CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Suspended floors, roofs, landings, balconies and access platform with water proof ply 12 mm thick

Item number
5.9.20
Analysis basis
Detail of cost for 10 Nos. room
Priced inputs
14
Derived rate
1,028.40 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.20 Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform with water proof ply 12 mm thick — is derived from 14 priced inputs for 10 Nos and works out to ₹1,028.40 each after water charges, GST, CPOH and cess. The full build-up is below.

  • 10x4.50x3.0 = 135 sqm, height 3.5 m
  • Adding for maintenance @ 10% of cost
  • Taking salvage value after full use of material
  • @ 25% of cost
  • Plates (size 0.75 m x 0.60 m)
  • Angle 40x40x5mm
  • 2x0.75 = 1.50 m
  • 2x0.60 = 1.20 m
  • = 2.70 m @ 3.00 kg/m = 8.1 kg
  • Weight of one plate = 8.10kg
  • Total = 8.51kg
  • Total weight of all plates =10x 5x6x8.51 =
  • 2553 kg.
  • Qty taken for cost using once.=
  • 2553x0.85/40 = 54.25 kg
  • Welding length = 10x(30x32)/40=240 cm
  • 10x1x4.50x3.00=135sqm
  • Qty taken for cost using once 141.8/8 =
  • 17.7sqm
  • Qty taken for cost using once = 10x5x0.85/40
  • = 1.063
  • Qty taken for cost using once = 10x6x0.85/40
  • = 1.275
  • Add for wastage @ 5% = 0.41 kg
  • Add wastage @ 5% =6.8sqm
  • Total 141.8sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.10.1 of SH:Steel WorkRate as per item 10.1Sub-analysiskg54.25117.356,366.24
1215Welding by electric plantMaterialcm2402.50600.00
8659Water proof ply 12mm thick.Water proof ply 12 mm thickMaterialsqm17.7578.0010,230.60
0112Carpenter 2nd classLabourday1.25816.001,020.00
0114BeldarLabourday1.25736.00920.00
1034Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterialquintal0.0215,200.00109.20
7342Adjustable span ESO+SI (2.35-3.40)Materialeach1.0631,540.001,637.02
7343Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach1.2751,051.001,340.03
9999Assembly nut & bolts etc.MaterialL.S.126.32.27286.70
9977CarriageMaterialL.S.1,3002.272,951.00
0116Fitter (grade 1)Labourday30897.0026,910.00
0114BeldarLabourday60736.0044,160.00
9999Shuttering oilMaterialL.S.7802.271,770.60
9999SundriesMaterialL.S.5202.271,180.40
TOTAL
99,481.79
Add 1 % Water charges on “W-A”
931.16
TOTAL
1,00,412.95
Add GST on “X-A” (multiplying factor 0.2127)
20,003.74
TOTAL
1,20,416.69
Add 15% CPOH on “Y-A”
17,107.57
TOTAL
1,37,524.26
Add Cess @ 1% on “Z-A”
1,311.58
Cost for 135 sqm.
1,38,835.84
Cost per sqm.
1,028.41
Say
1,028.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 235. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.