Centering and shuttering including strutting, propping etc. and removal of form for
- Item number
- 5.9.17
- Analysis basis
- 10m long
- Priced inputs
- 6
- Derived rate
- ₹856.80/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.17 (Centering and shuttering including strutting, propping etc. and removal of form for Cornices and mouldings) is derived from 6 priced inputs for 10m long and works out to ₹856.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- projection, 20cm depth and 40cm girth
- Area in contact 10x0.4 = 4.0 sqm.
- Assuming that the timber will become unserviceable after being used 8 times.
- (I) Planking 30mm thick = 4sqm.
- Extra & Wastage 20% = 0.8 sqm.
- Total = 4.8 sqm.
- 4.8x0.038 = 0.182 cum = 182 cudm
- Qty taken for cost using once = 182/8 =
- 22.75 cudm
- (ii) Battens-Joining to Planking
- 1x10x0.1x0.075 = 0.075 cum.
- From bottom shuttering
- 10x1.5x0.1x0.075 = 0.113 cum.
- Wales
- 10x0.4mx0.1x0.075 = 0.030 cum.
- Total = 0.218 cum = 218 cudm
- Qty taken for cost using once = 218/8 =
- 27.25 cudm
- (iii) Ballies 125 mm dia.
- Slant 10x0.3 = 3 m
- ver. 6x3.5 = 21.0 m
- Total= 24.0 m
- Wastage @ 5% = 1.2 m
- Total= 25.2 m
- Qty taken for cost using once = 25.2/8 =
- 3.15m
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1198 | MAT | Second class kail wood in planks | cudm 10 | 2.275 | 260.00 | 591.50 |
| 1197 | MAT | Second class kail wood in scantling | cudm 10 | 2.725 | 260.00 | 708.50 |
| 2447 | MAT | Hollock ballies 125 mm diameter | metre | 3.15 | 37.00 | 116.55 |
| 0112 | LAB | Carpenter 2nd class | day | 0.63 | 816.00 | 514.08 |
| 0114 | LAB | Beldar | day | 0.63 | 736.00 | 463.68 |
| 9999 | MAT | Sundries | L.S. | 6.5 | 2.27 | 14.76 |
- TOTAL
- 2,409.07
- Add 1 % Water charges on “W”
- +24.09
- TOTAL
- 2,433.16
- Add GST on “X” (multiplying factor 0.2127)
- +517.53
- TOTAL
- 2,950.69
- Add 15% CPOH on “Y”
- +442.60
- TOTAL
- 3,393.29
- Add Cess @ 1% on “Z”
- +33.93
- Cost of 4 sqm.
- 3,427.22
- Cost of 1 sqm.
- 856.81
- SAY
- ₹856.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 232
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 232. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.