Skip to main content

Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.5
Analysis basis
Details of cost for 26.73cum
Priced inputs
15
Derived rate
₹12,205.85
D-01/RATE ANALYSISITEM 5.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.5 (Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 15 priced inputs and works out to ₹12,205.85 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • for semicircular arch 6m clear span and 9m
  • long and 30cm thick.
  • Cement concrete 1:1.5:3 =
  • 1x0.50x3.14x6.30x9.00x0.30 = 26.73cum
  • Extra for laying CC over curved surfaces
  • (Extra labour for lifting material upto floor V
  • level :
  • Coolie = 0.75 x 2.0 x 26.73 = 40.10)
ANALYSIS OF RATES · ITEM 5.5DETAILS OF COST FOR 26.73CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum15.2361,425.0021,711.30
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum7.4841,400.0010,477.60
0982MATCoarse sand (zone III)cum11.361,450.0016,472.00
0367MATPortland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)tonne10.6925,156.0055,127.95
0155LABMason (average)day6.42857.005,501.94
0114LABBeldarday73.51736.0054,103.36
0101LABBhistiday24.06816.0019,632.96
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday2.14900.001,926.00
0012MACHVibrator(Needle type 40mm)Vibrator (Needle type 40 mm)day2.14400.00856.00
9999MATSundriesL.S.401.892.27912.29
0123LABMason 1st classMason 1st classday5897.004,485.00
0124LABMason 2nd classMason 2nd classday5816.004,080.00
0101LABBhistiday1.5816.001,224.00
0115LABCoolieday4.5736.003,312.00
0115LABCoolieday40.1736.0029,513.60
BUILD-UP TO RATE
TOTAL
2,29,336.00
Add 1 % Water charges on “W”
+2,293.36
TOTAL
2,31,629.36
Add GST on “X” (multiplying factor 0.2127)
+49,267.56
TOTAL
2,80,896.92
Add 15% CPOH on “Y”
+42,134.54
TOTAL
3,23,031.46
Add Cess @ 1% on “Z”
+3,230.31
Cost for 26.73 cum.
3,26,261.77
Cost for 1 cum.
12,205.83
SAY
₹12,205.85
D-02/SOURCEPRINTED PAGE 212
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
212

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 212. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.