Centering and shuttering including strutting, propping etc. and removal of form for

Cornices and mouldings
Item number
5.9.17
Analysis basis
10m long
Priced inputs
6
Derived rate
₹856.80/ SQM
D-01/RATE ANALYSISITEM 5.9.17

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.17 (Centering and shuttering including strutting, propping etc. and removal of form for Cornices and mouldings) is derived from 6 priced inputs for 10m long and works out to ₹856.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • projection, 20cm depth and 40cm girth
  • Area in contact 10x0.4 = 4.0 sqm.
  • Assuming that the timber will become unserviceable after being used 8 times.
  • (I) Planking 30mm thick = 4sqm.
  • Extra & Wastage 20% = 0.8 sqm.
  • Total = 4.8 sqm.
  • 4.8x0.038 = 0.182 cum = 182 cudm
  • Qty taken for cost using once = 182/8 =
  • 22.75 cudm
  • (ii) Battens-Joining to Planking
  • 1x10x0.1x0.075 = 0.075 cum.
  • From bottom shuttering
  • 10x1.5x0.1x0.075 = 0.113 cum.
  • Wales
  • 10x0.4mx0.1x0.075 = 0.030 cum.
  • Total = 0.218 cum = 218 cudm
  • Qty taken for cost using once = 218/8 =
  • 27.25 cudm
  • (iii) Ballies 125 mm dia.
  • Slant 10x0.3 = 3 m
  • ver. 6x3.5 = 21.0 m
  • Total= 24.0 m
  • Wastage @ 5% = 1.2 m
  • Total= 25.2 m
  • Qty taken for cost using once = 25.2/8 =
  • 3.15m
ANALYSIS OF RATES · ITEM 5.9.17DETAILS OF COST FOR 10M LONG MOULDING 10CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1198MATSecond class kail wood in plankscudm 102.275260.00591.50
1197MATSecond class kail wood in scantlingcudm 102.725260.00708.50
2447MATHollock ballies 125 mm diametermetre3.1537.00116.55
0112LABCarpenter 2nd classday0.63816.00514.08
0114LABBeldarday0.63736.00463.68
9999MATSundriesL.S.6.52.2714.76
BUILD-UP TO RATE
TOTAL
2,409.07
Add 1 % Water charges on “W”
+24.09
TOTAL
2,433.16
Add GST on “X” (multiplying factor 0.2127)
+517.53
TOTAL
2,950.69
Add 15% CPOH on “Y”
+442.60
TOTAL
3,393.29
Add Cess @ 1% on “Z”
+33.93
Cost of 4 sqm.
3,427.22
Cost of 1 sqm.
856.81
SAY
₹856.80
D-02/SOURCEPRINTED PAGE 232
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
232

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 232. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.