Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular as per design and shape for floors and roofs in 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 10 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but excluding the cost of reinforcement

Item number
5.36A
Analysis basis
Details of cost for 1.38 cum
Priced inputs
8
Derived rate
32,847.95 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.36A Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular as per design and shape for floors and roofs in 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 10 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%), including flush or deep ruled pointing at joints in cement mortar 1:2 (1 cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but excluding the cost of reinforcement — is derived from 8 priced inputs for 1.38 cum and works out to ₹32,847.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider a waffle 0.9 x 0.9 x 0.3m
  • Total area covered 4.548 x 3.636 = 16.54
  • sqm.
  • Cement concrete in 1unit
  • Top 0.8 x 0.8 x 0.035 = 0.0224
  • sides 2(0.8 x 0.265 x 0.0325) = 0.01382
  • (0.735 x 0.265 x 0.0325) = 0.0127
  • Total = 0.0489
  • Flange 4 x 0.85 x 0.05 x 0.035 = 0.0060
  • Total = 0.0549
  • Total = 0.069 cum.
  • Quantity for 20 such units = 1.38 cum
  • (i) Shuttering and centring
  • Face in contact
  • 4 x 0.8 x 0.265 = 0.848
  • Inner 4 x 0.735 x 0.265 = 0.779
  • Top (inside) 1 x 0.735 x 0.735 = 0.540
  • Flange 4 x 0.9 x 0.035 = 0.126
  • Total = 2.293 sqm.
  • Quantity 20 such units 45.86 sqm
  • Hooks for lifting
  • 2 x 1.5 = 3.0 m
  • 4 x 0.01 = 0.04 m = 3.04 m @ 3 kg per m
  • 9.12 kg or 0.009 t
  • (ii) 10 mm dia. Bolts 60 mm long with nuts
  • and washers 2 x 2 = 4Nos
  • (iv) Transportation and erection labour for
  • 20 units
  • (v) Cost of pointing flush or deep ruled in
  • cement mortar 1:2 (1 Cement : 2 fine sand)
  • Add for Fillets 25% = 0.0137
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 5.2.2A of SH: Reinforced cement concrete workRate as per item 5.2.2ASub-analysiscum1.3810,682.1514,741.37
Rate as per Item Number 5.9.15 of SH: Reinforced cement concrete workRate as per item 5.9.15Sub-analysissqm45.86392.1517,984.00
Rate as per Item Number 10.2 of SH: Steel workRate as per item 10.2Sub-analysiskg9133.701,203.30
9999Including carriage of boltsMaterialL.S.132.2729.51
9999SundriesMaterialL.S.79.952.27181.49
0126Mason (for ornamental stone work) 1 st classMason (for ornamental stone work) 1st classLabourday1897.00897.00
0114BeldarLabourday6736.004,416.00
Rate as per Item Number 13.35.1 of SH: FinishingRate as per item 13.35.1Sub-analysissqm16.54214.203,542.87
Total
42,995.54
Add 1 % Water charges on “W-A”
55.24
TOTAL
43,050.78
Add GST on “X-A” (multiplying factor 0.2127)
1,186.70
TOTAL
44,237.48
Add 15% CPOH on “Y-A”
1,014.89
TOTAL
45,252.37
Add Cess @ 1% on “Z-A”
77.81
Cost of 1.38 cum
45,330.18
Cost of 1 cum
32,847.96
Say
32,847.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 285. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works