Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof

Item number
5.38
Analysis basis
Details of cost for 1 cum
Priced inputs
1
Derived rate
355.65 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.38 Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof — is derived from 1 priced inputs for 1 cum and works out to ₹355.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0009Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinerycum1250.00250.00
TOTAL
250.00
Add 1 % Water charges on “W”
2.50
TOTAL
252.50
Add GST on “X” (multiplying factor 0.2127)
53.71
TOTAL
306.21
Add 15% CPOH on “Y”
45.93
TOTAL
352.14
Add Cess @ 1% on “Z”
3.52
Cost for 1 cum
355.66
Say
355.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 286. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works