Centering and shuttering including strutting, propping etc. and removal of form for

Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick
Item number
5.9.21
Analysis basis
10 Nos
Priced inputs
14
Derived rate
₹841.95/ NOS
D-01/RATE ANALYSISITEM 5.9.21

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.21 (Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick) is derived from 14 priced inputs for 10 Nos and works out to ₹841.95 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • span, 0.50 m deep 0.30 m wide and height
  • 3.5 m from floor
  • Cubical contents
  • 10x6.60x0.5x0.3 = 9.9 cum
  • Area=10x1x1.30x6.00 = 78 sqm
  • Assuming shuttering will become unserviceable after use of 8 times
  • @ 25% of cost of material
  • Steel plates for side and bottom (plate size
  • 1.20 x 0.50m)
  • Angle 40x40x5mm (both sides) & bottom
  • 2x(2x1.20) +(2x1.2) =7.20m
  • 2x(3x0.50)+(3x0.30)=3.9m
  • 11.10 m @ 3.00 kg/m =33.30 kg
  • Weight of one plate = 33.30 kg.
  • Total =34.97 kg.
  • 10x5x34.97 = 1748.5 kg
  • Qty taken for cost of using once =
  • 1748.5x0.85/40 =37.2 kg
  • Welding length 4800/40= 120 cm
  • 10x1x1.30x6.00 = 78 sqm
  • Total = 81.9 sqm
  • Qty taken for cost of using once 81.9/8 sqm=
  • 10.2 sqm
  • Qty taken for cost of using once =
  • 10x6x0.85/40 =1.275 m
  • Qty taken for cost of using once =
  • 10x5x0.85/40 = 1.063m
  • Add maintenance charges @ 10% of cost of
  • Less salvage value of material after full use
  • Add for wastage =1.67kg.
  • Total weight of all plates
  • Add 5% wastage = 3.9 sqm
ANALYSIS OF RATES · ITEM 5.9.21DETAILS OF COST FOR 10 NOS. BEAM OF 6 M CLEAR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.10.1 of SH:Steel WorkRate as per item 10.1kg37.2117.354,365.42
1215MATWelding by electric plantcm1202.50300.00
8659MATWater proof ply 12mm thick.Water proof ply 12 mm thicksqm10.2578.005,895.60
0112LABCarpenter 2nd classday1.25816.001,020.00
0114LABBeldarday1.25736.00920.00
1034MATBolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthquintal0.0215,200.00109.20
7343MATAdjustable telescopic prop 3 m (2.02-3.75 m)each1.2751,051.001,340.03
7344MATBeam clamp 300-380 mm (450-1070 mm)each set1.063375.00398.63
9999MATAssembly nut & bolts etc.L.S.110.52.27250.84
9977MATCarriageL.S.7802.271,770.60
0116LABFitter (grade 1)day12.5897.0011,212.50
0114LABBeldarday25736.0018,400.00
9999MATShuttering oilL.S.3902.27885.30
9999MATSundries, paper tape etc.L.S.2602.27590.20
BUILD-UP TO RATE
TOTAL
47,458.32
Add 1 % Water charges on “W-A”
+430.93
TOTAL
47,889.25
Add GST on “X-A” (multiplying factor 0.2127)
+9,257.52
TOTAL
57,146.77
Add 15% CPOH on “Y-A”
+7,917.20
TOTAL
65,063.97
Add Cess @ 1% on “Z-A”
+606.99
Cost for 78 sqm.
65,670.96
Cost per sqm.
841.94
SAY
₹841.95
D-02/SOURCEPRINTED PAGE 237
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
237

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 237. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.