Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls

Above 20 cm wide

Item number
5.9.16.2
Analysis basis
Details of cost for 10Nos of size 4mx4m slab
Priced inputs
5
Derived rate
879.05 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.16.2 Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Above 20 cm wide — is derived from 5 priced inputs for 10Nos of and works out to ₹879.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 25cm thick
  • 16 metre edge length
  • Shuttering surface area = 10x16 x 0.25 = 40
  • sqm
  • (i) Planks 38mm thick
  • 10x4x4x0.25x0.038 = 1.52
  • Wastage @ 5% = 0.08
  • Total = 1.60 cum. = 1600 cudm
  • Qty taken for cost of using once = 1600/8 =
  • 200 cudm
  • (ii) Battens
  • 10x6x2x0.6x0.075x0.100=0.54
  • 10x5x2x1.5x0.075x0.100=1.13
  • Total = 1.67
  • Wastage @ 5% = 0.08
  • Total= 1.75 cum. = 1750 cudm
  • Qty taken for cost of using once = 1750/8 =
  • 218.8 cudm
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterialcudm 1020260.005,200.00
1197Second class kail wood in scantlingMaterialcudm 1021.88260.005,688.80
0112Carpenter 2nd classLabourday10816.008,160.00
0114BeldarLabourday7.5736.005,520.00
9999SundriesMaterialL.S.652.27147.55
TOTAL
24,716.35
Add 1 % Water charges on “W”
247.16
TOTAL
24,963.51
Add GST on “X” (multiplying factor 0.2127)
5,309.74
TOTAL
30,273.25
Add 15% CPOH on “Y”
4,540.99
TOTAL
34,814.24
Add Cess @ 1% on “Z”
348.14
Cost of 40 sqm.
35,162.38
Cost of 1 sqm.
879.06
Say
879.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 231. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works