Annexure for item 5.48.1, Providing M50 grade Reinforced Cement Concrete data for 120.00 cum

Item number
5.48X
Analysis basis
each lot
Priced inputs
13
Derived rate
₹6,38,628.15/ EACH LOT
D-01/RATE ANALYSISITEM 5.48X

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48X (Annexure for item 5.48.1, Providing M50 grade Reinforced Cement Concrete data for 120.00 cum) is derived from 13 priced inputs for each lot and works out to ₹6,38,628.15 per each lot after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Sub Analysis for use in Item no 5.48.1
  • RCC Grade M50
  • Unit = 1 cum
  • Taking output = 120 cum
  • MATERIALS :
  • LABOUR :
  • MACHINERY :
  • Distance = 10 km
  • Qty= 120.00 cum
  • Total = 120.00x 10= 1200
ANALYSIS OF RATES · ITEM 5.48XDETAILS OF COST FOR EACH LOT OF 120 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne57.65,156.002,96,985.60
0982MATCoarse sand (zone III)cum541,450.0078,300.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum64.81,425.0092,340.00
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum43.21,400.0060,480.00
7318MATPlasticizer / super plasticizergram223.230.006,696.00
0128LABMateday0.94816.00767.04
0123LABMason 1st classMason 1st classday3.5897.003,139.50
0114LABBeldarday20736.0014,720.00
0066MACHBatching and Mixing Plant @ 75 cum per hourhour1.62,700.004,320.00
0070MACHGenerator 100 KVA/125 KVAhour1.6350.00560.00
0052MACHFront end loader 1 cum bucket capacity (incl POL)hour1.61,450.002,320.00
0029MACHCarriage of concrete by transit mixerCarriage of ready mixed concrete by rotatory transit mixercum km/1,20040.0048,000.00
0009MACHPumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.cum120250.0030,000.00
BUILD-UP TO RATE
TOTAL
6,38,628.14
Cost of each lot of 120 cum.
6,38,628.14
SAY
₹6,38,628.15
D-02/SOURCEPRINTED PAGE 299
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
299

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 299. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.