CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick

Item number
5.9.21
Analysis basis
Details of cost for 10 Nos. beam of 6 m clear
Priced inputs
14
Derived rate
841.95 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.21 Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick — is derived from 14 priced inputs for 10 Nos and works out to ₹841.95 each after water charges, GST, CPOH and cess. The full build-up is below.

  • span, 0.50 m deep 0.30 m wide and height
  • 3.5 m from floor
  • Cubical contents
  • 10x6.60x0.5x0.3 = 9.9 cum
  • Area=10x1x1.30x6.00 = 78 sqm
  • Assuming shuttering will become unserviceable after use of 8 times
  • @ 25% of cost of material
  • Steel plates for side and bottom (plate size
  • 1.20 x 0.50m)
  • Angle 40x40x5mm (both sides) & bottom
  • 2x(2x1.20) +(2x1.2) =7.20m
  • 2x(3x0.50)+(3x0.30)=3.9m
  • 11.10 m @ 3.00 kg/m =33.30 kg
  • Weight of one plate = 33.30 kg.
  • Total =34.97 kg.
  • 10x5x34.97 = 1748.5 kg
  • Qty taken for cost of using once =
  • 1748.5x0.85/40 =37.2 kg
  • Welding length 4800/40= 120 cm
  • 10x1x1.30x6.00 = 78 sqm
  • Total = 81.9 sqm
  • Qty taken for cost of using once 81.9/8 sqm=
  • 10.2 sqm
  • Qty taken for cost of using once =
  • 10x6x0.85/40 =1.275 m
  • Qty taken for cost of using once =
  • 10x5x0.85/40 = 1.063m
  • Add maintenance charges @ 10% of cost of
  • Less salvage value of material after full use
  • Add for wastage =1.67kg.
  • Total weight of all plates
  • Add 5% wastage = 3.9 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.10.1 of SH:Steel WorkRate as per item 10.1Sub-analysiskg37.2117.354,365.42
1215Welding by electric plantMaterialcm1202.50300.00
8659Water proof ply 12mm thick.Water proof ply 12 mm thickMaterialsqm10.2578.005,895.60
0112Carpenter 2nd classLabourday1.25816.001,020.00
0114BeldarLabourday1.25736.00920.00
1034Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterialquintal0.0215,200.00109.20
7343Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach1.2751,051.001,340.03
7344Beam clamp 300-380 mm (450-1070 mm)Materialeach set1.063375.00398.63
9999Assembly nut & bolts etc.MaterialL.S.110.52.27250.84
9977CarriageMaterialL.S.7802.271,770.60
0116Fitter (grade 1)Labourday12.5897.0011,212.50
0114BeldarLabourday25736.0018,400.00
9999Shuttering oilMaterialL.S.3902.27885.30
9999Sundries, paper tape etc.MaterialL.S.2602.27590.20
TOTAL
47,458.32
Add 1 % Water charges on “W-A”
430.93
TOTAL
47,889.25
Add GST on “X-A” (multiplying factor 0.2127)
9,257.52
TOTAL
57,146.77
Add 15% CPOH on “Y-A”
7,917.20
TOTAL
65,063.97
Add Cess @ 1% on “Z-A”
606.99
Cost for 78 sqm.
65,670.96
Cost per sqm.
841.94
Say
841.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 237. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.