Reinforced cement concrete work in well-steining, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item number
- 5.7
- Analysis basis
- 1 cum
- Priced inputs
- 2
- Derived rate
- ₹8,424.60/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.7 (Reinforced cement concrete work in well-steining, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 2 priced inputs for 1 cum and works out to ₹8,424.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- RCC 1:1 :3 in well steining
- Extra labour involved :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2 | cum | 1 | 8,340.85 | 8,340.85 | |
| 0115 | LAB | Coolie | day | 0.08 | 736.00 | 58.88 |
- TOTAL
- 8,399.73
- Add 1 % Water charges on “W-A”
- +0.59
- TOTAL
- 8,400.32
- Add GST on “X-A” (multiplying factor 0.2127)
- +12.65
- TOTAL
- 8,412.97
- Add 15% CPOH on “Y-A”
- +10.82
- TOTAL
- 8,423.79
- Add Cess @ 1% on “Z-A”
- +0.83
- Cost for 1 cum.
- 8,424.62
- SAY
- ₹8,424.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 215
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 215. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.