CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls
Under 20 cm wide
- Item number
- 5.9.16.1
- Analysis basis
- Details of cost for 10Nos of 3mx3m slab
- Priced inputs
- 5
- Derived rate
- ₹208.55 / Nos of
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.16.1 — Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Under 20 cm wide — is derived from 5 priced inputs for 10Nos of and works out to ₹208.55 per nos of after water charges, GST, CPOH and cess. The full build-up is below.
- 15cms thick
- 120 m edge Length
- Assuming that the timber will become unserviceable after being used 8 times.
- (i) Planks 30mm thick (2nd class Kail wood
- or equivalent local soft wood)
- 10x4x3x0.15x0.030=0.54 cum
- Wastage @5% = 0.03 cum.
- Total = 0.57 cum 570 cudm
- Qty taken for cost of using once = 570/8
- =71.25 cudm
- (ii) Battens 75mmx100mm (2nd class Kail
- wood)
- Horizontal 10x2x4x0.075x0.1x0.5=0.30
- Horizontal 10x2x4x0.075x0.1x1.5=0.90
- (iii) Vertical battens
- 10x16x0.15x0.075x0.030m = 0.054
- (iv) Struts
- 10x16x0.25x0.075x0.075=0.225
- Total = 1.479
- Wastage @5% = 0.074
- Total = 1.553 cum = 1550 cudm say
- Qty taken for cost ef using once = 1550/8
- =193.75 cudm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1198 | Second class kail wood in planksMaterial | cudm 10 | 7.125 | 260.00 | 1,852.50 |
| 1197 | Second class kail wood in scantlingMaterial | cudm 10 | 19.375 | 260.00 | 5,037.50 |
| 0112 | Carpenter 2nd classLabour | day | 8.1 | 816.00 | 6,609.60 |
| 0114 | BeldarLabour | day | 5.4 | 736.00 | 3,974.40 |
| 9999 | SundriesMaterial | L.S. | 52 | 2.27 | 118.04 |
- TOTAL
- 17,592.04
- Add 1 % Water charges on “W”
- 175.92
- TOTAL
- 17,767.96
- Add GST on “X” (multiplying factor 0.2127)
- 3,779.25
- TOTAL
- 21,547.21
- Add 15% CPOH on “Y”
- 3,232.08
- TOTAL
- 24,779.29
- Add Cess @ 1% on “Z”
- 247.79
- Cost of 120 metre
- 25,027.08
- Cost of one metre
- 208.56
- Say
- 208.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 230. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works