Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof

Item number
5.38
Analysis basis
1 cum
Priced inputs
1
Derived rate
₹355.65/ CUM
D-01/RATE ANALYSISITEM 5.38

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.38 (Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof) is derived from 1 priced inputs for 1 cum and works out to ₹355.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 5.38DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0009MACHPumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.cum1250.00250.00
BUILD-UP TO RATE
TOTAL
250.00
Add 1 % Water charges on “W”
+2.50
TOTAL
252.50
Add GST on “X” (multiplying factor 0.2127)
+53.71
TOTAL
306.21
Add 15% CPOH on “Y”
+45.93
TOTAL
352.14
Add Cess @ 1% on “Z”
+3.52
Cost for 1 cum
355.66
SAY
₹355.65
D-02/SOURCEPRINTED PAGE 286
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
286

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 286. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.