Annexure for items 5.48.2 for using M 60 grade Self Compacting Reinforced cement concrete data for 120.00 cum

Item number
5.48Y
Analysis basis
Detail of cost for each
Priced inputs
14
Derived rate
₹7,12,947.65
D-01/RATE ANALYSISITEM 5.48Y

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48Y (Annexure for items 5.48.2 for using M 60 grade Self Compacting Reinforced cement concrete data for 120.00 cum) is derived from 14 priced inputs and works out to ₹7,12,947.65 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Sub Analysis for use in Item no 5.48.2
  • RCC Grade M60
  • Unit = 1 cum
  • Taking output = 120 cum
  • MATERIALS :
  • LABOUR :
  • MACHINERY :
  • Distance = 10 km
  • Qty= 120.00 cum
  • Total = 120.00x 10= 1200
ANALYSIS OF RATES · ITEM 5.48YDETAIL OF COST FOR EACH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne57.65,156.002,96,985.60
0982MATCoarse sand (zone III)cum54.981,450.0079,721.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum57.541,425.0081,994.50
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum38.221,400.0053,508.00
7318MATPlasticizer / super plasticizergram230.430.006,912.00
8953MATMicro Silicakg3,60025.0090,000.00
0128LABMateday0.94816.00767.04
0123LABMason 1st classMason 1st classday3.5897.003,139.50
0114LABBeldarday20736.0014,720.00
0066MACHBatching and Mixing PlantT@ 75 cum per hourBatching and Mixing Plant @ 75 cum per hour1.62,700.004,320.00
0070MACHGenerator 100 KVA/125 KVAhour1.6350.00560.00
0052MACHFront end loader 1 cum bucket capacity (incl POL)hour1.61,450.002,320.00
0029MACHCarriage of concrete by transit mixerCarriage of ready mixed concrete by rotatory transit mixercum km/1,20040.0048,000.00
0009MACHPumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.cum120250.0030,000.00
BUILD-UP TO RATE
TOTAL
7,12,947.64
Cost of each.
7,12,947.64
SAY
₹7,12,947.65
D-02/SOURCEPRINTED PAGE 299
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
299

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 299. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.