CPWD Analysis of Rates · Reinforced Cement Concrete

Centering and shuttering including strutting, propping etc. and removal of form for

Small lintels not exceeding 1.5 m clear span, moulding as in cornices, window sills, string courses, bands, copings, bed plates, anchor blocks and the like

Item number
5.9.15
Analysis basis
Details of cost for lintel size 1.80m x 0.20m x
Priced inputs
1
Derived rate
392.15 / lintel size

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.15 Centering and shuttering including strutting, propping etc. and removal of form for Small lintels not exceeding 1.5 m clear span, moulding as in cornices, window sills, string courses, bands, copings, bed plates, anchor blocks and the like — is derived from 1 priced inputs for lintel size and works out to ₹392.15 per lintel size after water charges, GST, CPOH and cess. The full build-up is below.

  • 0.15m (Clear span 1.50 m) Area 0.84 sqm
  • Sides = 2 x 1.80 x 0.15 = 0.54
  • Bottom = 1 x 1.50 x 0.20 = 0.30
  • Total Contact Area = 0.84 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No. 5.9.1 of SH:Reinforced Concrete workRate as per item 5.9.1Sub-analysissqm0.84392.15329.41
Cost for 0.84 sqm.
329.41
Cost per sqm.
392.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 230. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works