Centering and shuttering including strutting, propping etc. and removal of form for

Vertical and horizontal fins individually or forming box louvers band, facias and eaves boards
Item number
5.9.13
Analysis basis
10Nos. Boxes
Priced inputs
6
Derived rate
₹1,296.70/ NOS. BOXES
D-01/RATE ANALYSISITEM 5.9.13

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.13 (Centering and shuttering including strutting, propping etc. and removal of form for Vertical and horizontal fins individually or forming box louvers band, facias and eaves boards) is derived from 6 priced inputs for 10Nos. Boxes and works out to ₹1,296.70 per nos. boxes after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • tical fins 4 metre high and at 1 metre centres,
  • with two horizontal fins all projecting 60cm
  • from face of wall and 5 cm thick.
  • i.e. 10x[(4x4.00x1.25) + (2x3.00x0.65)] =
  • 239sqm + 5% wastage = 251 sqm.
  • 38mm thick10x4x4x1.25=200
  • 10x2x3x0.65 =39
  • Total = 239
  • Wastage @ 5% = 12
  • Total = 251sqm.
  • 251x0.038=9.54 cum or 9540 cudm
  • Qty for cost using once = 9540/8 = 1192.5
  • cudm
  • 10x4x2x5x0.60x0.075x0.050=0.90
  • 10x3x2x5x1.00x0.075x0.050=1.12
  • 10x2x6x0.60x0.075x0.100=0.54 = 2.56 Cum.
  • Wastage @ 5% =0.13 cum
  • Total = 2.69 cum= 2690 cudm
  • Qty for cost using once = 2690/8 = 336.25
  • cudm
  • 10x2x2x6x4.00 =960m
  • Wastage @5% = 48m
  • Total= 1008 m
  • Qty for cost using once = 1008/8 = 126 m
ANALYSIS OF RATES · ITEM 5.9.13DETAILS OF COST FOR 10NOS. BOXES OF FINS 4 VER-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1198MATSecond class kail wood in plankscudm 10119.25260.0031,005.00
1197MATSecond class kail wood in scantlingcudm 1033.625260.008,742.50
0302MATSafeda ballies 125 mm diametermetre12644.005,544.00
0112LABCarpenter 2nd classday110816.0089,760.00
0114LABBeldarday110736.0080,960.00
9999MATSundriesL.S.807.32.271,832.57
BUILD-UP TO RATE
TOTAL
2,17,844.07
Add 1 % Water charges on “W”
+2,178.44
TOTAL
2,20,022.51
Add GST on “X” (multiplying factor 0.2127)
+46,798.79
TOTAL
2,66,821.30
Add 15% CPOH on “Y”
+40,023.20
TOTAL
3,06,844.50
Add Cess @ 1% on “Z”
+3,068.45
Cost for 239 sqm.
3,09,912.95
Cost per sqm.
1,296.71
SAY
₹1,296.70
D-02/SOURCEPRINTED PAGE 229
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
229

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 229. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.