CPWD Analysis of Rates · Reinforced Cement Concrete
Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zoneIII) derived from natural sources : 3 graded stone aggregate 20mm nominal size derived from natural sources)
- Item number
- 5.8
- Analysis basis
- Details of cost for10 sets of 4 RCC Vertical
- Priced inputs
- 18
- Derived rate
- ₹11,454.35
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.8 — Reinforced cement concrete work in vertical and horizontal fins individually or forming box louvers, facias and eaves boards above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zoneIII) derived from natural sources : 3 graded stone aggregate 20mm nominal size derived from natural sources) — is derived from 18 priced inputs and works out to ₹11,454.35 after water charges, GST, CPOH and cess. The full build-up is below.
- fins 4m high and 1m center with 2 horizontal
- fins, all projecting 60cm from face of wall and
- 5cm thick = 0.66 cum x 10 = 6.6 cum
- Cement Concrete 1:1.5.3
- 10x4x4.00x0.60x0.05 = 4.8 cum.
- 10x2x3x1.00x0.60x0.05 = 1.8 cum.
- Total = 6.6 cum.
- Extra labour for lifting material upto floor V
- level:(Coolie 6.6x0.75x2.00=9.9)
- Extra for restricted working in fins
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 3.762 | 1,425.00 | 5,360.85 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 1.848 | 1,400.00 | 2,587.20 |
| 0982 | Coarse sand (zone III)Material | cum | 2.805 | 1,450.00 | 4,067.25 |
| 0367 | Portland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)Material | tonne | 2.64 | 5,156.00 | 13,611.84 |
| 0114 | BeldarLabour | day | 7.9 | 736.00 | 5,814.40 |
| 0115 | CoolieLabour | day | 5.6 | 736.00 | 4,121.60 |
| 0101 | BhistiLabour | day | 6 | 816.00 | 4,896.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.6 | 897.00 | 538.20 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.6 | 816.00 | 489.60 |
| 9999 | ScafoldingMaterial | L.S. | 301.6 | 2.27 | 684.63 |
| 9999 | SundriesMaterial | L.S. | 94.9 | 2.27 | 215.42 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachinery | day | 0.5 | 900.00 | 450.00 |
| 0012 | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machinery | day | 0.5 | 400.00 | 200.00 |
| 0115 | CoolieLabour | day | 9.9 | 736.00 | 7,286.40 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0101 | BhistiLabour | day | 1.5 | 816.00 | 1,224.00 |
- TOTAL
- 53,139.89
- Add 1 % Water charges on “W”
- 531.40
- TOTAL
- 53,671.29
- Add GST on “X” (multiplying factor 0.2127)
- 11,415.88
- TOTAL
- 65,087.17
- Add 15% CPOH on “Y”
- 9,763.08
- TOTAL
- 74,850.25
- Add Cess @ 1% on “Z”
- 748.50
- Cost for 6.6 cum.
- 75,598.75
- Cost for 1 cum.
- 11,454.36
- Say
- 11,454.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 216. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works