Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.5A
- Analysis basis
- 26.73cum for
- Priced inputs
- 18
- Derived rate
- ₹12,035.00/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.5A (Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 18 priced inputs for 26.73cum for and works out to ₹12,035.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- lar arch 6m clear span and 9m long and
- 30cm thick. Cement concrete 1:1 :3 =
- 1x0.50x3.14x6.30x 9.00x0.30 = 26.73cum
- MATERIAL: ½
- Extra for laying CC over curved surfaces
- (Extra labour for lifting material upto floor V
- level : Coolie = 0.75 x 2.0 x 26.73 = 40.10)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal size | cum | 12.189 | 1,425.00 | 17,369.33 |
| 0279 | MAT | Recycled Concrete Aggregate (RCA) 20 mm nominal size | cum | 3.047 | 957.00 | 2,915.98 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal size | cum | 5.987 | 1,400.00 | 8,381.80 |
| 0281 | MAT | Recycled Concrete Aggregate (RCA) 10 mm nominal size | cum | 1.497 | 957.00 | 1,432.63 |
| 0982 | MAT | Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III) | cum | 9.088 | 1,450.00 | 13,177.60 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 2.272 | 957.00 | 2,174.30 |
| 0367 | MAT | Portland Cement (0.2833 cum)Portland Cement (OPC-43 Grade) | tonne | 10.692 | 5,156.00 | 55,127.95 |
| 0155 | LAB | Mason (average) | day | 6.42 | 857.00 | 5,501.94 |
| 0114 | LAB | Beldar | day | 73.51 | 736.00 | 54,103.36 |
| 0101 | LAB | Bhisti | day | 24.06 | 816.00 | 19,632.96 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 2.14 | 900.00 | 1,926.00 |
| 0012 | MACH | Vibrator (Needle type 40 mm) | day | 2.14 | 400.00 | 856.00 |
| 9999 | MAT | Sundries | L.S. | 401.89 | 2.27 | 912.29 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 5 | 897.00 | 4,485.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 5 | 816.00 | 4,080.00 |
| 0101 | LAB | Bhisti | day | 1.5 | 816.00 | 1,224.00 |
| 0115 | LAB | Coolie | day | 4.5 | 736.00 | 3,312.00 |
| 0115 | LAB | Coolie | day | 40.1 | 736.00 | 29,513.60 |
- Total
- 2,26,126.74
- Add 1 % Water charges on “W”
- +2,261.27
- TOTAL
- 2,28,388.01
- Add GST on “X” (multiplying factor 0.2127)
- +48,578.13
- TOTAL
- 2,76,966.14
- Add 15% CPOH on “Y”
- +41,544.92
- TOTAL
- 3,18,511.06
- Add Cess @ 1% on “Z”
- +3,185.11
- Cost of 26.73 cum
- 3,21,696.17
- Cost of 1 cum
- 12,035.02
- SAY
- ₹12,035.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 213
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 213. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.