Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls

Under 20 cm wide

Item number
5.9.16.1
Analysis basis
Details of cost for 10Nos of 3mx3m slab
Priced inputs
5
Derived rate
208.55 / Nos of

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.16.1 Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Under 20 cm wide — is derived from 5 priced inputs for 10Nos of and works out to ₹208.55 per nos of after water charges, GST, CPOH and cess. The full build-up is below.

  • 15cms thick
  • 120 m edge Length
  • Assuming that the timber will become unserviceable after being used 8 times.
  • (i) Planks 30mm thick (2nd class Kail wood
  • or equivalent local soft wood)
  • 10x4x3x0.15x0.030=0.54 cum
  • Wastage @5% = 0.03 cum.
  • Total = 0.57 cum 570 cudm
  • Qty taken for cost of using once = 570/8
  • =71.25 cudm
  • (ii) Battens 75mmx100mm (2nd class Kail
  • wood)
  • Horizontal 10x2x4x0.075x0.1x0.5=0.30
  • Horizontal 10x2x4x0.075x0.1x1.5=0.90
  • (iii) Vertical battens
  • 10x16x0.15x0.075x0.030m = 0.054
  • (iv) Struts
  • 10x16x0.25x0.075x0.075=0.225
  • Total = 1.479
  • Wastage @5% = 0.074
  • Total = 1.553 cum = 1550 cudm say
  • Qty taken for cost ef using once = 1550/8
  • =193.75 cudm
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterialcudm 107.125260.001,852.50
1197Second class kail wood in scantlingMaterialcudm 1019.375260.005,037.50
0112Carpenter 2nd classLabourday8.1816.006,609.60
0114BeldarLabourday5.4736.003,974.40
9999SundriesMaterialL.S.522.27118.04
TOTAL
17,592.04
Add 1 % Water charges on “W”
175.92
TOTAL
17,767.96
Add GST on “X” (multiplying factor 0.2127)
3,779.25
TOTAL
21,547.21
Add 15% CPOH on “Y”
3,232.08
TOTAL
24,779.29
Add Cess @ 1% on “Z”
247.79
Cost of 120 metre
25,027.08
Cost of one metre
208.56
Say
208.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 230. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works