CPWD Analysis of Rates · Reinforced Cement Concrete
Annexure for item 5.48.1, Providing M50 grade Reinforced Cement Concrete data for 120.00 cum
- Item number
- 5.48X
- Analysis basis
- Details of cost for each lot of 120 cum.
- Priced inputs
- 13
- Derived rate
- ₹6,38,628.15 / each lot
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48X — Annexure for item 5.48.1, Providing M50 grade Reinforced Cement Concrete data for 120.00 cum — is derived from 13 priced inputs for each lot and works out to ₹6,38,628.15 per each lot after water charges, GST, CPOH and cess. The full build-up is below.
- Sub Analysis for use in Item no 5.48.1
- RCC Grade M50
- Unit = 1 cum
- Taking output = 120 cum
- MATERIALS :
- LABOUR :
- MACHINERY :
- Distance = 10 km
- Qty= 120.00 cum
- Total = 120.00x 10= 1200
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 57.6 | 5,156.00 | 2,96,985.60 |
| 0982 | Coarse sand (zone III)Material | cum | 54 | 1,450.00 | 78,300.00 |
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 64.8 | 1,425.00 | 92,340.00 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 43.2 | 1,400.00 | 60,480.00 |
| 7318 | Plasticizer / super plasticizerMaterial | gram | 223.2 | 30.00 | 6,696.00 |
| 0128 | MateLabour | day | 0.94 | 816.00 | 767.04 |
| 0123 | Mason 1st classMason 1st classLabour | day | 3.5 | 897.00 | 3,139.50 |
| 0114 | BeldarLabour | day | 20 | 736.00 | 14,720.00 |
| 0066 | Batching and Mixing Plant @ 75 cum per hourMachinery | hour | 1.6 | 2,700.00 | 4,320.00 |
| 0070 | Generator 100 KVA/125 KVAMachinery | hour | 1.6 | 350.00 | 560.00 |
| 0052 | Front end loader 1 cum bucket capacity (incl POL)Machinery | hour | 1.6 | 1,450.00 | 2,320.00 |
| 0029 | Carriage of concrete by transit mixerCarriage of ready mixed concrete by rotatory transit mixerMachinery | cum km/ | 1,200 | 40.00 | 48,000.00 |
| 0009 | Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinery | cum | 120 | 250.00 | 30,000.00 |
- TOTAL
- 6,38,628.14
- Cost of each lot of 120 cum.
- 6,38,628.14
- Say
- 6,38,628.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 299. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.