:(Coolie 6.6x0.75x2.00=9.9)
  • Extra for restricted working in fins
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal sizeMaterialcum3.011,425.004,289.25
0279Recycled Concrete Aggregate (RCA) 20 mm nominal sizeMaterialcum0.752957.00719.66
0297Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal sizeMaterialcum1.4781,400.002,069.20
0281Recycled Concrete Aggregate (RCA) 10 mm nominal sizeMaterialcum0.37957.00354.09
0982Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III)Materialcum2.2441,450.003,253.80
0278Manufactured sand derived from Recycled Concrete Aggregate (RCA)Materialcum0.561957.00536.88
0367Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade)Materialtonne2.645,156.0013,611.84
0114BeldarLabourday7.9736.005,814.40
0115CoolieLabourday5.6736.004,121.60
0101BhistiLabourday6816.004,896.00
0123Mason 1st classMason 1st classLabourday0.6897.00538.20
0124Mason (brick layer) 2 nd classMason 2nd classLabourday0.6816.00489.60
9999ScaffoldingMaterialL.S.301.62.27684.63
9999SundriesMaterialL.S.94.92.27215.42
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.5900.00450.00
0012Vibrator (Needle type 40 mm)Machineryday0.5400.00200.00
0115CoolieLabourday9.9736.007,286.40
0123Mason 1st classMason 1st classLabourday0.5897.00448.50
0124Mason (brick layer) 2 nd classMason 2nd classLabourday0.5816.00408.00
0114BeldarLabourday1736.00736.00
0101BhistiLabourday1.5816.001,224.00
Total
52,347.47
Add 1 % Water charges on “W”
523.47
TOTAL
52,870.94
Add GST on “X” (multiplying factor 0.2127)
11,245.65
TOTAL
64,116.59
Add 15% CPOH on “Y”
9,617.49
TOTAL
73,734.08
Add Cess @ 1% on “Z”
737.34
Cost of 6.6 cum
74,471.42
Cost of 1 cum
11,283.55
Say
11,283.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 217. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.