Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Annexure for items 5.48.3. Extra for using M 60 grade Self Compacting Reinforced cement concrete data for 120.00 cum

Item number
5.48Z
Analysis basis
Details of cost for each.
Priced inputs
14
Derived rate
7,62,842.05

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48Z Annexure for items 5.48.3. Extra for using M 60 grade Self Compacting Reinforced cement concrete data for 120.00 cum — is derived from 14 priced inputs and works out to ₹7,62,842.05 after water charges, GST, CPOH and cess. The full build-up is below.

  • Sub Analysis for use in Item no 5.48.3X
  • RCC Grade M60 self compacting concrete
  • Using Batching Plant, Transit Mixer and
  • Conrete Pump
  • Unit = 1 cum
  • Taking Output = 120 cum
  • MATERIALS :
  • LABOUR :
  • MACHINERY :
  • Distance = 10 km
  • Qty= 120.00 cum
  • Total = 120.00x 10= 1200
CodeInputUnitQuantityRate (INR)Amount (INR)
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne57.65,156.002,96,985.60
0982Coarse sand (zone III)Materialcum541,450.0078,300.00
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum64.81,425.0092,340.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum43.21,400.0060,480.00
7318Plasticizer / super plasticizerMaterialgram230.430.006,912.00
8953Micro SilicaMaterialkg5,04025.001,26,000.00
0128MateLabourday0.84816.00685.44
0123Mason 1st classMason 1st classLabourday3897.002,691.00
0114BeldarLabourday18736.0013,248.00
0066Batching and Mixing Plant @ 75 cum per hourMachineryhour1.62,700.004,320.00
0070Generator 100 KVA/125 KVAMachineryhour1.6350.00560.00
0052Front end loader 1 cum bucket capacity (incl POL)Machineryhour1.61,450.002,320.00
0029Carriage of concrete by transit mixerCarriage of ready mixed concrete by rotatory transit mixerMachinerycum km/1,20040.0048,000.00
0009Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinerycum120250.0030,000.00
TOTAL
7,62,842.04
Cost of each.
7,62,842.04
Say
7,62,842.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 300. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works