CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Small surfaces such as cantilever ends, brackets and ends of steps, caps and bases to pilasters and columns and the like

Item number
5.9.18
Analysis basis
Details of cost for 10 bracket
Priced inputs
6
Derived rate
964.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.18 Centering and shuttering including strutting, propping etc. and removal of form for Small surfaces such as cantilever ends, brackets and ends of steps, caps and bases to pilasters and columns and the like — is derived from 6 priced inputs for 10 bracket and works out to ₹964.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 1.20m projected
  • Front area 0.50x0.60m
  • End area 0.50x0.75m
  • Area in contact with concrete
  • 10x2x{(0.60+0.75)/2}x1.2 = 16.2 sqm.
  • Front 10x0.5x0.6 = 3 sqm.
  • Bottom 10x0.5x1.21 = 6.05 sqm.
  • Total = 25.25 sqm.
  • Assuming that the timber will become unserviceable after being used 8 times.
  • Timber IInd class kail wood or equivalent
  • local soft wood
  • (I) Plank 30mm thick.
  • Sides 10x2{(0.60+0.75)/2}x1.238 = 16.71sqm
  • Battens 10x0.576x1.21 = 6.97
  • Front 10x0.5x0.638 = 3.19
  • Total = 26.87 sqm.
  • Cubical contents
  • 26.87x0.038 = 1.02 cum.
  • Wastage @ 5% = 0.05 cum.
  • Total = 1.07 cum.
  • Qty taken for cost using once = 1070/8 =
  • 133.75 cudm
  • (ii) Battens-0.05x0.05m
  • 10x2x1.238 = 24.76m
  • 10x2x1.21 = 24.2m
  • 10x2x0.688 = 13.76m
  • 10x2x0.838 = 16.76m
  • 10x3x0.5 = 15m
  • Total = 94.48m
  • Cubical contents
  • 94.48x0.05x0.05 = 0.24 cum.
  • Wastage 5% = 0.012 cum.
  • Total = 0.252 cum = 252 cudm
  • Qty taken for cost using once = 252/8 = 31.5
  • cudm
  • (iii) Ballies 125mm dia.
  • 10x1x2.5 = 25m
  • 10x1x2.65 = 26.5m
  • Total = 51.5 m
  • Wastage 5% = 2.6m
  • Total = 54.1 m
  • Qty taken for cost using once = 54.1/8=
  • 6.763 m
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterialcudm 1013.375260.003,477.50
1197Second class kail wood in scantlingMaterialcudm 103.15260.00819.00
2447Hollock ballies 125 mm diameterMaterialmetre6.76337.00250.23
0112Carpenter 2nd classLabourday8816.006,528.00
0114BeldarLabourday8736.005,888.00
9999SundriesMaterialL.S.71.52.27162.31
TOTAL
17,125.04
Add 1 % Water charges on “W”
171.25
TOTAL
17,296.29
Add GST on “X” (multiplying factor 0.2127)
3,678.92
TOTAL
20,975.21
Add 15% CPOH on “Y”
3,146.28
TOTAL
24,121.49
Add Cess @ 1% on “Z”
241.21
Cost of 25.25 sqm.
24,362.70
Cost of 1 sqm.
964.86
Say
964.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 233. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.