CPWD Analysis of Rates · Reinforced Cement Concrete
Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal
Door frame 85 mmx60 mm
- Item number
- 5.47.3
- Analysis basis
- Details of cost for 52 metre (10 Nos door
- Priced inputs
- 7
- Derived rate
- ₹727.30 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.47.3 — Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineerin-charge. The frame shall be measured in running metre correct to two places of decimal Door frame 85 mmx60 mm — is derived from 7 priced inputs for 52 metre and works out to ₹727.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- frame)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| RCC M40 Rate as per Item No.5.33.1.4 of SH: REINFORCED CEMENT CONCRETERate as per item 5.33.1.4Sub-analysis | cum | 0.27 | 9,957.65 | 2,688.57 | |
| Extra for scatter and smaller work @25 % i.e. Px0.25Other | NaN | NaN | 672.14 | ||
| 1005 | Twisted steel/ deformed barsTwisted steel/ deformed TMT bars Fe-500DMaterial | quintal | 0.324 | 5,550.00 | 1,798.20 |
| 0596 | Bright finished or black enameled mild steel butt hinges 75x47x1.70 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 75x47x 1.70 mmMaterial | 10 Nos | 6 | 63.00 | 378.00 |
| Centering and shuttering Rate as per Item No.4.3.3 of SH: CONCRETE WORKRate as per item 4.3.3Sub-analysis | sqm | 10.7 | 961.30 | 10,285.91 | |
| Fixing chowkhat Rate as per Item No.14.2.1 of SH: REPAIRS TO BUILDINGSRate as per item 14.2.1Sub-analysis | each | 10 | 1,782.55 | 17,825.50 | |
| 9999 | SundriesMaterial | L.S. | 1,006.7 | 2.27 | 2,285.21 |
- TOTAL
- 35,933.53
- Add 1 % Water charges on “W-A-P-R”
- 44.61
- TOTAL
- 35,978.14
- Add GST on “X-A-P-R” (multiplying factor 0.2127)
- 958.43
- TOTAL
- 36,936.57
- Add 15% CPOH on “Y-A-P-R”
- 819.67
- TOTAL
- 37,756.24
- Add Cess @ 1% on “Z-A-P-R”
- 62.84
- Cost of 52 metre
- 37,819.08
- Cost of 1 metre
- 727.29
- Say
- 727.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 296. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works