CPWD Analysis of Rates · Reinforced Cement Concrete
Centering and shuttering including strutting, propping etc. and removal of form for
Well steining
- Item number
- 5.9.12
- Analysis basis
- Details of cost 26.39 sqm.
- Priced inputs
- 3
- Derived rate
- ₹263.65
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.9.12 — Centering and shuttering including strutting, propping etc. and removal of form for Well steining — is derived from 3 priced inputs and works out to ₹263.65 after water charges, GST, CPOH and cess. The full build-up is below.
- Surface area
- Outside area = 26.39 sqm
- Assuming that the timber will become unserviceable after being used 8 times
- Planks 38 mm (Second class kail wood)
- 26.39x0.038 = 1.00cum.
- Wastage 20% = 0.20cum.
- Total = 1.20cum. or 1200 cudm.
- Qty for cost using once = 1200/8=150 cudm
- 2nd class kail wood battens
- Inside = 2x25x0.50x0.075x0.038 =
- 0.0712cum.
- Outside = 2x28x0.50x0.075x0.038 =
- 0.0798cum.
- Total = 0.1510cum.
- Wastage 5% = 0.0076 cum.
- Total = 0.1586 cum = 158.60 cudm
- Qty for cost using once = 0.1586/8= 0.02
- cudm
- Inside: 25x1.00 = 25.00m
- Outside: 28x1.00 = 28.00m
- Total = 53.00m
- Qty for cost using once = 53/8 =6.625 m
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1198 | Second class kail wood in planksMaterial | cudm | 15 | 260.00 | 3,900.00 |
| 1197 | Second class kail wood in scantlingMaterial | cudm | 0.002 | 260.00 | 0.52 |
| 0302 | Safeda ballies 125 mm diameterMaterial | metre | 6.625 | 44.00 | 291.50 |
- TOTAL
- 4,192.02
- Add for carriage, labour for erection and dis- mentalig etc @ 1/6 of cost of material i.e.M
- 698.68
- TOTAL
- 4,890.70
- Add 1 % Water charges on “W”
- 48.91
- TOTAL
- 4,939.61
- Add GST on “X” (multiplying factor 0.2127)
- 1,050.66
- TOTAL
- 5,990.27
- Add 15% CPOH on “Y”
- 898.54
- TOTAL
- 6,888.81
- Add Cess @ 1% on “Z”
- 68.89
- Cost for 26.39sqm.
- 6,957.70
- Cost per sqm.
- 263.65
- Say
- 263.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 228. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.