CPWD Analysis of Rates · Reinforced Cement Concrete
Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof
- Item number
- 5.38
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 1
- Derived rate
- ₹355.65 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.38 — Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof — is derived from 1 priced inputs for 1 cum and works out to ₹355.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0009 | Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinery | cum | 1 | 250.00 | 250.00 |
- TOTAL
- 250.00
- Add 1 % Water charges on “W”
- 2.50
- TOTAL
- 252.50
- Add GST on “X” (multiplying factor 0.2127)
- 53.71
- TOTAL
- 306.21
- Add 15% CPOH on “Y”
- 45.93
- TOTAL
- 352.14
- Add Cess @ 1% on “Z”
- 3.52
- Cost for 1 cum
- 355.66
- Say
- 355.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 286. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works