CPWD Analysis of Rates · Reinforced Cement Concrete

Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.5
Analysis basis
Details of cost for 26.73cum
Priced inputs
15
Derived rate
12,205.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.5 Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 15 priced inputs and works out to ₹12,205.85 after water charges, GST, CPOH and cess. The full build-up is below.

  • for semicircular arch 6m clear span and 9m
  • long and 30cm thick.
  • Cement concrete 1:1.5:3 =
  • 1x0.50x3.14x6.30x9.00x0.30 = 26.73cum
  • Extra for laying CC over curved surfaces
  • (Extra labour for lifting material upto floor V
  • level :
  • Coolie = 0.75 x 2.0 x 26.73 = 40.10)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum15.2361,425.0021,711.30
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum7.4841,400.0010,477.60
0982Coarse sand (zone III)Materialcum11.361,450.0016,472.00
0367Portland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)Materialtonne10.6925,156.0055,127.95
0155Mason (average)Labourday6.42857.005,501.94
0114BeldarLabourday73.51736.0054,103.36
0101BhistiLabourday24.06816.0019,632.96
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday2.14900.001,926.00
0012Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machineryday2.14400.00856.00
9999SundriesMaterialL.S.401.892.27912.29
0123Mason 1st classMason 1st classLabourday5897.004,485.00
0124Mason 2nd classMason 2nd classLabourday5816.004,080.00
0101BhistiLabourday1.5816.001,224.00
0115CoolieLabourday4.5736.003,312.00
0115CoolieLabourday40.1736.0029,513.60
TOTAL
2,29,336.00
Add 1 % Water charges on “W”
2,293.36
TOTAL
2,31,629.36
Add GST on “X” (multiplying factor 0.2127)
49,267.56
TOTAL
2,80,896.92
Add 15% CPOH on “Y”
42,134.54
TOTAL
3,23,031.46
Add Cess @ 1% on “Z”
3,230.31
Cost for 26.73 cum.
3,26,261.77
Cost for 1 cum.
12,205.83
Say
12,205.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 212. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.