CPWD Analysis of Rates · Reinforced Cement Concrete
Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular as per design and shape for floors and roofs in 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 10 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but excluding the cost of reinforcement
- Item number
- 5.36A
- Analysis basis
- Details of cost for 1.38 cum
- Priced inputs
- 8
- Derived rate
- ₹32,847.95 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.36A — Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular as per design and shape for floors and roofs in 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 10 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but excluding the cost of reinforcement — is derived from 8 priced inputs for 1.38 cum and works out to ₹32,847.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Consider a waffle 0.9 x 0.9 x 0.3m
- Total area covered 4.548 x 3.636 = 16.54
- sqm.
- Cement concrete in 1unit
- Top 0.8 x 0.8 x 0.035 = 0.0224
- sides 2(0.8 x 0.265 x 0.0325) = 0.01382
- (0.735 x 0.265 x 0.0325) = 0.0127
- Total = 0.0489
- Flange 4 x 0.85 x 0.05 x 0.035 = 0.0060
- Total = 0.0549
- Total = 0.069 cum.
- Quantity for 20 such units = 1.38 cum
- (i) Shuttering and centring
- Face in contact
- 4 x 0.8 x 0.265 = 0.848
- Inner 4 x 0.735 x 0.265 = 0.779
- Top (inside) 1 x 0.735 x 0.735 = 0.540
- Flange 4 x 0.9 x 0.035 = 0.126
- Total = 2.293 sqm.
- Quantity 20 such units 45.86 sqm
- Hooks for lifting
- 2 x 1.5 = 3.0 m
- 4 x 0.01 = 0.04 m = 3.04 m @ 3 kg per m
- 9.12 kg or 0.009 t
- (ii) 10 mm dia. Bolts 60 mm long with nuts
- and washers 2 x 2 = 4Nos
- (iv) Transportation and erection labour for
- 20 units
- (v) Cost of pointing flush or deep ruled in
- cement mortar 1:2 (1 Cement : 2 fine sand)
- Add for Fillets 25% = 0.0137
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 5.2.2A of SH: Reinforced cement concrete workRate as per item 5.2.2ASub-analysis | cum | 1.38 | 10,682.15 | 14,741.37 | |
| Rate as per Item Number 5.9.15 of SH: Reinforced cement concrete workRate as per item 5.9.15Sub-analysis | sqm | 45.86 | 392.15 | 17,984.00 | |
| Rate as per Item Number 10.2 of SH: Steel workRate as per item 10.2Sub-analysis | kg | 9 | 133.70 | 1,203.30 | |
| 9999 | Including carriage of boltsMaterial | L.S. | 13 | 2.27 | 29.51 |
| 9999 | SundriesMaterial | L.S. | 79.95 | 2.27 | 181.49 |
| 0126 | Mason (for ornamental stone work) 1 st classMason (for ornamental stone work) 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0114 | BeldarLabour | day | 6 | 736.00 | 4,416.00 |
| Rate as per Item Number 13.35.1 of SH: FinishingRate as per item 13.35.1Sub-analysis | sqm | 16.54 | 214.20 | 3,542.87 |
- Total
- 42,995.54
- Add 1 % Water charges on “W-A”
- 55.24
- TOTAL
- 43,050.78
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,186.70
- TOTAL
- 44,237.48
- Add 15% CPOH on “Y-A”
- 1,014.89
- TOTAL
- 45,252.37
- Add Cess @ 1% on “Z-A”
- 77.81
- Cost of 1.38 cum
- 45,330.18
- Cost of 1 cum
- 32,847.96
- Say
- 32,847.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 285. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.