Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.21
- Analysis basis
- 10 Nos
- Priced inputs
- 14
- Derived rate
- ₹841.95/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.21 (Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers with water proof ply 12 mm thick) is derived from 14 priced inputs for 10 Nos and works out to ₹841.95 each after water charges, GST, CPOH and cess. The full build-up is below.
- span, 0.50 m deep 0.30 m wide and height
- 3.5 m from floor
- Cubical contents
- 10x6.60x0.5x0.3 = 9.9 cum
- Area=10x1x1.30x6.00 = 78 sqm
- Assuming shuttering will become unserviceable after use of 8 times
- @ 25% of cost of material
- Steel plates for side and bottom (plate size
- 1.20 x 0.50m)
- Angle 40x40x5mm (both sides) & bottom
- 2x(2x1.20) +(2x1.2) =7.20m
- 2x(3x0.50)+(3x0.30)=3.9m
- 11.10 m @ 3.00 kg/m =33.30 kg
- Weight of one plate = 33.30 kg.
- Total =34.97 kg.
- 10x5x34.97 = 1748.5 kg
- Qty taken for cost of using once =
- 1748.5x0.85/40 =37.2 kg
- Welding length 4800/40= 120 cm
- 10x1x1.30x6.00 = 78 sqm
- Total = 81.9 sqm
- Qty taken for cost of using once 81.9/8 sqm=
- 10.2 sqm
- Qty taken for cost of using once =
- 10x6x0.85/40 =1.275 m
- Qty taken for cost of using once =
- 10x5x0.85/40 = 1.063m
- Add maintenance charges @ 10% of cost of
- Less salvage value of material after full use
- Add for wastage =1.67kg.
- Total weight of all plates
- Add 5% wastage = 3.9 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.10.1 of SH:Steel WorkRate as per item 10.1 | kg | 37.2 | 117.35 | 4,365.42 | |
| 1215 | MAT | Welding by electric plant | cm | 120 | 2.50 | 300.00 |
| 8659 | MAT | Water proof ply 12mm thick.Water proof ply 12 mm thick | sqm | 10.2 | 578.00 | 5,895.60 |
| 0112 | LAB | Carpenter 2nd class | day | 1.25 | 816.00 | 1,020.00 |
| 0114 | LAB | Beldar | day | 1.25 | 736.00 | 920.00 |
| 1034 | MAT | Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in length | quintal | 0.021 | 5,200.00 | 109.20 |
| 7343 | MAT | Adjustable telescopic prop 3 m (2.02-3.75 m) | each | 1.275 | 1,051.00 | 1,340.03 |
| 7344 | MAT | Beam clamp 300-380 mm (450-1070 mm) | each set | 1.063 | 375.00 | 398.63 |
| 9999 | MAT | Assembly nut & bolts etc. | L.S. | 110.5 | 2.27 | 250.84 |
| 9977 | MAT | Carriage | L.S. | 780 | 2.27 | 1,770.60 |
| 0116 | LAB | Fitter (grade 1) | day | 12.5 | 897.00 | 11,212.50 |
| 0114 | LAB | Beldar | day | 25 | 736.00 | 18,400.00 |
| 9999 | MAT | Shuttering oil | L.S. | 390 | 2.27 | 885.30 |
| 9999 | MAT | Sundries, paper tape etc. | L.S. | 260 | 2.27 | 590.20 |
- TOTAL
- 47,458.32
- Add 1 % Water charges on “W-A”
- +430.93
- TOTAL
- 47,889.25
- Add GST on “X-A” (multiplying factor 0.2127)
- +9,257.52
- TOTAL
- 57,146.77
- Add 15% CPOH on “Y-A”
- +7,917.20
- TOTAL
- 65,063.97
- Add Cess @ 1% on “Z-A”
- +606.99
- Cost for 78 sqm.
- 65,670.96
- Cost per sqm.
- 841.94
- SAY
- ₹841.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 237
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 237. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.