Skip to main content

Reinforced cement concrete work in well-steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.7A
Analysis basis
1 cum
Priced inputs
2
Derived rate
₹8,253.80/ CUM
D-01/RATE ANALYSISITEM 5.7A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.7A (Reinforced cement concrete work in well-steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 2 priced inputs for 1 cum and works out to ₹8,253.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra labour involved
ANALYSIS OF RATES · ITEM 5.7ADETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
OTHERMATERIAL: RCC 1:1.5:3 in well steining Sub AR 1 Rate as per Sub AR-1 (Ref item 4.1.2)cum18,170.058,170.05
0115LABCoolieday0.08736.0058.88
BUILD-UP TO RATE
Total
8,228.93
Add 1 % Water charges on “W-A”
+0.59
TOTAL
8,229.52
Add GST on “X-A” (multiplying factor 0.2127)
+12.65
TOTAL
8,242.17
Add 15% CPOH on “Y-A”
+10.82
TOTAL
8,252.99
Add Cess @ 1% on “Z-A”
+0.83
Cost of 1 cum
8,253.82
SAY
₹8,253.80
D-02/SOURCEPRINTED PAGE 215
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
215

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 215. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.