Providing and fixing of expansion joint system of approved make and manufactures for various roof locations as per approved drawings and direction of Engineer-In-Charge. The joints shall be of extruded aluminum base members with, self aligning and self centering arragement support plates as per ASTM B221-02. The system shall be such that it provides watertight roof to roof/roof to corner joint cover expansion control system that is capable of accommodating multidirectional seismic movement without stress to its components. System shall consist of metal profile that incorporates an universal aluminum base member designed to accommodate various project conditions and roof treatments. The cover plate shall be designed of width and thickness required to satisfy movement and loading requirements and secured to base members by utilizing manufacturer’s pre-engineered self-centering arrangement that freely rotates / moves in all directions. The Self centering arrangement shall exhibit circular sphere ends that lock and slide inside the corresponding aluminum extrusion cavity to allow freedom of movement and flexure in all directions including vertical displacement. The Joint System shall resists damage or deterioration from the impact of falling ice, exposure to UV, airborne contaminants and occasional foot traffic from maintenance personnel. Provision of Moisture Barrier Membrane in the Joint System to have water tight joint is mandatory requirement. (Material shall conform to ASTM 6063)

Roof Joint of 200 mm gap

Item number
5.46.3
Analysis basis
Details of Cost of 1 metre.
Priced inputs
6
Derived rate
7,927.60 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.46.3 Providing and fixing of expansion joint system of approved make and manufactures for various roof locations as per approved drawings and direction of Engineer-In-Charge. The joints shall be of extruded aluminum base members with, self aligning and self centering arragement support plates as per ASTM B221-02. The system shall be such that it provides watertight roof to roof/roof to corner joint cover expansion control system that is capable of accommodating multidirectional seismic movement without stress to its components. System shall consist of metal profile that incorporates an universal aluminum base member designed to accommodate various project conditions and roof treatments. The cover plate shall be designed of width and thickness required to satisfy movement and loading requirements and secured to base members by utilizing manufacturer’s pre-engineered self-centering arrangement that freely rotates / moves in all directions. The Self centering arrangement shall exhibit circular sphere ends that lock and slide inside the corresponding aluminum extrusion cavity to allow freedom of movement and flexure in all directions including vertical displacement. The Joint System shall resists damage or deterioration from the impact of falling ice, exposure to UV, airborne contaminants and occasional foot traffic from maintenance personnel. Provision of Moisture Barrier Membrane in the Joint System to have water tight joint is mandatory requirement. (Material shall conform to ASTM 6063) Roof Joint of 200 mm gap — is derived from 6 priced inputs and works out to ₹7,927.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIALS :
  • LABOUR :
CodeInputUnitQuantityRate (INR)Amount (INR)
2401Complete Roof Joint of 200 mmMaterialmetre14,284.004,284.00
2402Epoxy adhesiveMaterialkg4.75160.00760.00
9977CarriageMaterialL.S.124.92.27283.52
0102Blacksmith 1st classLabourday0.05897.0044.85
0123Mason 1st classMason 1st classLabourday0.1897.0089.70
0114BeldarLabourday0.15736.00110.40
TOTAL
5,572.47
Add 1 % Water charges on “W”
55.72
TOTAL
5,628.19
Add GST on “X” (multiplying factor 0.2127)
1,197.12
TOTAL
6,825.31
Add 15% CPOH on “Y”
1,023.80
TOTAL
7,849.11
Add Cess @ 1% on “Z”
78.49
Cost of 1 metre.
7,927.60
Say
7,927.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 294. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.