Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof
- Item number
- 5.38
- Analysis basis
- 1 cum
- Priced inputs
- 1
- Derived rate
- ₹355.65/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.38 (Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof) is derived from 1 priced inputs for 1 cum and works out to ₹355.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0009 | MACH | Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc. | cum | 1 | 250.00 | 250.00 |
- TOTAL
- 250.00
- Add 1 % Water charges on “W”
- +2.50
- TOTAL
- 252.50
- Add GST on “X” (multiplying factor 0.2127)
- +53.71
- TOTAL
- 306.21
- Add 15% CPOH on “Y”
- +45.93
- TOTAL
- 352.14
- Add Cess @ 1% on “Z”
- +3.52
- Cost for 1 cum
- 355.66
- SAY
- ₹355.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 286
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 286. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.