CPWD Analysis of Rates · Reinforced Cement Concrete

Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal

Door frame 100 mmx 60 mm

Item number
5.47.2
Analysis basis
Details of cost for 52 metre (10 Nos door
Priced inputs
7
Derived rate
757.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.47.2 Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal Door frame 100 mmx 60 mm — is derived from 7 priced inputs for 52 metre and works out to ₹757.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • frame)
CodeInputUnitQuantityRate (INR)Amount (INR)
RCC M-40 Rate as per Item No.5.33.1.4 of SH: RCCRate as per item 5.33.1.4Sub-analysiscum0.319,957.653,086.87
Extra for scattered and smaller work @25 %OtherNaNNaN771.72
1005Twisted steel/ deformed barsTwisted steel/ deformed TMT bars Fe-500DMaterialqtl0.3725,550.002,064.60
596 Bright finished or black enameled mild steel butt hinges 75x47x 1.70 mmOther10 nos663.00378.00
Centring and shuttering Rate as per Item No.4.3.3 of SH: CONCRETE WORKRate as per item 4.3.3Sub-analysissqm11.4961.3010,958.82
Fixing Chowkhat Rate as per Item No.14.2.1 of SH: REPAIRS TO BUILDINGRate as per item 14.2.1Sub-analysiseach101,782.5517,825.50
9999SundriesMaterialL.S.1,006.72.272,285.21
TOTAL
37,370.72
Add 1 % Water charges on “W-A-P-R”
47.28
TOTAL
37,418.00
Add GST on “X-A-P-R” (multiplying factor 0.2127)
1,015.66
TOTAL
38,433.66
Add 15% CPOH on “Y-A-P-R”
868.61
TOTAL
39,302.27
Add Cess @ 1% on “Z-A-P-R”
66.59
Cost of 52 metre
39,368.86
Cost of 1 metre
757.09
Say
757.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 296. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.