Skip to main content

Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal

Door frame 100 mmx 60 mm
Item number
5.47.2
Analysis basis
52 metre
Priced inputs
7
Derived rate
₹757.10/ METRE
D-01/RATE ANALYSISITEM 5.47.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.47.2 (Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal Door frame 100 mmx 60 mm) is derived from 7 priced inputs for 52 metre and works out to ₹757.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • frame)
ANALYSIS OF RATES · ITEM 5.47.2DETAILS OF COST FOR 52 METRE (10 NOS DOOR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRCC M-40 Rate as per Item No.5.33.1.4 of SH: RCCRate as per item 5.33.1.4cum0.319,957.653,086.87
OTHERExtra for scattered and smaller work @25 %——771.72
1005MATTwisted steel/ deformed barsTwisted steel/ deformed TMT bars Fe-500Dqtl0.3725,550.002,064.60
OTHER596 Bright finished or black enameled mild steel butt hinges 75x47x 1.70 mm10 nos663.00378.00
SUBCentring and shuttering Rate as per Item No.4.3.3 of SH: CONCRETE WORKRate as per item 4.3.3sqm11.4961.3010,958.82
SUBFixing Chowkhat Rate as per Item No.14.2.1 of SH: REPAIRS TO BUILDINGRate as per item 14.2.1each101,782.5517,825.50
9999MATSundriesL.S.1,006.72.272,285.21
BUILD-UP TO RATE
TOTAL
37,370.72
Add 1 % Water charges on “W-A-P-R”
+47.28
TOTAL
37,418.00
Add GST on “X-A-P-R” (multiplying factor 0.2127)
+1,015.66
TOTAL
38,433.66
Add 15% CPOH on “Y-A-P-R”
+868.61
TOTAL
39,302.27
Add Cess @ 1% on “Z-A-P-R”
+66.59
Cost of 52 metre
39,368.86
Cost of 1 metre
757.09
SAY
₹757.10
D-02/SOURCEPRINTED PAGE 296
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
296

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 296. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.