CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for
Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick
- Item number
- 5.9.21
- Analysis basis
- Details of cost for 10 Nos. beam of 6 m clear
- Priced inputs
- 14
- Derived rate
- ₹841.95 / Nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.21 — Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick — is derived from 14 priced inputs for 10 Nos and works out to ₹841.95 each after water charges, GST, CPOH and cess. The full build-up is below.
- span, 0.50 m deep 0.30 m wide and height
- 3.5 m from floor
- Cubical contents
- 10x6.60x0.5x0.3 = 9.9 cum
- Area=10x1x1.30x6.00 = 78 sqm
- Assuming shuttering will become unserviceable after use of 8 times
- @ 25% of cost of material
- Steel plates for side and bottom (plate size
- 1.20 x 0.50m)
- Angle 40x40x5mm (both sides) & bottom
- 2x(2x1.20) +(2x1.2) =7.20m
- 2x(3x0.50)+(3x0.30)=3.9m
- 11.10 m @ 3.00 kg/m =33.30 kg
- Weight of one plate = 33.30 kg.
- Total =34.97 kg.
- 10x5x34.97 = 1748.5 kg
- Qty taken for cost of using once =
- 1748.5x0.85/40 =37.2 kg
- Welding length 4800/40= 120 cm
- 10x1x1.30x6.00 = 78 sqm
- Total = 81.9 sqm
- Qty taken for cost of using once 81.9/8 sqm=
- 10.2 sqm
- Qty taken for cost of using once =
- 10x6x0.85/40 =1.275 m
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063m
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use
- Add for wastage =1.67kg.
- Total weight of all plates
- Add 5% wastage = 3.9 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.10.1 of SH:Steel WorkRate as per item 10.1Sub-analysis | kg | 37.2 | 117.35 | 4,365.42 | |
| 1215 | Welding by electric plantMaterial | cm | 120 | 2.50 | 300.00 |
| 8659 | Water proof ply 12mm thick.Water proof ply 12 mm thickMaterial | sqm | 10.2 | 578.00 | 5,895.60 |
| 0112 | Carpenter 2nd classLabour | day | 1.25 | 816.00 | 1,020.00 |
| 0114 | BeldarLabour | day | 1.25 | 736.00 | 920.00 |
| 1034 | Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterial | quintal | 0.021 | 5,200.00 | 109.20 |
| 7343 | Adjustable telescopic prop 3 m (2.02-3.75 m)Material | each | 1.275 | 1,051.00 | 1,340.03 |
| 7344 | Beam clamp 300-380 mm (450-1070 mm)Material | each set | 1.063 | 375.00 | 398.63 |
| 9999 | Assembly nut & bolts etc.Material | L.S. | 110.5 | 2.27 | 250.84 |
| 9977 | CarriageMaterial | L.S. | 780 | 2.27 | 1,770.60 |
| 0116 | Fitter (grade 1)Labour | day | 12.5 | 897.00 | 11,212.50 |
| 0114 | BeldarLabour | day | 25 | 736.00 | 18,400.00 |
| 9999 | Shuttering oilMaterial | L.S. | 390 | 2.27 | 885.30 |
| 9999 | Sundries, paper tape etc.Material | L.S. | 260 | 2.27 | 590.20 |
- TOTAL
- 47,458.32
- Add 1 % Water charges on “W-A”
- 430.93
- TOTAL
- 47,889.25
- Add GST on “X-A” (multiplying factor 0.2127)
- 9,257.52
- TOTAL
- 57,146.77
- Add 15% CPOH on “Y-A”
- 7,917.20
- TOTAL
- 65,063.97
- Add Cess @ 1% on “Z-A”
- 606.99
- Cost for 78 sqm.
- 65,670.96
- Cost per sqm.
- 841.94
- Say
- 841.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 237. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.