Annexure for item 5.48.1, Providing M50 grade Reinforced Cement Concrete data for 120.00 cum

Item number
5.48X
Analysis basis
Details of cost for each lot of 120 cum.
Priced inputs
13
Derived rate
6,38,628.15 / each lot

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48X Annexure for item 5.48.1, Providing M50 grade Reinforced Cement Concrete data for 120.00 cum — is derived from 13 priced inputs for each lot and works out to ₹6,38,628.15 per each lot after water charges, GST, CPOH and cess. The full build-up is below.

  • Sub Analysis for use in Item no 5.48.1
  • RCC Grade M50
  • Unit = 1 cum
  • Taking output = 120 cum
  • MATERIALS :
  • LABOUR :
  • MACHINERY :
  • Distance = 10 km
  • Qty= 120.00 cum
  • Total = 120.00x 10= 1200
CodeInputUnitQuantityRate (INR)Amount (INR)
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne57.65,156.002,96,985.60
0982Coarse sand (zone III)Materialcum541,450.0078,300.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum64.81,425.0092,340.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum43.21,400.0060,480.00
7318Plasticizer / super plasticizerMaterialgram223.230.006,696.00
0128MateLabourday0.94816.00767.04
0123Mason 1st classMason 1st classLabourday3.5897.003,139.50
0114BeldarLabourday20736.0014,720.00
0066Batching and Mixing Plant @ 75 cum per hourMachineryhour1.62,700.004,320.00
0070Generator 100 KVA/125 KVAMachineryhour1.6350.00560.00
0052Front end loader 1 cum bucket capacity (incl POL)Machineryhour1.61,450.002,320.00
0029Carriage of concrete by transit mixerCarriage of ready mixed concrete by rotatory transit mixerMachinerycum km/1,20040.0048,000.00
0009Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinerycum120250.0030,000.00
TOTAL
6,38,628.14
Cost of each lot of 120 cum.
6,38,628.14
Say
6,38,628.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 299. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.