CPWD Analysis of Rates · Reinforced Cement Concrete
Annexure for items 5.48.3. Extra for using M 60 grade Self Compacting Reinforced cement concrete data for 120.00 cum
- Item number
- 5.48Z
- Analysis basis
- Details of cost for each.
- Priced inputs
- 14
- Derived rate
- ₹7,62,842.05
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.48Z — Annexure for items 5.48.3. Extra for using M 60 grade Self Compacting Reinforced cement concrete data for 120.00 cum — is derived from 14 priced inputs and works out to ₹7,62,842.05 after water charges, GST, CPOH and cess. The full build-up is below.
- Sub Analysis for use in Item no 5.48.3X
- RCC Grade M60 self compacting concrete
- Using Batching Plant, Transit Mixer and
- Conrete Pump
- Unit = 1 cum
- Taking Output = 120 cum
- MATERIALS :
- LABOUR :
- MACHINERY :
- Distance = 10 km
- Qty= 120.00 cum
- Total = 120.00x 10= 1200
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 57.6 | 5,156.00 | 2,96,985.60 |
| 0982 | Coarse sand (zone III)Material | cum | 54 | 1,450.00 | 78,300.00 |
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 64.8 | 1,425.00 | 92,340.00 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 43.2 | 1,400.00 | 60,480.00 |
| 7318 | Plasticizer / super plasticizerMaterial | gram | 230.4 | 30.00 | 6,912.00 |
| 8953 | Micro SilicaMaterial | kg | 5,040 | 25.00 | 1,26,000.00 |
| 0128 | MateLabour | day | 0.84 | 816.00 | 685.44 |
| 0123 | Mason 1st classMason 1st classLabour | day | 3 | 897.00 | 2,691.00 |
| 0114 | BeldarLabour | day | 18 | 736.00 | 13,248.00 |
| 0066 | Batching and Mixing Plant @ 75 cum per hourMachinery | hour | 1.6 | 2,700.00 | 4,320.00 |
| 0070 | Generator 100 KVA/125 KVAMachinery | hour | 1.6 | 350.00 | 560.00 |
| 0052 | Front end loader 1 cum bucket capacity (incl POL)Machinery | hour | 1.6 | 1,450.00 | 2,320.00 |
| 0029 | Carriage of concrete by transit mixerCarriage of ready mixed concrete by rotatory transit mixerMachinery | cum km/ | 1,200 | 40.00 | 48,000.00 |
| 0009 | Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinery | cum | 120 | 250.00 | 30,000.00 |
- TOTAL
- 7,62,842.04
- Cost of each.
- 7,62,842.04
- Say
- 7,62,842.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 300. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.