Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular as per design and shape for floors and roofs in 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 10 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but excluding the cost of reinforcement

Item number
5.36A
Analysis basis
1.38 cum
Priced inputs
8
Derived rate
₹32,847.95/ CUM
D-01/RATE ANALYSISITEM 5.36A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.36A (Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular as per design and shape for floors and roofs in 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 10 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but excluding the cost of reinforcement) is derived from 8 priced inputs for 1.38 cum and works out to ₹32,847.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a waffle 0.9 x 0.9 x 0.3m
  • Total area covered 4.548 x 3.636 = 16.54
  • sqm.
  • Cement concrete in 1unit
  • Top 0.8 x 0.8 x 0.035 = 0.0224
  • sides 2(0.8 x 0.265 x 0.0325) = 0.01382
  • (0.735 x 0.265 x 0.0325) = 0.0127
  • Total = 0.0489
  • Flange 4 x 0.85 x 0.05 x 0.035 = 0.0060
  • Total = 0.0549
  • Total = 0.069 cum.
  • Quantity for 20 such units = 1.38 cum
  • (i) Shuttering and centring
  • Face in contact
  • 4 x 0.8 x 0.265 = 0.848
  • Inner 4 x 0.735 x 0.265 = 0.779
  • Top (inside) 1 x 0.735 x 0.735 = 0.540
  • Flange 4 x 0.9 x 0.035 = 0.126
  • Total = 2.293 sqm.
  • Quantity 20 such units 45.86 sqm
  • Hooks for lifting
  • 2 x 1.5 = 3.0 m
  • 4 x 0.01 = 0.04 m = 3.04 m @ 3 kg per m
  • 9.12 kg or 0.009 t
  • (ii) 10 mm dia. Bolts 60 mm long with nuts
  • and washers 2 x 2 = 4Nos
  • (iv) Transportation and erection labour for
  • 20 units
  • (v) Cost of pointing flush or deep ruled in
  • cement mortar 1:2 (1 Cement : 2 fine sand)
  • Add for Fillets 25% = 0.0137
ANALYSIS OF RATES · ITEM 5.36ADETAILS OF COST FOR 1.38 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 5.2.2A of SH: Reinforced cement concrete workRate as per item 5.2.2Acum1.3810,682.1514,741.37
SUBRate as per Item Number 5.9.15 of SH: Reinforced cement concrete workRate as per item 5.9.15sqm45.86392.1517,984.00
SUBRate as per Item Number 10.2 of SH: Steel workRate as per item 10.2kg9133.701,203.30
9999MATIncluding carriage of boltsL.S.132.2729.51
9999MATSundriesL.S.79.952.27181.49
0126LABMason (for ornamental stone work) 1 st classMason (for ornamental stone work) 1st classday1897.00897.00
0114LABBeldarday6736.004,416.00
SUBRate as per Item Number 13.35.1 of SH: FinishingRate as per item 13.35.1sqm16.54214.203,542.87
BUILD-UP TO RATE
Total
42,995.54
Add 1 % Water charges on “W-A”
+55.24
TOTAL
43,050.78
Add GST on “X-A” (multiplying factor 0.2127)
+1,186.70
TOTAL
44,237.48
Add 15% CPOH on “Y-A”
+1,014.89
TOTAL
45,252.37
Add Cess @ 1% on “Z-A”
+77.81
Cost of 1.38 cum
45,330.18
Cost of 1 cum
32,847.96
SAY
₹32,847.95
D-02/SOURCEPRINTED PAGE 285
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
285

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 285. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.