Supplying and applying pre tested and approved water based concrete curing compound to

concrete/ masonry surface, all as per manufacturer’s specification and direction of Engineerin-charge. Non pigmented wet curing compound
Item number
5.41.1
Analysis basis
10.00 sqm
Priced inputs
5
Derived rate
₹69.05/ SQM
D-01/RATE ANALYSISITEM 5.41.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.41.1 (Supplying and applying pre tested and approved water based concrete curing compound to concrete/ masonry surface, all as per manufacturer’s specification and direction of Engineerin-charge. Non pigmented wet curing compound) is derived from 5 priced inputs for 10.00 sqm and works out to ₹69.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • sqm/litre)
ANALYSIS OF RATES · ITEM 5.41.1DETAIL OF COST FOR 10.00 SQM (COVERING AREA 5
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0349MATCuring compoundlitre241.0082.00
9977MATCarriage of materialL.S.12.272.27
0131LABPainterday0.33816.00269.28
0114LABBeldarday0.17736.00125.12
9999MATSundries, BrushL.S.32.276.81
BUILD-UP TO RATE
TOTAL
485.48
Add 1 % Water charges on “W”
+4.85
TOTAL
490.33
Add GST on “X” (multiplying factor 0.2127)
+104.29
TOTAL
594.62
Add 15% CPOH on “Y”
+89.19
TOTAL
683.81
Add Cess @ 1% on “Z”
+6.84
Cost of 10 sqm
690.65
Cost of 1 sqm
69.07
SAY
₹69.05
D-02/SOURCEPRINTED PAGE 287
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
287

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 287. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.