Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal

Door frame 125 mmx 60 mm
Item number
5.47.1
Analysis basis
52 metre
Priced inputs
7
Derived rate
₹814.85/ METRE
D-01/RATE ANALYSISITEM 5.47.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.47.1 (Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal Door frame 125 mmx 60 mm) is derived from 7 priced inputs for 52 metre and works out to ₹814.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • frame)
ANALYSIS OF RATES · ITEM 5.47.1DETAILS OF COST FOR 52 METRE (10 NOS DOOR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRCC M40 Rate as per Item No.5.33.1.4 of SH: REINFORCED CEMENT CONCRETERate as per item 5.33.1.4cum0.399,957.653,883.48
OTHERExtra for scatter and smaller work @25 % i.e. Px0.25——970.87
1005MATTwisted steel/ deformed barsTwisted steel/ deformed TMT bars Fe-500Dquintal0.4685,550.002,597.40
0596MATBright finished or black enameled mild steel butt hinges 75x47x1.70 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 75x47x 1.70 mm10 Nos663.00378.00
SUBCentering and shuttering Rate as per Item No.4.3.3 of SH: CONCRETE WORKRate as per item 4.3.3sqm12.7961.3012,208.51
SUBFixing chowkhat Rate as per Item No.14.2.1 of SH: REPAIRS TO BUILDINGSRate as per item 14.2.1each101,782.5517,825.50
9999MATSundriesL.S.1,006.72.272,285.21
BUILD-UP TO RATE
TOTAL
40,148.97
Add 1 % Water charges on “W-A-P-R”
+52.61
TOTAL
40,201.58
Add GST on “X-A-P-R” (multiplying factor 0.2127)
+1,130.12
TOTAL
41,331.70
Add 15% CPOH on “Y-A-P-R”
+966.50
TOTAL
42,298.20
Add Cess @ 1% on “Z-A-P-R”
+74.10
Cost of 52 metre
42,372.30
Cost of 1 metre
814.85
SAY
₹814.85
D-02/SOURCEPRINTED PAGE 295
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
295

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 295. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.