Centering and shuttering including strutting, propping etc. and removal of form for

Small surfaces such as cantilever ends, brackets and ends of steps, caps and bases to pilasters and columns and the like
Item number
5.9.18
Analysis basis
10 bracket
Priced inputs
6
Derived rate
₹964.85/ SQM
D-01/RATE ANALYSISITEM 5.9.18

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.18 (Centering and shuttering including strutting, propping etc. and removal of form for Small surfaces such as cantilever ends, brackets and ends of steps, caps and bases to pilasters and columns and the like) is derived from 6 priced inputs for 10 bracket and works out to ₹964.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1.20m projected
  • Front area 0.50x0.60m
  • End area 0.50x0.75m
  • Area in contact with concrete
  • 10x2x{(0.60+0.75)/2}x1.2 = 16.2 sqm.
  • Front 10x0.5x0.6 = 3 sqm.
  • Bottom 10x0.5x1.21 = 6.05 sqm.
  • Total = 25.25 sqm.
  • Assuming that the timber will become unserviceable after being used 8 times.
  • Timber IInd class kail wood or equivalent
  • local soft wood
  • (I) Plank 30mm thick.
  • Sides 10x2{(0.60+0.75)/2}x1.238 = 16.71sqm
  • Battens 10x0.576x1.21 = 6.97
  • Front 10x0.5x0.638 = 3.19
  • Total = 26.87 sqm.
  • Cubical contents
  • 26.87x0.038 = 1.02 cum.
  • Wastage @ 5% = 0.05 cum.
  • Total = 1.07 cum.
  • Qty taken for cost using once = 1070/8 =
  • 133.75 cudm
  • (ii) Battens-0.05x0.05m
  • 10x2x1.238 = 24.76m
  • 10x2x1.21 = 24.2m
  • 10x2x0.688 = 13.76m
  • 10x2x0.838 = 16.76m
  • 10x3x0.5 = 15m
  • Total = 94.48m
  • Cubical contents
  • 94.48x0.05x0.05 = 0.24 cum.
  • Wastage 5% = 0.012 cum.
  • Total = 0.252 cum = 252 cudm
  • Qty taken for cost using once = 252/8 = 31.5
  • cudm
  • (iii) Ballies 125mm dia.
  • 10x1x2.5 = 25m
  • 10x1x2.65 = 26.5m
  • Total = 51.5 m
  • Wastage 5% = 2.6m
  • Total = 54.1 m
  • Qty taken for cost using once = 54.1/8=
  • 6.763 m
ANALYSIS OF RATES · ITEM 5.9.18DETAILS OF COST FOR 10 BRACKET
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1198MATSecond class kail wood in plankscudm 1013.375260.003,477.50
1197MATSecond class kail wood in scantlingcudm 103.15260.00819.00
2447MATHollock ballies 125 mm diametermetre6.76337.00250.23
0112LABCarpenter 2nd classday8816.006,528.00
0114LABBeldarday8736.005,888.00
9999MATSundriesL.S.71.52.27162.31
BUILD-UP TO RATE
TOTAL
17,125.04
Add 1 % Water charges on “W”
+171.25
TOTAL
17,296.29
Add GST on “X” (multiplying factor 0.2127)
+3,678.92
TOTAL
20,975.21
Add 15% CPOH on “Y”
+3,146.28
TOTAL
24,121.49
Add Cess @ 1% on “Z”
+241.21
Cost of 25.25 sqm.
24,362.70
Cost of 1 sqm.
964.86
SAY
₹964.85
D-02/SOURCEPRINTED PAGE 233
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
233

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 233. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.