CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for
Cornices and mouldings
- Item number
- 5.9.17
- Analysis basis
- Details of cost for 10m long moulding 10cm
- Priced inputs
- 6
- Derived rate
- ₹856.80 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.17 — Centering and shuttering including strutting, propping etc. and removal of form for Cornices and mouldings — is derived from 6 priced inputs for 10m long and works out to ₹856.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- projection, 20cm depth and 40cm girth
- Area in contact 10x0.4 = 4.0 sqm.
- Assuming that the timber will become unserviceable after being used 8 times.
- (I) Planking 30mm thick = 4sqm.
- Extra & Wastage 20% = 0.8 sqm.
- Total = 4.8 sqm.
- 4.8x0.038 = 0.182 cum = 182 cudm
- Qty taken for cost using once = 182/8 =
- 22.75 cudm
- (ii) Battens-Joining to Planking
- 1x10x0.1x0.075 = 0.075 cum.
- From bottom shuttering
- 10x1.5x0.1x0.075 = 0.113 cum.
- Wales
- 10x0.4mx0.1x0.075 = 0.030 cum.
- Total = 0.218 cum = 218 cudm
- Qty taken for cost using once = 218/8 =
- 27.25 cudm
- (iii) Ballies 125 mm dia.
- Slant 10x0.3 = 3 m
- ver. 6x3.5 = 21.0 m
- Total= 24.0 m
- Wastage @ 5% = 1.2 m
- Total= 25.2 m
- Qty taken for cost using once = 25.2/8 =
- 3.15m
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1198 | Second class kail wood in planksMaterial | cudm 10 | 2.275 | 260.00 | 591.50 |
| 1197 | Second class kail wood in scantlingMaterial | cudm 10 | 2.725 | 260.00 | 708.50 |
| 2447 | Hollock ballies 125 mm diameterMaterial | metre | 3.15 | 37.00 | 116.55 |
| 0112 | Carpenter 2nd classLabour | day | 0.63 | 816.00 | 514.08 |
| 0114 | BeldarLabour | day | 0.63 | 736.00 | 463.68 |
| 9999 | SundriesMaterial | L.S. | 6.5 | 2.27 | 14.76 |
- TOTAL
- 2,409.07
- Add 1 % Water charges on “W”
- 24.09
- TOTAL
- 2,433.16
- Add GST on “X” (multiplying factor 0.2127)
- 517.53
- TOTAL
- 2,950.69
- Add 15% CPOH on “Y”
- 442.60
- TOTAL
- 3,393.29
- Add Cess @ 1% on “Z”
- 33.93
- Cost of 4 sqm.
- 3,427.22
- Cost of 1 sqm.
- 856.81
- Say
- 856.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 232. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works