Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.18
- Analysis basis
- 10 bracket
- Priced inputs
- 6
- Derived rate
- ₹964.85/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.18 (Centering and shuttering including strutting, propping etc. and removal of form for Small surfaces such as cantilever ends, brackets and ends of steps, caps and bases to pilasters and columns and the like) is derived from 6 priced inputs for 10 bracket and works out to ₹964.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 1.20m projected
- Front area 0.50x0.60m
- End area 0.50x0.75m
- Area in contact with concrete
- 10x2x{(0.60+0.75)/2}x1.2 = 16.2 sqm.
- Front 10x0.5x0.6 = 3 sqm.
- Bottom 10x0.5x1.21 = 6.05 sqm.
- Total = 25.25 sqm.
- Assuming that the timber will become unserviceable after being used 8 times.
- Timber IInd class kail wood or equivalent
- local soft wood
- (I) Plank 30mm thick.
- Sides 10x2{(0.60+0.75)/2}x1.238 = 16.71sqm
- Battens 10x0.576x1.21 = 6.97
- Front 10x0.5x0.638 = 3.19
- Total = 26.87 sqm.
- Cubical contents
- 26.87x0.038 = 1.02 cum.
- Wastage @ 5% = 0.05 cum.
- Total = 1.07 cum.
- Qty taken for cost using once = 1070/8 =
- 133.75 cudm
- (ii) Battens-0.05x0.05m
- 10x2x1.238 = 24.76m
- 10x2x1.21 = 24.2m
- 10x2x0.688 = 13.76m
- 10x2x0.838 = 16.76m
- 10x3x0.5 = 15m
- Total = 94.48m
- Cubical contents
- 94.48x0.05x0.05 = 0.24 cum.
- Wastage 5% = 0.012 cum.
- Total = 0.252 cum = 252 cudm
- Qty taken for cost using once = 252/8 = 31.5
- cudm
- (iii) Ballies 125mm dia.
- 10x1x2.5 = 25m
- 10x1x2.65 = 26.5m
- Total = 51.5 m
- Wastage 5% = 2.6m
- Total = 54.1 m
- Qty taken for cost using once = 54.1/8=
- 6.763 m
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1198 | MAT | Second class kail wood in planks | cudm 10 | 13.375 | 260.00 | 3,477.50 |
| 1197 | MAT | Second class kail wood in scantling | cudm 10 | 3.15 | 260.00 | 819.00 |
| 2447 | MAT | Hollock ballies 125 mm diameter | metre | 6.763 | 37.00 | 250.23 |
| 0112 | LAB | Carpenter 2nd class | day | 8 | 816.00 | 6,528.00 |
| 0114 | LAB | Beldar | day | 8 | 736.00 | 5,888.00 |
| 9999 | MAT | Sundries | L.S. | 71.5 | 2.27 | 162.31 |
- TOTAL
- 17,125.04
- Add 1 % Water charges on “W”
- +171.25
- TOTAL
- 17,296.29
- Add GST on “X” (multiplying factor 0.2127)
- +3,678.92
- TOTAL
- 20,975.21
- Add 15% CPOH on “Y”
- +3,146.28
- TOTAL
- 24,121.49
- Add Cess @ 1% on “Z”
- +241.21
- Cost of 25.25 sqm.
- 24,362.70
- Cost of 1 sqm.
- 964.86
- SAY
- ₹964.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 233
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 233. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.